AES Puerto Rico, L.P. v. ALSTOM Power, Inc.

429 F. Supp. 2d 713, 2006 U.S. Dist. LEXIS 25036, 2006 WL 1154786
CourtDistrict Court, D. Delaware
DecidedApril 28, 2006
DocketCIV.A. 04-1282-JJF
StatusPublished
Cited by10 cases

This text of 429 F. Supp. 2d 713 (AES Puerto Rico, L.P. v. ALSTOM Power, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AES Puerto Rico, L.P. v. ALSTOM Power, Inc., 429 F. Supp. 2d 713, 2006 U.S. Dist. LEXIS 25036, 2006 WL 1154786 (D. Del. 2006).

Opinion

OPINION

FARNAN, District Judge.

Pending before the Court is ALSTOM Power Inc.’s Motion For Partial Summary Judgment (D.I.91). For the reasons discussed, the Motion will be denied.

I. FACTUAL BACKGROUND

The claims in this case result from the construction of a 454-megawatt coal-fired power plant built in Guayama, Puerto Rico. In April 1996, AES Puerto Rico, L.P. (“AES”) entered into a contract with Duke/Fluor Daniel Carribean, S.E. (“Duke”) for construction of the plant. Duke subcontracted with ALSTOM Power Inc. (“ALSTOM”), which agreed to furnish and construct two boilers and related pollution-control equipment for the power plant. ALSTOM entered into an agreement with Environmental Elements Corporation (“EEC”) to construct the pollution-control equipment. Upon completion of the project, Duke assigned its rights under its contract with ALSTOM to AES.

The Court understands that the pollution-control equipment operates as follows. As coal or feedstock is burned in the boilers, the smoke and ash (“flue gas”) rises out of the top of the combustor. While moving through the boiler, much of the ash is removed. After the flue gas leaves the boiler, it enters the circulating dry scrubbers (“CDS”), which remove sulfur dioxide and cool the flue gas by spraying the gas with an atomized mist of water. 1 The flue gas then enters the electrostatic precip-itators (“ESP”), which consist of an electric field that positively charges the particles of ash in the flue gas. The positively-charged particles are attracted to the ESP “collector plates,” which capture some of the remaining ash before it reaches the smokestack. (D.I. 91 at 4; D.I. 109 at 3).

A. Contentions Of AES

Following construction of the power plant, ALSTOM was required to provide technical support and consultation services to AES in the starting up and initial adjustment of the equipment, referred to as “commissioning.” During commissioning, ALSTOM and EEC deviated, and instructed AES to deviate, from the Operation and Maintenance Manuals (“Operation Manuals”) and modified a number of the operating procedures.

In November 2003, AES discovered that sections of the ESP collector plates in one of the boilers had disintegrated and other sections had come loose. Similar corrosion was discovered in the other boiler unit in January 2004. After each discovery, AES immediately informed ALSTOM. Initially, ALSTOM agreed that the equipment was covered under the accelerated corrosion warranty in the parties’ contract, but insisted that EEC was responsible for paying the claim. Later, ALSTOM contended that AES’ strict compliance with the August 2001 Operation Manual procedures, which had been modified several times, was a condition precedent to ALSTOM’s accelerated corrosion liability.

Due to ALSTOM’s inaction, AES undertook to solve the problem on its own, which AES contends is permitted under *716 the contract. Immediately after discovering the corrosion, AES stabilized the remaining collector plates until it could purchase new plates. AES also installed a reverse osmosis system, which slowed the rate of corrosion. In order to comply with environmental standards, AES also had to contract to purchase a brine crystallizer to turn the brine, a byproduct of the reverse osmosis system, into salt for disposal.

B. Contentions Of ALSTOM

As early as January 2000, EEC stated that the guarantees against corrosion were conditioned upon the use of proper operation and maintenance procedures. In February 2000, ALSTOM and EEC met with Duke and AES personnel to discuss corrosion and the precautions that AES would have to take to prevent it. The drafts of the Operation Manuals also discussed the importance of performing maintenance procedures.

In November 2003, ALSTOM received notification that AES had found corrosion in one of the boilers. ALSTOM immediately sent a specialist to analyze the cause of the corrosion. ALSTOM’s specialist discovered significant corrosion of the ESP collector plates and determined that it was most likely related to low operating temperatures and high chloride content in violation of the Operation Manuals. The specialist took samples of the corroded material for analysis.

Only days after the analysis had begun, AES unilaterally began remedying the corrosion by ordering replacement collector plates. AES also took unilateral action by installing the reverse osmosis system. Such action was taken by AES despite the fact that the contract required mutual agreement as to remedy. On April 30, 2004, AES sent ALSTOM a letter requesting reimbursement for the reverse osmosis system. ALSTOM responded that it was still investigating the cause of the problem and that until it received all pertinent records, it would not be able to complete that investigation.

II. PARTIES CONTENTIONS

ALSTOM contends that any warranty liability for corrosion was subject to a condition precedent in the contract, which provides that the “corrosion guarantee is conditioned upon operation and maintenance of the system in accordance with Contractor’s Operation and Maintenance manuals.” ALSTOM contends that AES failed to comply with the Operation Manuals, and as a result, ALSTOM’s duty to perform under the warranty never arose.

AES contends that there is no condition precedent in the contract, and therefore, the “conditioned upon” language must be read as establishing legal covenants or obligations. AES further contends that even if there is a condition precedent, ALSTOM is estopped from asserting it because AL-STOM instructed AES to deviate from the standards set forth in the Operation Manuals.

III. LEGAL STANDARD

Pursuant to Rule 56(c) of the Federal Rules of Civil Procedure, a party is entitled to summary judgment if a court determines from its examination of “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any,” that there are no genuine issues of material fact and that the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c). To defeat a motion for summary judgment, the non-moving party must “do more than simply show that there is some metaphysical doubt as to the material facts. In the language of the Rule, the non-moving party must come forward with ‘specific facts showing that there is a gen *717 uine issue for trial.’ ” Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 586-87, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986) (citations omitted).

IV. DISCUSSION

A. Whether The Contract Contains A Condition Precedent To ALSTOM’s Liability Under The Corrosion Guarantee Such That The Court Should Grant ALSTOM Summary Judgment

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
429 F. Supp. 2d 713, 2006 U.S. Dist. LEXIS 25036, 2006 WL 1154786, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aes-puerto-rico-lp-v-alstom-power-inc-ded-2006.