Alberici Constructors, Inc. v. Ohio Farmers Insurance Co.

866 N.E.2d 740, 2007 Ind. LEXIS 362
CourtIndiana Supreme Court
DecidedMay 22, 2007
Docket94S00-0612-CQ-488
StatusPublished
Cited by4 cases

This text of 866 N.E.2d 740 (Alberici Constructors, Inc. v. Ohio Farmers Insurance Co.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alberici Constructors, Inc. v. Ohio Farmers Insurance Co., 866 N.E.2d 740, 2007 Ind. LEXIS 362 (Ind. 2007).

Opinion

SHEPARD, Chief Justice.

The U.S. District Court for the Northern District of Indiana has certified to us a question of Indiana law, pursuant to Indiana Appellate Rule 64:

Does a performance bond required by and issued in accordance with Ind.Code § 8-23-9-9 afford coverage to a third-tier claimant?

We now answer that Ind.Code § 8-23-9-9 does not afford coverage to claimants who do not have privity of contract with the general contractor or a subcontractor.

Facts and Procedural History

On or about May 27, 2004, the Indiana Department of Transportation (“INDOT”) awarded Primeo, Inc. a construction contract for the reconstruction of an existing bridge and the erection of a pedestrian bridge near Bluffton, Indiana. On May 25, 2004, Primeo secured a performance bond with defendant Ohio Farmers Insurance Company (“Farmers”). The performance bond follows INDOT contract requirements and the requirements of Ind.Code § 8-23-9-9, and the parties agree that the bond’s protection does not extend to any party not otherwise envisioned by § 8-23-9-9.

On June 14, 2004, Primeo issued a purchase order to Harmon Steel, Inc. for the provision of a pre-fabricated steel bridge to be used in the construction project. In turn, Harmon Steel issued a purchase order on June 18, 2004 to Gateway Bridge, LLC for a “pre-engineered, prefabricated steel truss pedestrian bridge, shipped in two pieces.” (Stip. Facts ¶ 5.) Then on February 21, 2005, Gateway Bridge issued a purchase order for the fabrication of the bridge to “Hillsdale Fabricators,” whose actual corporate name is Alberici Constructors, Inc.

Alberici fabricated and delivered the bridge pieces to Gateway Bridge, which has failed to pay Alberici. Alberici filed its bond claim with Farmers by letter dated October 31, 2005. Farmers denied the claim by letter dated January 13, 2006, explaining its position that Alberici “is too removed to have standing to bring claim.” (Stip. Facts ¶ 13.)

Alberici sued Farmers in the U.S. District Court for the Northern District of Indiana. The parties filed cross-motions for summary judgment. Alberici asserts that the statute reflects an intent to allow parties situated similarly to Alberici to recover under the performance bond. (Pl.’s *742 Br. in Supp. of Summ. J. at 10-16.) Alber-ici asks us to reject a tier-based approach to this issue and to adopt the functional coverage test laid out by the Court of Appeals in Title Guaranty & Surety Co. of Scranton, Pennsylvania v. State ex rel. Leavenworth State Bank, 61 Ind.App. 268, 109 N.E. 237 (1915).

Farmers and amici curiae Indiana Construction Association and Surety & Fidelity Association of America contend that Alberici’s claim is too remote to be covered by the performance bond. They argue that statutory construction, INDOT regulations, federal easelaw, and sound public policy support their contention.

Section 8-23-9-9 Does Not Afford Coverage Beyond the Second Tier

The Indiana Code requires the general contractor on a state highway contract to obtain a performance bond as surety for the project. Ind.Code Ann. §§ 8-23-9-8 through -12 (West 2007). Section 8-23-9-9 provides, among other things, that the bond must be “conditioned ... upon the payment by the contractor and by all subcontractors for all labor performed or materials furnished or other services rendered in the construction of the highway.” Similarly, although not the focus of this certified question, § 8-23-9-12 directs a specific form and substance for such performance bonds: “[The principal] shall promptly pay all debts incurred by the principal or any subcontractor in the construction of the work, including labor, service, and materials furnished.” Ind.Code Ann. § 8-23-9-12 (West 2001). 1

We conclude that these provisions contemplate that the contractor and subcontractors must pay their debts related to a state highway project, and if they do not, the performance bond must provide coverage to protect laborers, material suppliers, and other service providers. At a minimum, the provisions seem to protect all entities who share privity of contract with either the contractor or any subcontractor.

The definitions of “contractor” and “subcontractor” are central to this statutory regime, yet neither term is defined by the statute. The “contractor,” also called a “general contractor” or “prime contractor,” is commonly the person or organization “who contracts for the completion of an entire project,” in this case with the state government. Black’s Law Dictionary 351 (8th ed.2004). The parties agree that Primeo is the contractor.

“Subcontractor” is defined a bit more ambiguously. Interpreted broadly, “subcontractor” might mean any person or organization that has contracted, at any level, to provide any part of the labor or materials for the project, no matter how insignificant. This broad view of “subcontractor” includes what have been traditionally understood as “laborers” (those who supply only labor) and “materialmen” (those who supply only materials). But read more narrowly, “subcontractor” may be limited to those within one or a few degrees of contractual separation from the contractor and who are delegated a specific part of the contractual performance requirements. This narrower definition frequently excludes “laborers” and “materialmen.”

The difference between these two viewpoints is crucial to determining the extent of the contractor’s and the surety’s responsibility for protecting laborers, material suppliers, and other service providers. As it is our objective in statutory construction “to determine and implement *743 the intent of the legislature,” we turn to other sources for guidance. Superior Const. Co. v. Carr, 564 N.E.2d 281, 284 (Ind.1990).

A. Other Sections of the Indiana Code. When interpreting a statute, we presume the legislature intended to apply harmoniously Indiana Code sections with a similar purpose and subject matter. Schrenker v. Clifford, 270 Ind. 525, 387 N.E.2d 59 (1979).

There are other Code sections governing surety bonds and state construction projects, all of which share a similar purpose: to financially protect subcontractors, laborers, and material suppliers. See, e.g., Ind. Code Ann. §§ 4-13.6-7-6 (state public works projects); 5-16-5-2 (other state agencies’ projects); and 5-16-5.5^1 (state projects over $100,000) (West 2007).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: The Name Change of Cory M. Wallace
Indiana Court of Appeals, 2024
Bart Whitesitt v. Town of Knightstown
998 N.E.2d 729 (Indiana Court of Appeals, 2013)
GRADEX, INC. v. Arbuckle
903 N.E.2d 969 (Indiana Court of Appeals, 2009)
Gibson v. Indiana Department of Correction
899 N.E.2d 40 (Indiana Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
866 N.E.2d 740, 2007 Ind. LEXIS 362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alberici-constructors-inc-v-ohio-farmers-insurance-co-ind-2007.