Algonquin Gas Transmission Company v. Federal Power Commission, Bay State Gas Company, Intervenor(two Cases)

534 F.2d 952, 175 U.S. App. D.C. 215
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 29, 1976
Docket75-1460, 76-1043
StatusPublished
Cited by16 cases

This text of 534 F.2d 952 (Algonquin Gas Transmission Company v. Federal Power Commission, Bay State Gas Company, Intervenor(two Cases)) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Algonquin Gas Transmission Company v. Federal Power Commission, Bay State Gas Company, Intervenor(two Cases), 534 F.2d 952, 175 U.S. App. D.C. 215 (D.C. Cir. 1976).

Opinion

Opinion for the Court filed by Circuit Judge LEVENTHAL.

LEVENTHAL, Circuit Judge:

This is a consolidated appeal from two temporary certificates 1 issued by the FPC to Algonquin, governing excess production of synthetic gas from a plant certified in Opinion No. 637, 48 FPC 1216 (1972). 2 The record, briefs and argument leave us uncertain as to the nature of the certificates, and identification of precise objections of petitioner and responses of the Commission. We have nevertheless become convinced that in the interest of justice 3 there may be some need for prompt consideration of relief to Algonquin. We therefore indicate what we consider the fundamental principles of law applicable to the issues raised in these appeals, and remand the record to the Commission for consideration in light of those principles.

Factual Background. In Opinion No. 637 (Dec. 1972) the Commission issued a § 7 4 certificate of public convenience and necessity to Algonquin authorizing it to sell up to 120,000 Mcf per day of synthetic natural gas, this to be mixed with natural gas, to its existing wholesale customers. Initially, Algonquin was authorized to provide annual service from October 16 through April 5 5 to its regular wholesale customers who at that time, had contracted for only 57,536 Mcf synthetic gas per day. The FPC opinion provided that service agreements to sell additional synthetic gas up to the 120,000 Mcf/d design approval could be submitted to the Commission under the same rate schedule governing the original wholesale customers (Rate Schedule SNG-1). That rate schedule was designed to assure that the cost of the synthetic natural gas service would be recovered only from those customers actually receiving that service. The Commission also adopted a “protective condition” whose interpretation and application have been the subject of continuing controversy in the instant and other proceedings. Condition 6(iv) (48 FPC at 1252) provides:

“notwithstanding the provisions of any rate schedule or applicable service agreement, said applicant shall not, without prior Commission approval, file any rate schedule providing for any increase in rates based in any part, directly or indirectly, upon any fixed unit costs calculated upon the basis of a total volume of production of synthetic gas by the aforesaid reforming plant, during any period from October 16 through April 15 in any year, less than the equivalent of 151 days production at the rate of 120,000 Mcf/d.”

The Commission has interpreted that condition as requiring that any future rate increase be based upon the full design capacity of the synthetic natural gas plant (120,000 Mcf per day), and not upon the level of operation actually achieved. The rate schedule carries out that condition by a *955 demand component that is calculated by apportioning distribution of the plant’s fixed costs on the assumption of full design capacity production. Algonquin has apparently not, however, been able to achieve full capacity production daily; the practical effect of condition 6(iv) as applied has th.us been to require Algonquin to absorb substantial fixed costs.

The temporary certificates involved in this appeal were issued to permit sale of excess volumes of synthetic natural gas for the succeeding service periods of Nov. 1, 1974-April 15,1975, and October 16,1975 to April 15, 1976. In each case Algonquin contracted to sell gas to its new customers on the assumption it would produce gas at full design capacity, although it could not deliver in reality. In the first certificate, the Commission required that Algonquin curtail its new customers first whenever full production could not be achieved, and Algonquin appeals from that condition, requesting instead pro rata curtailment of all its customers. In the second certificate, the Commission retained the curtailment requirement of the first certificate, and also required that the demand charge of the rate schedule covering fixed costs be applicable to the new customers “only on those days when excess gas is tendered, and only to those volumes tendered.” Algonquin challenges both those conditions here.

