Advanced Tubular Products, Inc. v. Solar Atmospheres, Inc.

149 F. App'x 81
CourtCourt of Appeals for the Third Circuit
DecidedSeptember 16, 2005
Docket04-2016
StatusUnpublished
Cited by7 cases

This text of 149 F. App'x 81 (Advanced Tubular Products, Inc. v. Solar Atmospheres, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advanced Tubular Products, Inc. v. Solar Atmospheres, Inc., 149 F. App'x 81 (3d Cir. 2005).

Opinion

OPINION

SLOVITER, Circuit Judge.

This case comes to us on appeal by Advanced Tubular Products (Tubular) from an order of the District Court granting summary judgment to defendant Solar Atmospheres (Solar). On appeal, we must determine when the contract between the two parties was formed and whether the contract included Solar’s “Terms of Sale.” We must also decide whether the limited remedies available to Tubular under Solar’s terms failed in their essential purpose and thus barred summary judgment. Lastly, we must determine whether Solar fraudulently induced Tubular to enter into the contract and whether the “gist of the *83 action” doctrine bars Tubular’s fraud claim.

I.

Tubular was a Kentucky corporation that manufactured stainless steel tubing. Originally, the majority of the company’s business was derived from the automotive industry but in 2000/2001 Tubular decided to begin selling tubing to the oil and gas industry. As a result, Tubular contacted Solar regarding Solar’s ability to provide heat treatment for Tubular’s stainless steel tubing. Tubular met with Solar and discussed the demands of the particular heat treatment application needed for the job. This treatment included the specification standard known as ASTM A789. After being informed of the need to use ASTM A789, Solar assured Tubular that it was familiar with the process and that “they could handle it.” App. at 2.

On February 19, 2001, Tubular sent Solar three sample cods of tubing, labeled “sample,” to Solar for treatment. These sample tubes were heat treated by Solar and then sent back to Tubular to be tested. After receiving the heat treated samples from Solar, Tubular tested them for “sigmaphase” (improper heat treatment) at “a variety of points through the coil.” App at 113. After the February 19, 2001 shipment, Tubular sent another two sets of “sample” coils to Solar to be heat treated and then returned for testing. After conducting these tests, Tubular was satisfied that Solar could perform the work, and on March 19, 2001, Tubular began shipping larger quantities of tubes to Solar and omitting the “sample” label.

On February 20, 2001, the day after Tubular sent its first shipment of sample coils, Solar faxed a quotation for the price of its heating services and mailed a hard copy of the quotation along with the Terms of Sale to Tubular. The faxed quotation referred to the Terms of Sale but did not include them. The Terms of Sale included a limitation of liability and remedies. The limited liability provision stated that “seller’s liability shall not exceed twice the amount of seller’s charges for services performed on any material ... except by written agreement signed by an officer of seller.” App at 3.

After Solar treated the non-sample tubes, Tubular sent them to Tubeco, Inc., which in turn sold them to a contractor in Texas. Shortly thereafter, Tubular was informed that the tubing was brittle and failed as a result of improper “sigma-phase.” App. at 6. Because of this failure, Tubular’s customers refused to pay Tubular and Tubular alleges that as a result it went out of business.

Tubular brought suit against Solar in the United States District Court for the Eastern District of Pennsylvania based on diversity jurisdiction, alleging breach of oral contract and fraudulent misrepresentation arising out of the services provided by Solar. Solar filed a motion to dismiss, asserting that the contract between the parties limited liability to an amount less than $75,000 and thereby divested the District Court of jurisdiction. On September 24, 2003, the Court denied the motion without prejudice based on the need for further discovery. Limited discovery regarding the contract formation was taken after which Solar again moved for summary judgment.

Thereafter, the District Court granted Solar’s motion for summary judgment. The District Court found that the limited liability clause was a term of the contract. According to the District Court, the Terms of Sale were incorporated by reference in the quotation sent by Solar and Tubular manifested its assent to these terms when it repeatedly sent its tubing to Solar for *84 heat treatment. The District Court further found this type of limited liability clause is the type routinely enforced between sophisticated parties and that it was reasonable. Therefore, the District Court held that it was an enforceable part of the contract.

The District Court also held that Tubular’s claim that Solar fraudulently induced it to enter into the contract was barred by the “gist of the action” doctrine. Under this doctrine, a plaintiff is barred from bringing a tort claim when such a claim is merely another way of stating the party’s breach of contract claim or when the success of such a claim is wholly dependant upon the terms of the contract. See Sunquest Info. Sys., Inc. v. Dean Witter Reynolds, Inc., 40 F.Supp.2d 644, 651 (W.D.Pa. 1999). The District Court held that under Pennsylvania law the “gist of the action” doctrine may not apply to claims of fraud in the inducement, but that Tubular’s claim was not one of fraudulent inducement but “a question of performance of the contract,” i.e., whether Solar in fact properly heat treated the coils. App. at 13-14. Therefore, the Court concluded that the gist of the action doctrine barred Tubular’s fraud claim. 1

II.

Tubular raises three issues on appeal. First, Tubular argues that the contract with Solar was formed before it received Solar’s Terms of Sale. Therefore, Tubular contends, the terms were not part of the original contract and that they could not have subsequently become part of the contract because they materially altered the bargain. Accordingly, Tubular argues that the District Court erred in determining that the terms were part of the contract. In addition, Tubular argues that the District Court erred in granting summary judgment because the limited remedy failed in its essential purpose. Lastly, Tubular argues that the District Court erred in finding that its fraud claim was barred by the “gist of the action” doctrine.

A.

The District Court found that the Terms of Sale were included in the contract because they were incorporated by reference in the February 20, 2001 offer. That finding suffers from the fact that the faxed offer did not actually include a copy of the Terms of Sale. However, because we agree with Solar that the contract was not formed until March 19, well after Tubular received the terms, we conclude that Tubular was bound by the limited liability provision.

It is undisputed that the first set of tube coils were sent on February 19, a day before Solar faxed its offer, and that these coils were labeled “sample.” It is clear that Solar’s ability to effectively heat treat the sample tubes was a condition precedent to Tubular’s acceptance of Solar’s offer. Once Solar had satisfied this condition precedent by effectively heat treating the sample tube coils, Tubular accepted Solar’s offer by shipping non-sample tube coils on March 19. Accordingly, because Tubular had received the terms of sale by that date and because there is no record of any objection, 2 the Terms of Sale were part of the contract.

B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
149 F. App'x 81, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advanced-tubular-products-inc-v-solar-atmospheres-inc-ca3-2005.