All American Environmental, LLC v. 58 Old Grays Bridge, LLC

CourtDistrict Court, D. Connecticut
DecidedSeptember 10, 2021
Docket3:20-cv-01295
StatusUnknown

This text of All American Environmental, LLC v. 58 Old Grays Bridge, LLC (All American Environmental, LLC v. 58 Old Grays Bridge, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All American Environmental, LLC v. 58 Old Grays Bridge, LLC, (D. Conn. 2021).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF CONNECTICUT

ALL AMERICAN ENVIRONMENTAL, LLC, Plaintiff, No. 3:20-cv-01295 (MPS)

v.

58 OLD GRAYS BRIDGE, LLC, Defendant.

RULING ON MOTION TO DISMISS Plaintiff All American Environmental, LLC (“All American”) brings this action against 58 Old Grays Bridge, LLC (“58 Old Grays”) for damages based on claims of breach of contract, breach of the implied covenant of good faith and fair dealing, unjust enrichment, intentional misrepresentation, and violation of the Connecticut Unfair Trade Practice Act (“CUTPA”). 58 Old Grays now moves to dismiss All American’s suit for failure to state a claim upon which relief can be granted under Fed. R. Civ. P. 12(b)(6). (ECF No. 14). For the reasons discussed below, 58 Old Grays’s motion is DENIED. I. BACKGROUND The following facts are derived from the Plaintiff’s complaint (ECF No. 1) and are assumed to be true for the purposes of this motion. On or about December 6, 2016 All American entered into an agreement with 58 Old Grays, according to which All American would provide labor and materials for an environmental remediation project (the “Project”) located at 58 Old Grays Bridge Road in Brookfield, CT (the “Property”). (Id. at 2 ¶ 11.) The parties set forth the details of this agreement in a contract dated December 6 (the “Contract”). (Id.) That Contract provided that the scope of work to be performed on the Project by All American was removal for off-site disposal of all soil that exhibited polychlorinated bi-phenol (“PCB”) levels in excess of 10 mg/kg. (Id. at 3 ¶ 12.) The December 2016 Contract also set forth a schedule of values listing the items of work to be performed by All American alongside their corresponding prices. (Id. at 3 ¶ 13.) It provided that

the cost of the Project, based on this schedule of values, was $1,216,400.00. (Id.) It also provided that this price did not include “scope of work to be done on any items other th[an] described herein.” (Id. at 3 ¶ 14.) The parties also executed an Addendum to the Contract in which they agreed that the scope of work set forth in the Contract would be done on a “capped fee” basis not to exceed $1,216,400.00. (Id. at 4 ¶ 20.) The schedule of values set forth in the Contract was based on a 2017 work plan approved by the Connecticut Department of Energy & Environmental Protection (“DEEP”) dated April 5, 2017 (“2017 Work Plan”).1 (Id. at 3 ¶ 15.) The 2017 Work Plan states that “58 Old Grays Bridge LLC proposes to remediate all soils beneath the building to PCB cleanup criterion of 10 mg/kg.” (Id. at 3 ¶ 16.) It also identifies 1,751 square feet of surface area that would need to be

excavated in order the complete the remediation. (Id. at 3 ¶ 17.) The Work Plan also states that—upon reaching the cleanup target of 10 mg/kg—58 Old Grays would seek and obtain an Environmental Land Use Restriction (“ELUR”) for the property. (Id. at 3 ¶ 18.) All American relied on the 2017 Work Plan to estimate that it would need to excavate 2,000 tons of soil to reach the target levels of 10 mg/kg. (Id. at 4 ¶ 19.) On or about February 28, 2017, All American began work on the Project. (Id. at 4 ¶ 21.) All American identified thirteen interior areas and six exterior areas of contamination to be excavated and remediated in order to complete the Project. (Id. at 4 ¶ 22.) All American

1 It is not clear to the Court how the contents of an agreement dated December 6, 2016 could be based upon a work plan dated April 5, 2017, but this allegation is not critical to the Court’s ruling on this motion. contracted with Licensed Site Remediation Professional (“LSRP”) Ralph Klass to complete the site remediation. (Id. at 4 ¶ 23.) Shortly after the Project began, 58 Old Grays communicated to All American and LSRP Klass that it wanted to remediate all soils on the Property to a PCB cleanup criterion of less than