In addition to the instant proceedings, the issues raised in this case were also being considered in a § 4 rate 6 tariff proceeding. The Commission has required that the § 4 proceeding be bound, however, by condition 6(iv) of the original certificate, and that therefore Algonquin cannot file for a rate increase justified by failure to produce at full design capacity. 7 Also in progress before an administrative law judge is a proceeding re-evaluating the terms of the original § 7 certificate.

Discussion. In this case, the Commission has apparently departed from its existing, and approved, practice of using the § 7 certification requirement as a “holding operation on initial rates.” Consumer Federation of America v. FPC, 169 U.S.App.D.C. 116, 125, 515 F.2d 347, 356 (1975). Cert. denied 423 U.S. 906, 96 S.Ct. 208, 46 L.Ed.2d 136 (1975). Instead, the Commission seeks to hold Algonquin to a rate condition established before practical building and operating experience with a new technology could be accumulated and evaluated. The Supreme Court in Atlantic Refining Co. v. Public Service Comm’n (CATCO), 360 U.S. 378, 392, 79 S.Ct. 1246, 1255, 3 L.Ed.2d 1312, 1321 8 (1959) recognized the appropriateness of putting rate conditions into § 7 certificates to protect consumer interests, but with the express purpose of furthering the Act’s objectives as a whole by using those rate conditions “to hold the line awaiting adjudication of a just and reasonable rate.” 9 By viewing the § 7 rate condition as rigid, binding on the § 4 proceeding, and modifiable only prospectively, the Commission has preempted the very § 4 proceeding that the Supreme Court in CATCO anticipated as providing the appropriate forum for final resolution of the public interest in just and reasonable rates.

*956 In contradiction to Algonquin’s assertions here, 10 we have no doubt that the Commission meant to establish a rate condition governing Algonquin’s synthetic natural gas production in the original certificate. However, in applying that rate condition to automatically limit the terms of the temporary certificates at issue here, the Commission failed to give due consideration to either the precise terms of that condition or the inherent limits on rate conditions established in § 7 proceedings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MO Pub Svc Cmsn v. FERC
337 F.3d 1066 (D.C. Circuit, 2003)
Transwestern Pipeline Company v. Federal Energy Regulatory Commission, the Public Utilities Commission of the State of California, Process Gas Consumers Group, Southern California Gas Company, El Paso Natural Gas Company, Pacific Gas and Electric Company, Texas Eastern Transmission Corporation, the Kansas Power and Light Company, Southwest Gas Corporation, Williams Natural Gas Company, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Southern California Gas Company, Southwest Gas Corporation, Pacific Gas and Electric Company, Williams Natural Gas Company, Public Utilities Commission of the State of California, El Paso Natural Gas Company, Citizens Energy Corporation, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Williams Natural Gas Company, Southern California Gas Company, Public Utilities Commission of the State of California, Intervenors. Transwestern Pipeline Company v. Federal Energy Regulatory Commission, Kansas Power & Light Company, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Southern California Gas Company, Public Utilities Commission of the State of California, Pacific Gas & Electric Company, Psi, Inc., Texas Eastern Transmission Corp., Southwest Gas Corp., Intervenors. Public Utilities Commission of the State of California v. Federal Energy Regulatory Commission, Kansas Power & Light Company, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Southern California Gas Company, Pacific Gas & Electric Company, Psi, Inc., Southwest Gas Corp., Transwestern Pipeline Company, Intervenors. Kansas Power & Light Company v. Federal Energy Regulatory Commission, Natural Gas Clearinghouse, Inc., Williams Natural Gas Company, Pacific Gas & Electric Company, Public Utilities Commission of the State of California, Southern California Gas Company, Psi, Inc., Transwestern Pipeline Company, Intervenors
897 F.2d 570 (D.C. Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
534 F.2d 952, 175 U.S. App. D.C. 215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/algonquin-gas-transmission-company-v-federal-power-commission-bay-state-cadc-1976.