Alabama Metal Products, Inc. v. United States

31 Cont. Cas. Fed. 72,156, 4 Cl. Ct. 530, 1984 U.S. Claims LEXIS 1488
CourtUnited States Court of Claims
DecidedFebruary 14, 1984
DocketNo. 610-83C
StatusPublished
Cited by7 cases

This text of 31 Cont. Cas. Fed. 72,156 (Alabama Metal Products, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alabama Metal Products, Inc. v. United States, 31 Cont. Cas. Fed. 72,156, 4 Cl. Ct. 530, 1984 U.S. Claims LEXIS 1488 (cc 1984).

Opinion

OPINION

WIESE, Judge.

This matter is before the court on defendant’s motion to dismiss or, in the alternative, for summary judgment and plaintiff’s opposition thereto. At issue is a question on which the opinions of the Claims Court have expressed a difference of view: whether the court’s injunctive authority under 28 U.S.C. § 1491(a)(3) (1976), as amended by Act of Apr. 2, 1982, Pub.L. No. 97-164, 96 Stat. 25, extends to contract actions challenging intended procurement awards on grounds other than the claimed denial of a fair opportunity to compete.

This court has answered that question in the negative: Cecile Industries, Inc. v. United States, 2 Cl.Ct. 690 (1983), defined the boundaries of our injunctive authority in disappointed bidder suits in terms of a procuring agency’s contractually enforceable responsibilities to evaluate a bid fairly and honestly. In this action, plaintiff urges the court to reexamine this position. We have done so but find in the arguments offered no support for a different result. On the facts of the case and the law applicable thereto, the court holds that it is without jurisdiction. The motion to dismiss is therefore granted.

Procedural Background

In a complaint for declaratory and injunctive relief filed here on October 6,1983, plaintiff, a disappointed bidder, asked for a temporary restraining order and preliminary injunction barring the General Services Administration (GSA) from proceeding with an intended award under Invitation for Bids No. FNPS-S1-1532-A-9-2-83. Following an initial hearing, the parties jointly moved for a suspension of proceedings in order to permit the matter to be taken before the General Accounting Office (GAO) for decision. Pursuant to this motion, the Government agreed to postpone the intended award until the GAO had ruled on the matter.

The administrative decision was entered on December 12, 1983. In that decision, designated by file number B-213493, the GAO upheld the legality of the various procurement matters which plaintiff had challenged. Dissatisfied with this result and claiming GAO’s decision to be wrong as a matter of law, plaintiff, by motion orally made on December 14,1983, asked the court to preliminarily enjoin GSA from proceeding with the award and to schedule the matter for trial on a permanent injunction.

The request for temporary restraint was denied by the court. As to the demand for trial and permanent injunction, it was decided, for economy’s sake, that resolution of the jurisdictional problem in the case ought to precede any trial on the merits. An appropriate briefing schedule was thereupon set. That having now been completed, and oral argument having been heard, the matter is ready for disposition.

The Solicitation

The solicitation in question, issued August 1, 1983, involved a Federal Supply Schedule contract for an indefinite quantity of stackable beds and drawer units for purchase during the period July 1, 1983 through June 30, 1984. For bidding purposes, these requirements were divided into [532]*532two separate award groups — “Award Group 1” covering the beds and “Award Group 2”, the drawer units. Within each group, bidders were required to submit a price for domestic and overseas shipments. Additionally, the award groups were further separated into geographic zones (Zones 1, 2, and 3), with each zone being assigned a “weight factor” — an indicator that expressed, in ratio form, the relative dollar volume between the prior year’s per-zone sales and total purchase activity. The solicitation requested separate pricing in each of these three geographic zones.

Thus, for the drawer units upon which plaintiff bid, the schedule appeared roughly as follows:

Weight Supplies or Services
Factors Price
Zones Zones
12 3 12 3
Award Group 2
Items 481-2(a) & 481-2(b)
3 1 2 481-2(a) Domestic Shipments - - -
4 1 2 481-2(b) Overseas Shipments - - -

The solicitation’s “method of award” clause advised that “[a]ward will be made in the aggregate by group for each zone” and that the low aggregate offeror “will be determined by multiplying the unit price offered on each item by the weight factor shown, and adding the resultant extensions.” The clause also informed bidders that “[i]n order [to] qualify for an award on a group for a zone, prices must be offered on each item in the group for the zone.”

While bidders were thus required to bid on each item in a group for a zone they were not restricted to that format. That is to say, “all or none” offers were acceptable. However, the solicitation cautioned that for requirements and indefinite quantity contracts (the situation here) such all-or-none offers “will not be considered unless the offer is low on each item to which the ‘all or none’ offer is made applicable.”

Plaintiff submitted an all-or-none offer for the three geographic zones on which offers were sought. As it turned out, that offer was lowest in two of the three zones and lowest in the overall; on the remaining zone, however, it stood second low. In terms of the solicitation then, the bid was not “low on each item to which the ‘all or none’ offer [was] made applicable.” The bid was therefore rejected; from that rejection this lawsuit followed.

Discussion

1.

Of the several grounds of attack that plaintiff raised in its complaint, the only matter that concerns us now is the contention that the solicitation unreasonably limited the acceptability of an all-or-none bid and, in so doing, violated the statutory directives of 41 U.S.C. § 253(b) (1976) (calling for award to the bidder whose bid “will be most advantageous to the Government”) and 10 U.S.C. § 2305(a)(1982) requiring that invitations for bids “permit such free and full competition as is consistent with” the agency’s needs.

As to specifics, the argument goes this way: If the weight factors set out in the solicitation are sufficiently reliable to permit — indeed, to require — aggregation of domestic and overseas bid prices for purposes of determining the lowest intra-zone bidder, then those same factors should also suffice to permit inter-zone aggregation of domestic and overseas bid prices for purposes of determining, and awarding to, the lowest overall bidder (i.e., all-or-none bidder). The same numbers cannot logically be regarded as credible for one bid evaluation purpose and not another.

Therefore — the argument continues — to incorporate such an imbalance into an invitation for bids is to structure a solicitation that is fatally defective. To allow aggregation for one award purpose and not another is to say either that the weight factors have no inherent reliability, in.which event the solicitation must be cancelled, or else that they are fully credible in which event the all-or-none bidder has been arbitrarily denied their competitive significance. In either case, says plaintiff, the admixture of [533]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Levine v. Johnson
78 F.3d 603 (Federal Circuit, 1996)
Data Transformation Corp. v. United States
34 Cont. Cas. Fed. 75,338 (Court of Claims, 1987)
Olympia USA, Inc. v. United States
32 Cont. Cas. Fed. 73,084 (Court of Claims, 1984)
Harris Systems International, Inc. v. United States
32 Cont. Cas. Fed. 72,486 (Court of Claims, 1984)
Space Age Engineering, Inc. v. United States
32 Cont. Cas. Fed. 72,388 (Court of Claims, 1984)
Golden Eagle Refining Co. v. United States
31 Cont. Cas. Fed. 72,190 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 72,156, 4 Cl. Ct. 530, 1984 U.S. Claims LEXIS 1488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alabama-metal-products-inc-v-united-states-cc-1984.