Alexander v. Smith

57 So. 104, 3 Ala. App. 501, 1911 Ala. App. LEXIS 168
CourtAlabama Court of Appeals
DecidedNovember 28, 1911
StatusPublished
Cited by7 cases

This text of 57 So. 104 (Alexander v. Smith) is published on Counsel Stack Legal Research, covering Alabama Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alexander v. Smith, 57 So. 104, 3 Ala. App. 501, 1911 Ala. App. LEXIS 168 (Ala. Ct. App. 1911).

Opinion

WALKER, P. J.

One of the counts of the complaint embodies a copy of the contract between the parties, avers performance by the plaintiff of its stipulationo on his part, and that the defendant has failed and refused to pay one-half of the actual cost of the work, as he agreed to do.

Under his plea of the general issue, the defendant had the benefit in the trial of presenting the claims; which he sought to set up by special pleas, that the work done by the plaintiff did not constitute a performance of the contract according to its terms. This being true, if there was error in sustaining the demurrers to those special pleas, it was error without injury to the defendant.—Selma Street & Suburban Ry. Co. v. Campbell, 158 Ala. 438, 48 South. 378.

The defendant owned a tract of land lying between the plaintiff’s land and Cat creek. By the contract, the plaintiff undertook “to furnish labor to clear off right of way and dig ditch through Cypress pond, and to clean out and open the old ditch, all on lands owned by J. L. Alexander (the defendant), known as the Carew Place. McQueen Smith (the plaintiff) is to dig this ditch not less than six or. eight feet wide and the proper depth necessary, not to exceed three feet in the new ditch.” Each of the parties was to pay one-half of the actual cost. The contract concluded with the stipulation “that the said J. L. Alexander is to allow McQueen Smith water right of way through said ditch through Cypress pond to Cat creek, for purpose of keeping ditch clean and open.” The defendant resisted the plaintiff’s right to recover anything for the digging of this new ditch, on the ground that it was dug more [505]*505than three feet deep, instead of not .to exceed the depth mentioned in the contract. For support in this position he relies on the words in the contract, “not to exceed three feet in the new ditch.”

In construing a contract as a whole or any provision of it that is brought into question, the effort should be to ascertain the intention of the parties, “and, to ascertain their intention, regard may be had. to the nature of the instrument itself, the condition of the parties executing it, and the objects they had in view.”—Lewman & Co. et al. v. Ogden Bros, et al., 143 Ala. 351, 42 South. 102. The situation with which the parties dealt in making the contract in question was the possession of the defendant of an old ditch on his land which he was interested' in having cleaned out and opened and rendered more useful for the draining of his land by the construction of a new ditch to connect with it; while the old and new ditches together would serve plaintiff’s purpose by furnishing drainage for his adjoining land. The two landowners agreed to the scheme of improvement. One of them was to do the work, and each was to pay one-half of the actual cost. The object of each of them was to get his land drained. The obligation of the one who undertook to dig the ditch “the proper depth necessary” was limited and qualified by the words “not to exceed three feet in new ditch;” and while the connection in which those words are found makes it plain that this was the primary purpose of their use, yet the clause also inured to the benefit of the other party to the contract, as it is a fair inference that he did not intend to bind himself to pay one-half of the cost of work done in excess of the requirements of the contract. It being perfectly plain that the paramount object of both parties was to have a ditch that would serve as an effective drain into Cat creek, [506]*506it is not to be supposed that it was any part of their purpose in inserting the clause in question'to enable the defendant to claim that no liability was imposed on him by the digging of the new ditch in the event of its depth exceeding three feet, though the ditch as dug-accomplished the purpose of affording an effective means of drainage, at a cost to the defendant within the limit indicated by the terms of the contract, and the additional digging done by the plaintiff involved no loss or damage to the defendant. Even if the clause in question could reasonably be construed as a limitation upon the right of the plaintiff to dig the new ditch beyond the depth specified, and not as a limitation of the amount of digging required of him by the contract, still the mere fact that the ditch as dug was more than three feet deep would not have the effect claimed by the defendant, unless the excess in the depth of the ditch constituted a material departure from the scheme of improvement contemplated by the parties. It is not every variation from specifications that entitles a party who has contracted for work to be done to claim that his obligation to pay has not been incurred because the work as done does not conform to the terms of the contract.

If the work as done substantially conforms to the requirements of the contract immaterial deviations from specifications do not constitute an obstacle in the way of a recovery of the contract price, less the amount, by way of damages, requisite to indemnify the party sought to be charged against whatever injury he may have sustained as the result of such a departure from the letter of the contract.—Singer Manufacturing Co. v. McLean, 105 Ala. 316, 16 South. 912; Pitcairn v. Philip Hiss Co., 113 Fed. 492, 51 C. C. A. 323; City of Elizbeth v. Fitzgerald, 114 Fed. 547, 52 C. C. A. 321; Crouch v. Gutmann, 134 N. Y. 45, 31 N. E. 271, 30 Am. St. Rep. [507]*507608; 3 Page on Contracts, § § 1385,1386. Tlie ditch here in question was to be six or eig'ht feet wide, and it is not questioned that the plaintiff had the right to dig it “the proper depth necessary, not to exceed three feet in the new ditch.”

Under the evidence, it was a question for the jury whether as dug it was more than three feet deep, and, if so, whether its depth was so little in excess of what was contemplated as to constitute no material deviation from the requirement of the contract in this connection, and to entail no loss or injury upon the defendant. In this state of the evidence the defendant was not entitled to a ruling to the effect that digging the ditch more than three feet deep constituted a material departure from the provisions of the contract. The foregoing considerations disclose the incorrectness of the propositions involved in the second and eighth written charges refused to the defendant. Under those instructions, the jury would have been required to treat any deviation by the plaintiff from the provision referred to, however trivial or substantial as vitally affecting the plaintiff’s rights under the contract.

Another claim set up by the defendant was that he was not chargeable with any part of the cost incurred by the plaintiff in widening the old ditch. This claim is based upon the contention that the stipulation on the part of the plaintiff “to clean out and open the old ditch” did not authorize him to incur any expense in widening that ditch. This clause of the contract also is to be construed in the light of the situation dealt with by the parties and of the object sought to be accomplished. The new ditch provided for was to be connected with the old ditch mentioned, and the latter was to furnish .the outlet to Cat creek. The result in contemplation was in reality one drainage ditch, which was to [508]*508be lengthened by the digging of what was called the “new ditch,” the water from which was to go ont through the old ditch. The language of the contract is to be read in the light of this state of fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miles v. Moore
79 So. 2d 432 (Supreme Court of Alabama, 1955)
Wilson v. Williams
59 So. 616 (Supreme Court of Alabama, 1952)
Griggs v. State
93 So. 499 (Alabama Court of Appeals, 1922)
Alabama City, G. & A. Ry. Co. v. Kyle
87 So. 191 (Supreme Court of Alabama, 1920)
Tate v. Cody-Henderson Co.
66 So. 837 (Alabama Court of Appeals, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
57 So. 104, 3 Ala. App. 501, 1911 Ala. App. LEXIS 168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alexander-v-smith-alactapp-1911.