Aetna Casualty & Surety Co. v. J. F. Brunken & Son, Inc.

357 F. Supp. 290, 12 U.C.C. Rep. Serv. (West) 388, 1973 U.S. Dist. LEXIS 13938
CourtDistrict Court, D. South Dakota
DecidedApril 23, 1973
DocketCiv. 72-4036
StatusPublished
Cited by7 cases

This text of 357 F. Supp. 290 (Aetna Casualty & Surety Co. v. J. F. Brunken & Son, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aetna Casualty & Surety Co. v. J. F. Brunken & Son, Inc., 357 F. Supp. 290, 12 U.C.C. Rep. Serv. (West) 388, 1973 U.S. Dist. LEXIS 13938 (D.S.D. 1973).

Opinion

MEMORANDUM DECISION

NICHOL, Chief Judge.

This is a declaratory judgment action, 28 U.S.C. Secs. 2201 and 2202, brought by a surety, Aetna Casualty and Surety Company (Aetna), to determine priorities between conflicting claimants to the property of J. F. Brunken & Son, Inc. (Brunken), or the proceeds thereof, now in the possession of the court-appointed receiver. In addition to the Brunken Corporation, those defendants remaining in the suit at the time of trial were the National Bank of South Dakota (NBSD) and Northwestern National Bank (NWB), both asserting security interests in the Brunken proceeds pursuant to the secured transaction provisions of the South Dakota Uniform Commercial Code, SDCL Chapters 57-35 to 57-39, as amended.

Defendant Brunken contracted for eight different construction projects which required performance bonds. Aetna furnished the requisite bonds pursuant to Brunken’s separate applications dating from July, 1967, to March, 1970. Under the terms of the applications for the bonds, Brunken assigned, transferred and conveyed to Aetna

all rights, title and interest in and to all tools, plant, equipment and materials of every nature and description that the said (Brunken) may now or hereafter have upon said work, or in or about the site thereof, or used in connection with the work and located elsewhere, ....

Subsequently, Aetna was called upon and did perform in compliance with the bond’s provisions on these four projects: Butte-Meade — bond application date: August 1, 1968. Hayward Sanitary Sewer District — bond application date: October 17, 1968.

Town of Toronto — bond application date: July 11, 1969. City of Rapid City —bond application date: August 4, 1969. As of December 19, 1972, the surety had expended $404,759.30 in performance of its contracts and had received $102,392.85, leaving a deficit of $302,366.45.

The evidence shows that the defendant NBSD had established a line of credit with Bi'unken since 1955, and over the years financed equipment purchases of the Brunken Corporation. On January 25, 1968, Brunken entered into a security agreement with NBSD. The security agreement listed specific pieces of property as collateral, and, also, contained an “after-acquired” clause 1 providing *292 NBSD ' with a security interest in all other equipment subsequently acquired by Brunken. A financing statement was filed with the South Dakota Secretary of State on February 2, 1968, to perfect NBSD’s security interest in the designated collateral. The financing statement and security agreement were identical except that the financing statement lacked the after-acquired clause present in the security agreement. The filed financing statement includes the attached list of equipment specified in the security agreement as collateral, and only that portion of the security agreement’s after-acquired phrase which provides: “together with all repairs, improvements and accessions thereto and substitutions and replacements therefor at any time hereinafter made or acquired and all other”.

In reliance upon the security agreement and financing statement, NBSD extended additional loans to the Brunken Corporation, which are now evidenced by five promissory notes signed by a corporate officer. As of May 26, 1972, the amount due and owing NBSD on these notes, according to its stipulated figures, is $180,933.99. Additional expenses were incurred by NBSD when Brunken defaulted upon all of its secured obligations in July, 1971, and NBSD “called in” its loans to Brunken. In the latter part of December, 1971, NBSD demanded possession of the collateral and proceeded to prepare the equipment for disposition. It was during this repair process that the Receiver demanded and obtained these assets for sale. According to NBSD’s Exhibit 6, the conceded and contested amounts for preparing the collateral for auction totals $27,236.67.

Defendant NWB’s interest in this litigation arises from its.loans to Brunken which were sought to be protected by an April 7, 1970, financing statement filed with the Secretary of State. NWB concedes that the individual demands made by the three parties exceeds the fund now in the possession of the Receiver which totals $142,149.02.

With this factual background, which will be more fully developed herein, the two major issues can be stated. First, whether or not an unsecured surety, who is called upon to perform, acquires priority in the defaulting contractor’s personal property over secured creditors whose security interests have been perfected in compliance with the South Dakota Uniform Commercial Code provisions. Secondly, if the banks as secured creditors prevail, what are their respective priorities in the fund now held by the Receiver ?

Aetna relies upon two alternative theories to support its position that no Uniform Commercial Code (UCC) filing was required for it to prevail over the secured interests of the two banks. First, it contends that by performance of its suretyship obligations for and on behalf of Brunken, an equitable lien arises in favor of Aetna, which lien relates back to the inception of the surety-ship agreement (the bond application date) for the purposes of determining priorities. In the alternative, should Aetna’s claim be found to be a security interest, it must be considered to be the assignment of a contract right to'an assignee who is also to do the performance under the contract, and, as such, it is expressly excluded from the secured transaction provisions of the UCC. See SDCL 57-35-14 (1967) (UCC Sec. 9-104(f)).

The seeds of invention which propagated Aetna’s first theory were sown by court decisions recognizing the great weight of authority to the effect that a surety company is entitled to be subrogated to the rights of the contractor in the proceeds of the contract as against one asserting a claim for money loaned or advanced to the building contractor. “This is true even where there is an as *293 signment of the right to collect the funds by the contractor to the bank or other lending institution.” National Surety Corporation v. State Bank of Frankfort, 454 S.W.2d 354, 356 (Ky. 1970); see also In re J. V. Gleason, 452 F.2d 1219 (8th Cir. 1971) and cases cited therein.

It is Aetna’s contention that its claim to the proceeds of the sale of the Brunken equipment is not a security interest within the meaning of the UCC as enacted in South Dakota. SDCL 57-1-10 (1967) (UCC Sec. 1-201(37)). The surety propounds a number of arguments in support of this contention, all of which have been previously used to establish a performing surety’s superior claim, whether it be under an equitable lien or a subrogation theory, to retained funds due the defaulting contractor. J. White & R. Summers, Uniform Commercial Code Sec. 22-5 (1972); Comment, Surety vs. Lender: Priority of Claims to Contract Funds, 10 Washburn L.J.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Bank & Trust Co. v. Insurance Co. of the West
132 F.3d 203 (Fifth Circuit, 1997)
State Bank & Trust v. Ins Co of the West
132 F.3d 203 (Fifth Circuit, 1997)
Transamerica Ins. Co. v. Barnett Bank of Marion County, NA
524 So. 2d 439 (District Court of Appeal of Florida, 1988)
United States Fidelity & Guaranty Co. v. United Penn Bank
524 A.2d 958 (Supreme Court of Pennsylvania, 1987)
United States Fidelity & Guaranty Co. v. Leach
438 F. Supp. 295 (M.D. Georgia, 1977)
In Re Merts Equipment Co.
438 F. Supp. 295 (M.D. Georgia, 1977)
General Insurance Co. of America v. Lowry
412 F. Supp. 12 (S.D. Ohio, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
357 F. Supp. 290, 12 U.C.C. Rep. Serv. (West) 388, 1973 U.S. Dist. LEXIS 13938, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aetna-casualty-surety-co-v-j-f-brunken-son-inc-sdd-1973.