1 mg/kg, rather than the 10 mg/kg level agreed to in the December 2016 Contract, so that it would not need to seek a ELUR. (Id. at 4 ¶ 24.) All American agreed to perform the additional work on the condition that 58 Old Grays would compensate it for all work performed outside the scope of the Contract. (Id. at 4 ¶ 25.) 58 Old Grays repeatedly assured All American that it would pay for the extra work because it wanted to get the Property fully clean. (Id. at 4 ¶ 26.) 58 Old Grays also communicated to the DEEP, through mandated filings LSRP Klass submitted to the DEEP, that it wanted to bring the PCB levels to less than 1 mg/kg. (Id. at 4 ¶ 27.) LSRP Klass filed a status report with the DEEP on June 27, 2018 on behalf of 58 Old Grays in which he stated that 58 Old Grays was “committed to continue soil excavation with a goal of obtaining compliance with the [PCB criteria of 1.0 mg/kg].” (Id. at 5 ¶ 28.) He filed a second status report

on August 8, 2019, which stated that “[a]t the present time Mr. Mehmetaj has set the project cleanup target criteria for site soil remediation at the [level] of 1.0 mg/Kg.” (Id. at 5 ¶ 29.) (Arif Mehmetaj is one of the members of 58 Old Grays Bridge, LLC.) At 58 Old Grays’s request, All American performed excavations and soil remediation outside the scope of the Contract in an attempt to bring the PCB levels on the Property below 1 mg/kg. (Id. at 5 ¶ 30.) In addition, as All American performed work on the Project, it discovered that the soil contamination was far more extensive than 58 Old Grays had indicated. (Id. at 5 ¶ 31.) As a result, costs associated with the Project increased “exponentially” as it progressed. (Id.) As of August 8, 2019, All American had remediated 3 of the 6 exterior areas to the 10 mg/kg level agreed to in the Contract. (Id. at 5 ¶ 32.) As of December 5, 2019, All American had remediated 10 of the 13 interior areas to the 10 mg/kg level agreed to in the Contract. (Id. at 5 ¶ 32.) 58 Old Grays instructed All American to continue excavating and testing areas which

had already reached the 10 mg/kg threshold in order to reach the new goal of PCB levels below 1 mg/kg. (Id. at 5 ¶ 34.) Additional sampling and excavations must still be performed in order to achieve PCB levels less than 1 mg/kg throughout the property. (Id. at 5 ¶ 35.) As of September 2, 2020, All American had excavated 4,446 square feet, over two and a half times the 1,751 square feet agreed to by the parties in the Contract, and 2,421 tons of soil, 421 tons more than the parties agreed to in the Contract. (Id. at 5 ¶ 36-37.) All American has been unable to complete portions of the Project, such as the installation of a concrete cap, because 58 Old Grays required that excavations continue in order to bring the PCB levels to less than 1.0 mg/kg. (Id. at 5 ¶ 38.) In the Contract, the parties agreed that 58 Old Grays would make progress payments commensurate with the amount of work performed by All American. (Id. at 6 ¶ 39.) From about

December 16, 2016 through October 1, 2018, 58 Old Grays made payments totaling $670,000.00. (Id. at 6 ¶ 40.) From October 1, 2018 through July 30, 2019, 58 Old Grays made only two payments—one for $20,000.00 on May 31, 2019 and one for $80,000.00 on July 30, 2019. (Id.at 6 ¶ 41.) All American continued to perform work at 58 Old Grays’s direction until February 26, 2020, at which point it discontinued performance due to 58 Old Grays’s refusal to make progress payments. (Id. at 6 ¶ 42.) 58 Old Grays has made payments totaling $770,000.00. (Id. at 6 ¶ 43.) The total Contract price is $1,216,400.00. (Id. at 3 ¶ 13.) All American has performed work in the amount of $1,472,235.97 (approximately 121% of the Contract price). (Id. at 6 ¶ 44.) In addition, All American continues to be charged monthly fees while the contaminated soil sits on the Property. (Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Landry v. Spitz
925 A.2d 334 (Connecticut Appellate Court, 2007)
Scott v. Town of Monroe
306 F. Supp. 2d 191 (D. Connecticut, 2004)
Nwachukwu v. Liberty Bank
257 F. Supp. 3d 280 (D. Connecticut, 2017)
Hartford Whalers Hockey Club v. Uniroyal Goodrich Tire Co.
649 A.2d 518 (Supreme Court of Connecticut, 1994)
Macomber v. Travelers Property & Casualty Corp.
804 A.2d 180 (Supreme Court of Connecticut, 2002)
De La Concha of Hartford, Inc. v. Aetna Life Insurance
849 A.2d 382 (Supreme Court of Connecticut, 2004)
Vertex, Inc. v. City of Waterbury
898 A.2d 178 (Supreme Court of Connecticut, 2006)
Goel v. Bunge, Ltd.
820 F.3d 554 (Second Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
All American Environmental, LLC v. 58 Old Grays Bridge, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-american-environmental-llc-v-58-old-grays-bridge-llc-ctd-2021.