Aljaf Associates Ltd. Partnership v. Federal Deposit Insurance

879 F. Supp. 515, 1995 U.S. Dist. LEXIS 3785
CourtDistrict Court, E.D. Pennsylvania
DecidedMarch 27, 1995
DocketCiv. A. 95-146
StatusPublished
Cited by5 cases

This text of 879 F. Supp. 515 (Aljaf Associates Ltd. Partnership v. Federal Deposit Insurance) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aljaf Associates Ltd. Partnership v. Federal Deposit Insurance, 879 F. Supp. 515, 1995 U.S. Dist. LEXIS 3785 (E.D. Pa. 1995).

Opinion

MEMORANDUM

BARTLE, District Judge.

Plaintiff, Aljaf Associates Limited Partnership (“Aljaf’), alleges that its former tenant, Meritor Savings Bank (“Meritor”), failed to maintain and repair the building it rented from Aljaf as required by the sublease agreement between them. The Federal Deposit Insurance Corporation (“FDIC”) was appointed Meritor’s receiver pursuant to 12 U.S.C. § 1821(c)(3)(A) prior to the institution of this lawsuit. This court has jurisdiction of this matter pursuant to 12 U.S.C. § 1821(d)(6) and 28 U.S.C. § 1332.

Aljafs complaint alleges, among other things, that Meritor committed fraud by falsely certifying that it was in compliance with the maintenance provisions of the sublease. The FDIC has moved for summary judgment on plaintiffs fraud claim. It contends that Aljaf failed to exhaust the mandatory administrative remedy set forth in the Financial Institutions Reform, Recovery and Enforcement Act of 1989 (“FIRREA”), at 12 U.S.C. § 1821(d), before instituting suit on this claim. -

Although the FDIC has denominated its motion as a motion for summary judgment, its sole argument is that this court lacks subject matter jurisdiction over plaintiffs fraud claim. A motion predicated on lack of subject matter jurisdiction is properly brought under Rule 12(b)(1) of the Federal Rules of Civil Procedure. A motion to dismiss for lack of subject matter jurisdiction may be made at any time. See Fed.R.Civ.Proc. 12(h)(3); 2A Moore’s Federal Practice ¶ 12.07. This court will therefore consider defendant’s motion as one brought pursuant to Rule 12(b)(1) of the Federal Rules of Civil Procedure.

Section 1821(d)(13)(D) of FIRREA specifies that:

Except as otherwise provided in this subsection, no court shall have jurisdiction over—
(i) any claim or action for payment from, or any action seeking a determination of rights with respect to, the assets of any depository institution for which the [FDIC] has been appointed receiver, including assets which the [FDIC] may acquire from itself as such receiver; or
(ii) any claim relating to any act or omission of such institution or the [FDIC] as receiver.

12 U.S.C. § 1821(d)(13)(D). Section 1821(d)(6) provides an exception to the jurisdictional bar of § 1821(d)(13)(D) for “claims which have been properly submitted through the administrative claims procedure.” National Union Fire Ins. Co. v. City Savings, F.S.B., 28 F.3d 376, 385 (3d Cir.1994).

*517 The Court of Appeals for the Third Circuit has held that “FIRREA’s claims procedure in section 1821(d) is exclusive. Congress expressly withdrew jurisdiction from all courts over any claim to a failed bank’s assets that are made outside the procedure set forth in section 1821.” FDIC v. Shain, Schaffer & Rafanello, 944 F.2d 129, 132 (3d Cir.1991). Accordingly, this court must determine whether Aljaf complied with the requirements of § 1821(d) with regard to its fraud claim. If not, this court lacks subject matter jurisdiction over it.

On January 25, 1993, plaintiff sent the FDIC a letter which described Aljafs claim as being based on:

(i) all defaults under the [sublease], (ii) any waste that has occurred with respect to the Premises, (iii) any failure to perform obligations under the [sublease], and (iv) any consequential loss, cost, expense or liability to [Aljaf] as a result of any default or nonpayment under the [sublease].

In this letter, Aljaf informed the FDIC that it did not “maintain any day-to-day functions” pertaining to building maintenance, and requested “certification” from the FDIC that “all repair and maintenance of the Premises ha[d] been and will continue to be provided.”

On or about March 18, 1993, Aljaf submitted a formal Proof of Claim to the FDIC. In this Proof of Claim, Aljaf asserted that Meritor had breached the following obligations:

1. The obligation to pay all rent required pursuant to the terms of the Sublease
2. The obligation to maintain and repair the Premises.
3. The obligation to comply and cause the Premises to comply with all federal, state and local laws, ordinances, regulations, rules, orders and determinations applicable to the Premises or the ownership, operation, use or possession, thereof.
4. The obligation to pay all taxes, assessments, levies, fees, rents and charges assessed against or which arise with respect to the Premises.
5. The obligation to maintain insurance as required by the Sublease.
6. The obligation to surrender the Premises in good condition and repair.
7. The obligation to indemnify [Aljaf] and its partners from and against claims

Defendant contends that these documents fail to set forth any claim of fraud.

Aljaf concedes that it never submitted a claim to the FDIC which was specifically denominated as a fraud claim. Nevertheless, Aljaf contends that its letter of January 25, 1993 and its formal Proof of Claim sufficiently notified the FDIC of the “nature” of its claims. Plaintiff argues that because it “did not purport to state or limit its legal theories” in its administrative claim, it would be “patently unreasonable” for the FDIC not to have known that plaintiff was asserting a claim of fraud.

The District Court for the Northern District of Illinois considered a similar argument in Brown Leasing Co. v. FDIC, 833 F.Supp. 672 (N.D.Ill.1993), aff'd sub nom Brown Leasing Co. v. Cosmopolitan Bancorp, 42 F.3d 1112 (7th Cir.1994). There, the plaintiff filed suit requesting a determination of the rights and responsibilities of the parties to a participation agreement. Id. at 674-75. When the defendant entered receivership, plaintiff pursued an administrative claim alleging the same facts and legal theories. Id. After exhaustion of the administrative procedure for these claims, the plaintiff amended its complaint to add claims for conversion and breach of contract. The Brown Leasing

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Firstier Bank v. Federal Deposit Insurance
935 F. Supp. 2d 1109 (D. Colorado, 2013)
Westberg v. Federal Deposit Insurance Corporation
926 F. Supp. 2d 61 (District of Columbia, 2013)
Bhc Interim Funding II, L.P. v. Federal Deposit Insurance Corporation
851 F. Supp. 2d 131 (District of Columbia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
879 F. Supp. 515, 1995 U.S. Dist. LEXIS 3785, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aljaf-associates-ltd-partnership-v-federal-deposit-insurance-paed-1995.