Alabama Rivers Alliance, Inc. v. U.S. Army Corps of Engineers

697 F. Supp. 2d 1251, 2009 U.S. Dist. LEXIS 129699, 2009 WL 6084649
District Court, N.D. Alabama·Decided March 31, 2009·No. CV-07-BE-1609-NE·Published

Opinion

MEMORANDUM OPINION

KARON OWEN BOWDRE, District Judge.

This case comes before the court on “Plaintiffs’ Motion for Summary Judgment” (doc. 32); “City of Cullman’s Motion for Summary Judgment” (doc. 57); and “Federal Defendants’ Cross-Motion for Summary Judgment” (doc. 59). Plaintiffs, Alabama Rivers Alliance, Black Warrior Riverkeeper, Friends of the Mulberry Fork River, Wild South, Nelson Brooke, James Robertson, and Paul Perret, object to the decision of the United States Army Corps of Engineers to issue a permit under § 404 of the Clean Water Act to the Cullman-Morgan Water District to construct a dam across the Duck River in Cullman County, Alabama. Defendants are Peter Geren, the Secretary of the Army; Robert L. Van Antwerp, the Chief of Engineers in the Department of the Army; Peter F. Taylor, the District Engineer and District Commander for the Mobile District of the Corps of Engineers; and the United States Army Corps of Engineers (Corps). The City of Cullman and the Utilities Board of the City of Cullman are intervenors. The parties have fully *1255 briefed all the motions for summary judgment.

For the reasons stated below, the court finds that the Plaintiffs’ motion (doc. 32) is due to be DENIED, the City of Cullman’s motion (doc. 57) is due to be GRANTED, and the Federal Defendants’ motion (doc. 59) is due to be GRANTED.

The court determined in a prior incantation of this case that the Corps had not taken the requisite “hard look” at several considerations in issuing the original permit and FONSI. Am. Canoe Ass’n v. White, 277 F.Supp.2d 1244 (N.D.Ala.2003). Based on that determination, the court remanded the case to the Corps so that the Corps could take the requisite hard look. Following the remand, the Corps conducted further analysis and ultimately decided to issue another FONSI and permit. The court concludes that the Defendants in the present case are entitled to judgment as a matter of law because the Corps’ decision was not arbitrary and capricious and because the Corps took a hard look at the issues discussed below. A separate order to that effect will be entered simultaneously.

INTRODUCTION

Plaintiffs brought this action pursuant to the National Environmental Policy Act (NEPA), 42 U.S.C. § 4332(2), and the Clean Water Act (CWA), 33 U.S.C. § 1344(b)(1). Plaintiffs argue that the Corps’ Finding of No Significant Impact (FONSI), the Corps’ resulting decision not to prepare an environmental impact statement (EIS), and the Corps’ ultimate decision to issue the permit were arbitrary and capricious. Plaintiffs also assert that the Corps’ environmental assessment is inadequate, arbitrary, and capricious, and that the Corps failed to consider all appropriate alternatives.

Plaintiffs ask this court to find that the Corps’ decision to issue a FONSI and not to prepare an environmental impact statement was arbitrary and capricious and not in accordance with 42 U.S.C. § 4332(2)(C). Plaintiffs also ask this court to find that the Corps failed to properly consider alternatives, specifically the option of protecting the existing water source from contamination, in violation of 40 C.F.R. § 1508.9 and 42 U.S.C. § 4332(2)(E). Plaintiffs urge the court to find that the Corps’ determination that the discharge of fill material into the Duck River to create the dam complies with guidelines published under 33 U.S.C. § 1344(b)(1) was arbitrary and capricious. Plaintiffs further urge the court to declare that the Corps’ failure to supplement the original environmental assessment with a discussion of the reduction in the growth of water demand, reduction in population growth, reduction in poultry production, and increase in water supply was arbitrary and capricious. Plaintiffs ask the court to declare that the Corps’ determination that a 3,300 pounds per year reduction in Total Phosphorous (TP) load at the proposed Duck River reservoir is possible was arbitrary and capricious.

Plaintiffs, in essence, ask the court to declare that the Corps issued a permit for the Duck River dam in violation of NEPA and the CWA and to vacate that permit. They also ask the court to enjoin the Corps from allowing the Duck River Project to proceed until the Corps prepares an environmental impact statement or adequately supplements the environmental assessment.

The parties have fully briefed the issues raised in the cross motions for summary judgment. The issue before the court, essentially, is whether the Corps’ decision to issue a FONSI based upon the allegedly inadequate supplemental environmental assessment conducted in 2006, and the resulting issuance of a permit to build the dam, was arbitrary and capricious. Upon *1256 due consideration and for the reasons stated below, the court answers this question in the negative.

FACTS 1

I. Background

Cullman County is located in north central Alabama approximately 50 miles north of Birmingham, Alabama’s largest city, and approximately 50 miles south of Huntsville. Cullman County covers a land area of 743 square miles and features 11 incorporated municipalities. Little groundwater exists in the area, so local water systems utilize a surface supply that is interconnected over a large area. These systems now serve a large population in Cullman County and portions of five adjoining counties.

Free access — add to your briefcase to read the full text and ask questions with AI

Alabama Rivers Alliance, Inc. v. U.S. Army Corps of Engineers, 697 F. Supp. 2d 1251, 2009 U.S. Dist. LEXIS 129699, 2009 WL 6084649 (N.D. Ala. 2009).

697 F. Supp. 2d 1251 (Alabama Rivers Alliance, Inc. v. U.S. Army Corps of Engineers) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hill v. Boy
144 F.3d 1446 (Eleventh Circuit, 1998)
Sierra Club v. U.S. Army Corps of Engineers
295 F.3d 1209 (Eleventh Circuit, 2002)
Sierra Club v. Van Antwerp
526 F.3d 1353 (Eleventh Circuit, 2008)
Florida Power & Light Co. v. Lorion
470 U.S. 729 (Supreme Court, 1985)
Marsh v. Oregon Natural Resources Council
490 U.S. 360 (Supreme Court, 1989)
Sierra Club v. John O. Marsh, Jr.
872 F.2d 497 (First Circuit, 1989)
Georgia River Network v. U.S. Army Corps of Engineers
334 F. Supp. 2d 1329 (N.D. Georgia, 2003)
American Canoe Ass'n v. White
277 F. Supp. 2d 1244 (N.D. Alabama, 2003)
North Buckhead Civic Ass'n v. Skinner
903 F.2d 1533 (Eleventh Circuit, 1990)