Aleris Aluminum Canada L.P. v. Valeo, Inc.

718 F. Supp. 2d 825, 72 U.C.C. Rep. Serv. 2d (West) 323, 2010 U.S. Dist. LEXIS 56361, 2010 WL 2351496
District Court, E.D. Michigan·Decided June 8, 2010·No. Case 09-10490·Published·Cited by 4 cases

Opinion

OPINION AND ORDER

PATRICK J. DUGGAN, District Judge.

Aleris Aluminum Canada L.P. and Aleris Aluminum Koblenz GmbH filed this lawsuit alleging various contract related claims against Valeo, Inc. (‘Valeo”) on February 9, 2009. On April 2, 2009, Aleris *827 Aluminum Koblenz GmbH voluntarily dismissed its claims. On April 6, 2009, Valeo filed an answer, affirmative defenses, and counterclaims against Aleris Aluminum Canada L.P. (“Aleris”). On May 4, 2010, 2010 WL 1782166, with leave of the Court, Valeo amended its counterclaims. Now pending is Aleris’s motion for summary judgment as to its breach of contract claim and all of Valeo’s counterclaims. The motion has been fully briefed and the Court heard oral argument on May 26, 2010.

I. Facts and Procedural Background

Prior to the filing of this lawsuit, Aleris and Valeo were engaged in a business relationship whereby Aleris manufactured rolled aluminum products for purchase by Valeo. Valeo then used the rolled aluminum products to fabricate various parts for Chrysler, Ford, and General Motors.

Generally, the arrangement between Aleris and Valeo began with a purchase order assigning product numbers and prices for the various rolled aluminum products. (See Aleris’s Mot. Ex. 3.) The purchase order also reflected an invoice and delivery address, listed the terms of payment, and incorporated Valeo’s “Purchasing Terms and Conditions.” (Id.) Aleris periodically updated its prices based on variations in metal costs but the parties did not physically create a new purchase order with each price adjustment. (Aleris’s Mot. Ex. 1 at 66.) The purchase order itself failed to list purchase quantities and made no reference to Valeo’s requirements. (See Aleris’s Mot. Ex. 3.) Meanwhile, Valeo’s Purchasing Terms and Conditions provided, among other things, that “Valeo reserves the right to terminate any purchase order for its sole convenience, without reason or cause.” (Valeo’s Resp. Ex. 22 ¶ 13.-B.) In the event of termination, Aleris was required to immediately stop all work and was only entitled to recover “a reasonable termination charge consisting solely of a percentage of the order price reflecting the percentage of the work performed pri- or to the notice of termination.” (Id.)

To accommodate actual purchases Valeo sent Aleris weekly forecasts indicating its estimated needs for the products identified in the purchase order. (See Aleris’s Mot. Ex. 5.) The forecasts provided weekly estimates for the upcoming three months and then monthly estimates for the following eight months, for a total 11-month forecast. (Id.) Aleris used the forecast amounts along with historical data to plan its production of the various products. (See Valeo’s Resp. Ex. 5 at 98.) Nothing in the forecasts, however, obligated Valeo to purchase the quantities contained therein. (See Aleris’s Mot. Ex. 5.)

Having planned its production based on the forecasts and historical data, Aleris then delivered finished products to a third-party consignment warehouse. (Aleris’s Mot. Ex. 1 at 55-56.) Valeo, in turn, retrieved the products directly therefrom resulting in a “release” from consignment. (Id.) Aleris ultimately received notice of the released amounts and products and invoiced accordingly. (Id.) The quantities associated with Valeo’s actual releases ranged between zero and 300% of the amounts in Valeo’s forecasts. (Aleris’s Mot. Ex. 10 at 94-95.) As a general matter, Aleris understood that Valeo’s actual purchases would fluctuate with the needs of Valeo’s car manufacturer clients. (See Valeo’s Resp. Ex. 5 at 170, Ex. 6 at 48.) If at any time Valeo required a different product or an unusual amount of product, Valeo and Aleris entered into individual “spot-buy” agreements to deal with the special need. (See Valeo’s Resp. Ex. 6 at 56.) These arrangements were separate from Valeo’s normal practice of retrieving products under the terms of the purchase order as described above. (See id.)

To facilitate and formalize their arrangement, Aleris and Valeo entered into a *828 “Business Agreement” in 2007. (See Valeo Resp. Ex. 38.) The 2007 Business Agreement included pricing standards, payment terms, delivery arrangements, and estimates of Valeo’s needs for each product. (Id.) Although the agreement again did not require that Valeo purchase the estimated volumes or any set minimum, it did make Valeo liable for a maximum of 12 weeks’ material produced or in-process based on Valeo forecasts. (Id.) The agreement indicated effective dates of January 1, 2007, to December 31, 2007, but the parties agreed to apply its terms through March 31, 2008. 1 (See Valeo Resp. Exs. 38, 41.)

In February 2008 the parties also signed a “Logistic Protocol,” retroactively applicable to December 1, 2007, that provided additional detail regarding “the delivery process applicable to the Products supplied by [Aleris] to [Valeo] under the Business Agreement.” (Valeo’s Resp. Ex. 48.) The parties contemplated that the termination date for the Logistic Protocol would be December 31, 2009, based on a future business agreement; in any event, though, the Logistic Protocol was to automatically terminate on termination of the “Business Agreement.” (Id.) The Logistic Protocol provided, among other things, that Aleris would “provide flexibility in line with Valeo’s customers schedule changes” and that Valeo would take title to and pay for any product stored in the consignment warehouse for three months. (Id.)

Anticipating the termination of the 2007 Business Agreement, the parties also began to negotiate a new Business Agreement in early 2008. The parties expected that the new agreement would run from May 1, 2008, to December 31, 2010. (See Valeo’s Resp. Ex. 39.) The 2008-2010 Business Agreement was similar in most respects to the 2007 Business Agreement but also explored the expansion of the relationship between the parties both in the number of products and the number of Valeo facilities supplied by Aleris. 2 (See Valeo’s Resp. Ex. 42.)

Free access — add to your briefcase to read the full text and ask questions with AI

Aleris Aluminum Canada L.P. v. Valeo, Inc., 718 F. Supp. 2d 825, 72 U.C.C. Rep. Serv. 2d (West) 323, 2010 U.S. Dist. LEXIS 56361, 2010 WL 2351496 (E.D. Mich. 2010).

718 F. Supp. 2d 825 (Aleris Aluminum Canada L.P. v. Valeo, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related