Ahtna Design-Build, Inc. v. Asphalt Surfacing, Inc.

CourtDistrict Court, D. Alaska
DecidedSeptember 6, 2022
Docket3:21-cv-00228
StatusUnknown

This text of Ahtna Design-Build, Inc. v. Asphalt Surfacing, Inc. (Ahtna Design-Build, Inc. v. Asphalt Surfacing, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Alaska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ahtna Design-Build, Inc. v. Asphalt Surfacing, Inc., (D. Alaska 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF ALASKA

AHTNA DESIGN-BUILD, INC., an Alaska corporation, Case No. 3:21-cv-00228-JMK Plaintiff,

vs. ORDER DENYING DEFENDANTS’ MOTION TO DISMISS AND ASPHALT SURFACING, INC., a MOTION TO TRANSFER California corporation, and UNITED FIRE & CASUALTY COMPANY Bond No. 54-197210,

Defendants.

Pending before the Court at Docket 17 is Defendants Asphalt Surfacing, Inc. (“ASI”), and United Fire & Casualty Company Bond No. 54-197210’s (“UFCC,” and together with ASI, “Defendants”) Motion to Dismiss or Transfer for Lack of Personal Jurisdiction/Invalid Venue or for Forum Non Conveniens the (the “Motion”). Plaintiff Ahtna Design-Build, Inc. (“ADB”) responded in opposition at Docket 20. Defendants replied at Docket 24. For the forthcoming reasons, Defendants’ Motion is DENIED. I. FACTUAL HISTORY A. The Parties

ADB is a corporation that provides construction and engineering services and is headquartered and incorporated in Alaska, with offices in California.1 ADB is a wholly owned subsidiary of Ahtna Netiye’, LLC, which in turn is a wholly owned subsidiary of Ahtna, Inc., an Alaska Regional Native Corporation.2 ADB is the prime contractor for a contract (the “Prime Contract”) with the United States Army Mission Installation Contracting Command–Fort McCoy.3 One task order of the Prime Contract requested

maintenance of asphalt roads at Fort Hunter Liggett in California (the “Project”).4 The Project involved resurfacing approximately 750,000 square feet of asphalt.5 ASI is a paving contractor incorporated and headquartered in California.6 ADB and ASI entered into a Subcontract for Construction Services (the “Subcontract”), in which ASI agreed to perform the Project work for the price of $1,108,107.29.7 The terms

of the Subcontract required ASI to secure a performance bond in the amount of the

1 Docket 1 at 3. 2 Docket 20 at 3. 3 Docket 1 at 3. 4 Id. 5 Id. 6 Id.; Docket 9 at 2. 7 Docket 1 at 3–4. Subcontract price.8 ASI did so by securing a bond through UFCC, an Iowa corporation.9 UFCC Bond No. 54-197210 (the “Bond”) lists ADB as the “Owner” of the Bond.10

B. The Subcontract and the Bond Relevant to the present motion, the Subcontract contains a forum selection clause, which states: Any controversy or claim arising out of or relating to this Agreement, or the breach of the same, shall be settled through consultation and negotiation in good faith and a spirit of mutual cooperation. However, if those attempts fail after thirty (30) days, or longer, if the parties mutually agree in writing, the parties agree that any misunderstandings or disputes arising from this Agreement shall be resolved by a court of competent jurisdiction located in Anchorage Alaska, without regard to its choice of law and venue rules. The parties hereby agree to venue and personal jurisdiction in Alaska.11

The Bond contains its own forum selection clause, which reads: Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located and shall be instituted within two years after a declaration of Contractor Default or within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform its obligations under this Bond, whichever occurs first. If the provisions of this Paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable.12

8 Id. at 4. 9 Docket 1 at 2; Docket 9 at 2. 10 Docket 17-5 at 1; Docket 20-5 at 1. The Court notes that the Bond is sometimes referred to as Bond No. 54197228. See Docket 9 at 2; Docket 17-14 at 2; Docket 17-5 at 1. The parties do not address this discrepancy in their briefing. 11 Docket 17-4 at 6; Docket 20-3 at 6. 12 Docket 17-5 at 3; Docket 20-5 at 3. The Bond also has a provision that incorporates the entirety of the Subcontract by reference, stating, “[t]he Contractor [(ASI)] and Surety [(UFCC)], jointly and severally,

bind themselves . . . to the Owner [(ADB)] for the performance of the Construction Contract [(the Subcontract)], which is incorporated herein by reference.”13 C. The Dispute ADB alleges that, both during the Project work and afterwards, it noticed defects in ASI’s performance under the Subcontract, including cosmetic problems, unexpected damage to the newly paved road surface caused by vehicle traffic, and defects

in the application of thermoplastic lines and signage.14 In February 2021, ADB and ASI discussed ASI’s alleged defective performance, but the parties could not come to an agreement regarding the scope of the corrective work needed on the Project.15 On April 19, 2021, ADB provided ASI with a written notice (the “Notice”) that it had defaulted on its obligations under the Subcontract by failing to perform the work according to the

