AEnergy, S.A. v. General Electric International, Inc.

CourtDistrict Court, D. Connecticut
DecidedJuly 21, 2023
Docket3:22-cv-01055
StatusUnknown

This text of AEnergy, S.A. v. General Electric International, Inc. (AEnergy, S.A. v. General Electric International, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AEnergy, S.A. v. General Electric International, Inc., (D. Conn. 2023).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF CONNECTICUT

AENERGY, S.A., and COMBINED CYCLE POWER PLANT SOYO, S.A., Plaintiffs,

v.

Nos. 3:22-cv-1054 (JAM) GE CAPITAL EFS FINANCING, INC., 3:22-cv-1055 (JAM) Defendant,

and,

GENERAL ELECTRIC INTERNATIONAL, INC., Defendant.

ORDER GRANTING DEFENDANTS’ MOTIONS TO DISMISS Plaintiffs Aenergy, S.A. (“AE”) and Combined Cycle Power Plant Soyo, S.A. (“CCPP”) have filed two related actions against defendants GE Capital EFS Financing, Inc. (“GE Capital”) and General Electric International, Inc. (“GE International”) alleging that the defendants’ tortious conduct caused the plaintiffs to lose out on wind- and energy-related projects with the Angolan government to the tune of roughly $1.1 billion. Both defendants have filed motions to dismiss. They principally argue that the plaintiffs’ suits are precluded by a ruling of the Southern District of New York finding that an earlier incarnation of this lawsuit should be dismissed for forum non conveniens. In the alternative, the defendants argue that the case should be dismissed on grounds of forum non conveniens. Although I decline to find that the prior ruling has preclusive effect, I conclude that forum non conveniens requires dismissal of this lawsuit. I will conditionally grant the motions to dismiss subject to the filing of a stipulation by the defendants with respect to the litigation of this case in Angola. BACKGROUND According to the complaints, AE is a shareholder-owned corporation constituted under the laws of the Republic of Angola and headquartered in Portugal.1 Ricardo Machado, a Portuguese citizen, founded the company in 2012 and owns 99.9% of its stock. See Aenergy, S.A.

v. Republic of Angola, 2021 WL 1998725, at *1 (S.D.N.Y. 2021). CCPP is a wholly owned subsidiary of AE, incorporated in Angola with its principal commercial activities undertaken in Angola.2 In 2013 AE began contracting with corporate affiliates of General Electric Co. to purchase GE-made power products and services for energy projects commissioned by the Angolan Ministry of Energy and Water (“MINEA”).3 After a number of successful projects AE and GE began discussing a “mega” power deal to market to the Angolan government whereby AE would install and service a series of power-plant facilities in Angola using GE-manufactured technology.4 As part of the deal AE agreed to purchase fourteen TM2500s (a gas turbine GE describes as a “power plant on wheels”) from GE for anticipated deployment in Angola.5

AE and GE knew that to finance these energy projects the Angolan government would have to secure an international source of funding.6 So in 2017 Jeff Immelt—then-CEO of GE Co.—travelled to Angola to meet with then-President José Eduardo Dos Santos of Angola.7 The two reached an agreement under which GE Capital would provide $1.1 billion to Angola’s

1 Doc. #3/1054 at 4 (¶ 9); Doc. #4/1055 at 4 (¶ 9). 2 Doc. #3/1054 at 4 (¶ 10); Doc. #4/1055 at 4 (¶ 10). 3 Doc. #3/1054 at 7-8 (¶¶ 25, 28); Doc. #4/1055 at 7-8 (¶¶ 25, 28). 4 Doc. #3/1054 at 9-10 (¶¶ 29-30); Doc. #4/1055 at 9 (¶¶ 29-30). 5 Doc. #3/1054 at 9, 11-14 (¶¶ 28(c), 35, 39, 42-43); Doc. #4/1055 at 8-9, 11-14 (¶¶ 28(c), 35, 39, 42-43). 6 Doc. #3/1054 at 10 (¶ 31); Doc. #4/1055 at 9-10 (¶ 31). 7 Doc. #3/1054 at 10 (¶ 32); Doc. #4/1055 at 10 (¶ 32). finance ministry (“MINFIN”), which Angola would draw up front to prepay AE for the agreed-to energy projects.8 GE Capital and GE Co. approved the $1.1 billion credit facility in late June or early July 2017 based on their assumption that Angola had agreed to purchase at least twelve TM2500s paid for upfront.9 The President of Angola similarly approved the financing plan, and then at the

end of July 2017 AE and MINEA executed a total of thirteen “On-Sale Contracts” (“OSCs”) in the amount of $1.148 billion.10 But the OSCs collectively called for only eight TM2500 turbines—six fewer than the total number AE had agreed to buy from GE and four fewer than GE had anticipated when it approved the financing deal.11 AE promptly sent the signed OSCs to GE.12 Machado then explained to Wilson da Costa—who was employed by GE International but represented GE Capital in Angola—that the signed contracts covered only eight turbines.13 Unbeknownst to AE however, da Costa then informed his colleagues at GE Co. and GE Capital that the OSCs covered twelve TM2500s and that AE would use its margin on the OSCs to pay for two additional turbines, bringing the total back up to the originally agreed-to fourteen turbines.14

