Alabama Power Co. v. Federal Energy Regulatory Commission

220 F.3d 595, 343 U.S. App. D.C. 11, 2000 U.S. App. LEXIS 15363, 2000 WL 798183
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 30, 2000
Docket98-1214
StatusPublished
Cited by1 cases

This text of 220 F.3d 595 (Alabama Power Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alabama Power Co. v. Federal Energy Regulatory Commission, 220 F.3d 595, 343 U.S. App. D.C. 11, 2000 U.S. App. LEXIS 15363, 2000 WL 798183 (D.C. Cir. 2000).

Opinion

Opinion for the court filed by Circuit Judge HENDERSON.

KAREN LECRAFT HENDERSON, Circuit Judge:

Petitioners Alabama Power Company, Georgia Power Company, Gulf Power Company, Mississippi Power Company, Savannah Electric and Power Company and Southern Company Services, Inc. (collectively, the Southern Companies, petitioners) seek review of two orders of the Federal Energy Regulatory Commission (FERC, Commission) rejecting two components of the rates they had proposed for supplying electric power to the City of Tallahassee, Florida (City). 1 The first component is “turbine assembly costs” and the second is “heating loss costs.” With regard to the former, the Southern Companies argue that FERC’s policy as applied here is inconsistent with a recent FERC decision allowing recovery of such costs. With regard to the Commission’s denial of recovery for heating loss, the Southern Companies argue that the method they used to calculate loss, yielding-results FERC deemed unreliable, is used by FERC for related purposes. They also . argue that the Commission’s concern over double recovery of heating loss costs is misplaced.

For the reasons set forth below, we grant the petition for review and remand to the Commission for proceedings consistent with this opinion and with its recent decision approving recovery of turbine costs to determine whether the Southern Companies justified this component of its rate.

I.

In 1990 the Southern Companies filed a Unit Power Sales (UPS) Agreement between themselves and the City proposing the sale of certain electric power capacity to the City for a term of ten years. The UPS Agreement prescribed transmission charges for various support services, including a monthly reactive control charge for the costs associated with generator-supplied reactive power. The Southern Companies then faced the task of satisfying FERC that their proposed reactive power charge was just and reasonable. Hearings before an administrative law judge yielded an Initial Decision largely approving the Southern Companies’ proposal, concluding that “the proposed reactive power charges, with modification to certain component allocations and [the Southern Companies’] reactive power credits, are just and reasonable.” Southern Co. Servs., Inc., 61 FERC ¶ 63,009 at 65,-024 (1992). The Commission affirmed in part and reversed in part, taking issue with certain aspects of the Southern Companies’ methodology. See Southern Co. Servs., Inc., 80 FERC ¶ 61,318 (1997). The Commission’s two modifications at issue here, on which the Commission stood firm in denying rehearing, see 82 FERC ¶ 61,168 (1998), are the exclusion of turbine assembly costs and the exclusion of heating loss .costs.

The Commission described reactive power and its role in the provision of electric power as follows:

Electric power consists, of two components. The first component, “real” power (expressed in terms, of watts), is the active force that causes electrical equipment to perform work. The second component, “reactive” power, (expressed *597 in terms of volt-amperes reactive (VARs)) is necessary to maintain adequate voltages so.thát “real” power can be transmitted. .
Failure to provide the correct amount of reactive power at various points on the transmission system can cause deviations from desired voltage levels and disruption in the flow of power on the system. In order to maintain desired voltage levels, reactive power must be supplied or absorbed by generators (or transmission equipment) at various points on the transmission system.

Southern Co. Servs., Inc., 80 FERC at 62,080 (footnotes omitted).

The Southern Companies utilize generators to produce reactive power and the production of reactive power causes heating loss that increases fuel consumption and demand on the generators. See Brief of Commission at 36. 2 The Southern Companies factored the heating loss into its costs equation, seeking to recoup for the required use of additional fuel and for a portion of the generators’ real power capacity. To calculate costs, the Southern Companies combined the cost of reactive power “impacts” on their energy system with the heating loss cost to arrive at a control charge. Brief of Petitioners at 12. They determined the cost of the reactive power impacts through use of two load flow studies. One study measured the “base-case” load flow conditions and quantified the reactive power requirement of all generators, in the transmission system. The other, a “transaction-case” load flow study, measured the effect on the system of an energy transaction similar to those proposed in the UPS Agreement with the City. A comparison of the studies demonstrated the impact (measured in megavolt ampere reactives (MVARs)) of individual transactions under the UPS Agreement, allowing the petitioners to determine the amount of generating capacity lost in each transaction and then to multiply that figure by an average energy rate and thus quantify the heating loss resulting from production of reactive power necessary to supply the City.

The petitioners also sought to recoup, through the proposed reactivé power charge at issue, costs incurred from use of their generators to supply or absorb reactive power. Having determined the amount of MVARs the transactions under the UPS Agreement demanded, their next step in calculating the charge was to identify the six major generator components associated with reactive power production. 3 Relying on the connection between the turbines and the production of reactive power, 4 the Southern Companies included the “turbine assembly” 5 as one of the six *598 major components in its costs calculation. Using these components, they estimated the plant investment associated with production of reactive power. Because the turbine assembly is involved with the production of both real power and reactive power, the Southern Companies included in their estimate, and thus in the reactive power charge, only that portion of the turbine assembly cost allocated to reactive power based on the ratio of total power to reactive power. See 80 FERC at 62,083.

The Commission concluded the Southern Companies’ calculations suffered from “erroneous modeling assumptions and flawed rate design.” Id. at 62,084. The load flow studies used to calculate heating loss costs came under attack first. The base-case load flow study reflected a hypothetical operating condition that, as the Southern Companies’ expert conceded, is not typical or desirable. See id. at 62,084-85. The Commission disapproved the transaction cases as well because the Southern Companies’ calculations did not account for possible generator responses that benefit the system by either absorbing or producing fewer MVARs. For example, some transactions cause a decrease in the absorption of MVARs, a benefit to the transmission system, but the petitioners’ calculations reflected this reduction of demand on the system as an increase in demand for reactive power service.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
220 F.3d 595, 343 U.S. App. D.C. 11, 2000 U.S. App. LEXIS 15363, 2000 WL 798183, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alabama-power-co-v-federal-energy-regulatory-commission-cadc-2000.