Subcontract specifications and “with the skill and care reasonably expected for that type of work.”16 The Notice identified eight defects in ASI’s performance that needed remediation and gave ASI fourteen days to submit a plan to perform all of the remediation work.17 Following the Notice, ADB and ASI again failed to agree on a remediation plan.18 On May 12, 2021, ADB contacted UFCC and submitted a formal claim on the Bond, indicating

13 Docket 17-5 at 2; Docket 20-5 at 2. 14 Docket 1 at 4. 15 Id. at 4–5. 16 Id. at 5. 17 Id. at 5–6. 18 Id. at 6–7. that it intended to declare ASI in default.19 UFCC agreed to evaluate the claim and proceeded to investigate and retain experts for third-party analyses of ASI’s work.20

ADB alleges that the United States Government informed ADB that it would not process payment for the Project due to the defects that ADB identified in its Notice.21 After several other unsuccessful attempts to reach a resolution regarding an appropriate remediation plan, ADB gave ASI notice that its performance under the Subcontract was terminated due to ASI’s default of its performance obligations.22 ADB informed UFCC of ASI’s termination and demanded that UFCC complete the Project work.23 UFCC refused,

arguing that it had no remaining obligations to ADB.24 ADB then informed UFCC it was in default of its Bond obligations.25 ASI and UFCC deny the allegations of defective work.26 They admit there were cosmetic issues that needed resolution, but argue these issues were adequately addressed by ASI’s proposed remediation plan, which was wrongfully rejected by ADB.27

II. PROCEDURAL HISTORY ADB brought this lawsuit against ASI and UFCC on October 14, 2021, asserting claims for breach of contract, breach of the implied warranty of good faith and fair dealing, a claim against the Bond, performance bond bad faith, and a violation of the

19 Id. at 7. 20 Id. 21 Id. 22 Id. at 8. 23 Id. 24 Id. 25 Id. at 9. 26 Docket 9 at 5; Docket 17 at 4. 27 Docket 9 at 5; Docket 17 at 4–5. Alaska Unfair Trade Practices and Consumer Protection Act.28 Defendants filed an Answer on November 22, 2021, asserting counterclaims for breach of an express and implied contract.29

On November 3, 2021, ASI filed a separate action against ADB and Great American Insurance Group (“Great American”) in the Northern District of California, San Jose (the “California Action”).30 The California Action involves claims for breach of the Subcontract against ADB and for recovery on a Miller Act bond against ADB and Great American, ABD’s surety under the performance bond ADB secured pursuant to the terms

of the Prime Contract.31 On November 23, 2021, ADB filed a Motion to Dismiss, Transfer or Stay in the California Action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Shoe Co. v. Washington
326 U.S. 310 (Supreme Court, 1945)
The Bremen v. Zapata Off-Shore Co.
407 U.S. 1 (Supreme Court, 1972)
Piper Aircraft Co. v. Reyno
454 U.S. 235 (Supreme Court, 1982)
Burger King Corp. v. Rudzewicz
471 U.S. 462 (Supreme Court, 1985)
The Rice Corporation v. Grain Board of Iraq
430 F. App'x 604 (Ninth Circuit, 2011)
Simonoff v. Expedia, Inc.
643 F.3d 1202 (Ninth Circuit, 2011)
Murphy v. Schneider National, Inc.
362 F.3d 1133 (Ninth Circuit, 2004)
Pavone v. Pavone
860 P.2d 1228 (Alaska Supreme Court, 1993)
Doe 1 v. AOL LLC
552 F.3d 1077 (Ninth Circuit, 2009)
Boston Telecommunications Group, Inc. v. Wood
588 F.3d 1201 (Ninth Circuit, 2009)
Cates Construction, Inc. v. Talbot Partners
980 P.2d 407 (California Supreme Court, 1999)
Holck v. Bank of New York Mellon Corp.
769 F. Supp. 2d 1240 (D. Hawaii, 2011)
Nunez v. American Seafoods
52 P.3d 720 (Alaska Supreme Court, 2002)
Daimler AG v. Bauman
134 S. Ct. 746 (Supreme Court, 2014)
Bernard Picot v. Dean Weston
780 F.3d 1206 (Ninth Circuit, 2015)
Peter Weber v. Pact XPP Technologies, AG
811 F.3d 758 (Fifth Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Ahtna Design-Build, Inc. v. Asphalt Surfacing, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ahtna-design-build-inc-v-asphalt-surfacing-inc-akd-2022.