In August 2017 representatives from AE and GE Capital met to begin planning for the financing disbursement.15 The GE participants were surprised to learn that the existing OSCs called only for eight turbines, while AE was surprised to learn that GE expected to be paid for fourteen turbines.16 To resolve the discrepancy AE agreed to use its “best efforts” to amend its

8 Doc. #3/1054 at 15 (¶ 44); Doc. #4/1055 at 15 (¶ 44). 9 Doc. #3/1054 at 18 (¶ 48); Doc. #4/1055 at 18 (¶ 48). 10 Doc. #3/1054 at 19-20 (¶ 50); Doc. #4/1055 at 19-20 (¶ 50). 11 Doc. #3/1054 at 21 (¶ 51); Doc. #4/1055 at 20-21 (¶ 51). 12 Doc. #3/1054 at 21-22 (¶ 54); Doc. #4/1055 at 21-22 (¶ 54). 13 Ibid. 14 Doc. #3/1054 at 22 (¶ 55); Doc. #4/1055 at 22 (¶ 55). 15 Doc. #3/1054 at 22-23 (¶ 56); Doc. #4/1055 at 22-23 (¶ 56). 16 Ibid. contracts with Angola to add six turbines to the existing OSCs without increasing the overall cost.17 When AE explained that Angola could only formally amend the OSCs via a presidential decree, GE responded that it could rely on “technical letters” to confirm the addition of the first four turbines as long as those letters met certain wording requirements.18

AE subsequently asked MINEA to sign amendment letters adding two additional turbines to OSCs 7 and 11 using the language requested by GE.19 Angola responded, not with a firm commitment but with conditional intent letters stating their agencies would consider purchasing four additional turbines subject to technical analyses and legal review.20 The intent letters were provided to da Costa, who told Machado that he would transmit them to relevant individuals at GE.21 Unbeknownst to AE, after receiving the documents from Angola, unspecified “GE employees” used Photoshop to edit the letters to reflect the language GE wanted.22 Then on the evening of October 12, “from the safety and secrecy of his home in Luanda,” da Costa took photos of the forged letters and emailed those photos to various GE employees, passing them off as the real documents.23 In his email attaching the forged letters, da Costa reported that “[w]e got

the contract number 7 signed with the languages that we agreed on and countersigned by AE. We then . . . got contract number 11 amendment signed with the language approved by Brad [Galvin of GE Capital] and then counter signed by AE.”24 Leslie Nelson, da Costa’s then-supervisor at

17 Doc. #3/1054 at 25-26 (¶ 61(a)); Doc. #4/1055 at 25-26 (¶ 61(a)). 18 Doc. #3/1054 at 26, 29 (¶¶ 61(b), 70); Doc. #4/1055 at 26, 29 (¶¶ 61(b), 70). 19 Doc. #3/1054 at 29 (¶ 68); Doc. #4/1055 at 29 (¶ 68). 20 Doc. #3/1054 at 29-30 (¶ 71); Doc. #4/1055 at 29-30 (¶ 71). 21 Doc. #3/1054 at 30 (¶ 72); Doc. #4/1055 at 30 (¶ 72). 22 Doc. #3/1054 at 30 (¶ 73); Doc. #4/1055 at 30 (¶ 73). 23 Doc. #3/1054 at 30-31 (¶ 74); Doc. #4/1055 at 30-31 (¶ 74). 24 Doc. #3/1054 at 31 (¶ 75); Doc. #4/1055 at 31 (¶ 75). GE International, also assured another GE executive a few days later that the critical amendments had been obtained from MINEA.25 With all parties under the impression that the problem had been resolved, Angola finally drew its initial disbursement from the GE Credit Facility in December 2017.26 The request

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abdullahi v. Pfizer, Inc.
562 F.3d 163 (Second Circuit, 2009)
Seales v. Panamanian Aviation Co.
356 F. App'x 461 (Second Circuit, 2009)
Gulf Oil Corp. v. Gilbert
330 U.S. 501 (Supreme Court, 1947)
Piper Aircraft Co. v. Reyno
454 U.S. 235 (Supreme Court, 1982)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Aguinda v. Texaco, Inc.
303 F.3d 470 (Second Circuit, 2002)
Lust v. Nederlandse Programma Stichting
501 F. App'x 13 (Second Circuit, 2012)
Palacios v. THE COCA-COLA CO.
757 F. Supp. 2d 347 (S.D. New York, 2010)
Daimler AG v. Bauman
134 S. Ct. 746 (Supreme Court, 2014)
Martinez v. Bloomberg LP
740 F.3d 211 (Second Circuit, 2014)
Western Dermatology Consultants, P.C. v. VitalWorks, Inc.
143 A.3d 564 (Supreme Court of Connecticut, 2016)
Hernandez v. United States
939 F.3d 191 (Second Circuit, 2019)
Aenergy, S.A. v. Republic of Angola
31 F.4th 119 (Second Circuit, 2022)
Norex Petroleum Ltd. v. Access Industries, Inc.
416 F.3d 146 (Second Circuit, 2005)
Kim v. Kimm
884 F.3d 98 (Second Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
AEnergy, S.A. v. General Electric International, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/aenergy-sa-v-general-electric-international-inc-ctd-2023.