Al Urbain Construction Management Company, Inc. v. CW Wolfe LLC
Opinion
IN THE COURT OF APPEALS OF IOWA
No. 20-1627
Filed January 12, 2022
AL URBAIN CONSTRUCTION MANAGEMENT COMPANY, INC., Plaintiff-Appellant/Cross-Appellee,
vs.
CW WOLFF, LLC, Defendant-Appellee/Cross-Appellant.
Appeal from the Iowa District Court for Dubuque County, Alan Heavens, Judge.
Plaintiff appeals and defendant cross-appeals the district court’s decision on their breach-of-contract claims. AFFIRMED ON BOTH APPEALS.
Robert E. Sabers, Dubuque, for appellant.
Darin S. Harmon and Jeremy N. Gallagher of Kintzinger, Harmon, Konrardy, P.L.C., Dubuque, for appellee.
Considered by Bower, C.J. and Vaitheswaran and Schumacher, JJ.
SCHUMACHER, Judge.
Al Urbain Construction Management Co. (AUCM) appeals and CW Wolff, LLC (CWW) cross-appeals the district court’s decision on their breach-of-contract claims. The district court awarded damages to AUCM on one project and CWW on another project, then offset these two amounts. We find the district court’s decision is supported by substantial evidence and affirm on the appeal and cross- appeal.
I. Background Facts & Proceedings Aloysius Urbain is the president and sole shareholder of AUCM, a construction management company. AUCM works with commercial clients through a pre-construction phase, produces a project budget, arranges a sequence of construction, and ensures everything is done according to plan. A construction management company is different from a general contractor, who retains subcontractors for a job. Urbain testified, “The way management works is I find the contractors and I share the exact numbers with the client and historically the client pays those bills directly is way it’s supposed to work.”
Clark Wolff is the owner of CWW, a real estate business. He is also the president of Selco, Inc., a contract traffic control company. Urbain and Wolff were acquainted socially. They entered into agreements that AUCM would work on two building projects for CWW—a new building for Selco (Selco project), and a barbeque restaurant called Devil’s Pit (Devil’s Pit project). There were no written contracts.
During the construction process, CWW became increasingly concerned with what it viewed as AUCM’s lack of attention to the projects. Many problems
were caused by a lack of documentation concerning what services AUCM was hired to provide and communication difficulties. When AUCM presented bills to CWW for contractors and suppliers, CWW would not pay the full amount due, so AUCM paid the shortfall. AUCM also began sending some contractors directly to CWW, rather than CWW paying AUCM and then AUCM paying the contractors. These practices caused problems in determining the actual costs of the projects. Both projects were completed on time and lien waivers were obtained from all of the contractors.
On November 22, 2017, AUCM sent a letter to CWW asking for a meeting to close out the projects. AUCM stated CWW owed $88,734.36 for the Devil’s Pit project. This included a payment of ten percent of the project costs for AUCM’s services, which it stated was $16,600.00. AUCM also stated CWW owed $48,981.14 for the Selco project, which included a payment of $35,856.14, representing six percent of the project costs. The total amount due was $137,715.50. CWW did not respond to the letter and AUCM sent a second letter on December 20, again requesting a meeting. No response was made to the second letter.
On May 2, 2018, AUCM sent a letter to CWW stating it had revised its billing.
The letter stated, “It was my intent not to charge you for services provided at your previous Selco operation located at 15 S. Main Street, Dubuque, Iowa, plus additional sites, including your personal residence as outlined in my new final billing in the amount of $177,827.41.” AUCM asked to be paid $120 per hour for looking at other locations for the new Selco building before the present location was selected. The revised billing asked for $89,494.36 for the Devil’s Pit project
and $58,319.75 for the Selco project, plus payment for work at other sites. CWW did not respond to this request for payment.
On June 14, AUCM filed a petition claiming CWW breached their contract by not paying for services. In the alternative, AUCM sought relief on a theory of quantum meruit. CWW raised counterclaims against AUCM, asserting claims of breach of contract, unjust enrichment, and conversion. A bench trial was conducted on October 29 and 30, 2020. Testimony was provided by Urbain; Wolff; Damien Miller, a general contractor; Dan Muntz, a supervisor for Selco; Roger Klosterman, a certified public accountant (CPA) and financial advisor; and Steve Ulstad, an architect.
The district court found AUCM proved CWW breached the contract for construction management services for the Devil’s Pit project by failing to pay for AUCM’s services and the reimbursement of some of the contractors. The court awarded AUCM damages of $89,494.36 for the Devil’s Pit project. The court denied AUCM’s request to be paid $120 per hour for work scouting out other locations for the new Selco building, finding there was no agreement AUCM would be paid for the work. The court determined AUCM did not prove its other claims for damages related to the Selco project but CWW did prove its claims through the testimony of Klosterman. The court awarded CWW damages of $83,050.51 for the Selco project. The two awards were set off and the court entered judgment for AUCM in the amount of $6443.85. AUCM appealed and CWW cross-appealed.
II. Standard of Review We review breach-of-contract actions for the correction of errors at law.
Iowa Mortg. Ctr., L.L.C. v. Baccam, 841 N.W.2d 107, 110 (Iowa 2013). “If
substantial evidence in the record supports a district court’s finding of fact, we are bound by its finding. However, a district court’s conclusions of law or its application of legal principles do not bind us.” Id. (citation omitted). “When a party challenges a district court’s ruling claiming substantial evidence does not support the decision, we must view the evidence in the light most favorable to support the judgment and liberally construe the court’s finding to uphold, rather than defeat, the result reached.” Papillon v. Jones, 892 N.W.2d 763, 770 (Iowa 2017), as amended (June 6, 2017) (quoting Iowa Beta Chapter of Phi Delta Theta Fraternity v. State, 763 N.W.2d 250, 257 (Iowa 2017)).
III. Selco Project AUCM contends the district court erred by denying its claims for damages for the Selco project. In order to show a breach of contract, a party must show:
(1) the existence of a contract; (2) the terms and conditions of the contract; (3) that it has performed all the terms and conditions required under the contract; (4) the defendant’s breach of the contract in some particular way; and (5) that plaintiff has suffered damages as a result of the breach.
Iowa Mtg. Ctr., 841 N.W.2d at 111 (citation omitted).
AUCM claims CWW breached the contract by not paying AUCM the total amount due for its services. It asserts there was not substantial evidence in the record to support the district court’s conclusion that AUCM was overpaid for the Selco project. AUCM contends the financial exhibits show it was underpaid $29,061.19 for its work.1 AUCM also states that it was not paid the six percent
1 AUCM states CWW paid $710,000.00 for the Selco project and AUCM paid vendors $739,061.19, which is a deficit of $29,061.19.
management fee, which it calculates to be $88,190.16. In total, AUCM claims CWW owes it $117,251.35 for the Selco project.
The district court found AUCM did not adequately prove its damages, stating, “To put it mildly, AUCM’s damages request for the Selco project was a moving target.” AUCM’s request for damages kept changing over time. The court found:
Free access — add to your briefcase to read the full text and ask questions with AI
Al Urbain Construction Management Company, Inc. v. CW Wolfe LLC (Al Urbain Construction Management Company, Inc. v. CW Wolfe LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.