Advanced Energy United v. FERC

Court of Appeals for the D.C. Circuit·Decided July 31, 2026·No. 23-1282·Published

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued September 26, 2025 Decided July 31, 2026

No. 23-1282

ADVANCED ENERGY UNITED, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

CONSUMERS ENERGY COMPANY, ET AL., INTERVENORS

Consolidated with 23-1284, 23-1289, 23-1297, 23-1299, 23-1305, 23-1310, 23-1312, 23-1313, 23-1320, 23-1327, 23-1330, 23-1346, 24-1093, 24-1106, 24-1112, 24-1136, 24-1137, 24-1139, 24-1140, 24-1141

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

John Lee Shepherd Jr. and Elbert Lin argued the causes for Transmission Provider Petitioners. With them on the briefs were Catherine P. McCarthy, Joshua Kirstein, Paul A. Colbert,

Blake Grow, Sara Weinberg, Lisa B. Luftig, Christopher D. Supino, Ilia Levitine, Ted Murphy, Andrew W. Tunnell, Wendy N. Reed, Matthew J. Binette, Abraham F. Johns, III, Lyle D. Larson, Abigail C. Fox, Robert V. Eckenrod, Christopher R. Jones, Antonia M. Douglas, Adrienne Thompson, Wendy B. Warren, David S. Berman, Elizabeth P. Trinkle, and Priyanka Vashisht. Ryan J. Collins, Kevin M. Leroy, Jason Tompkins, Misha Tseytlin, and Susan J. LoFrumento, entered appearances.

Melissa Alfano argued the causes for Association Petitioners. With her on the briefs were Ben Norris, Gabriel Tabak, Jeremy McDiarmid, Nicholas M. Gladd, and Kelsey C. Catina.

Robert H. Solomon, Solicitor, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were David L. Morenoff, Acting General Counsel, and Susanna Y. Chu and J. Houston Shaner, Attorneys.

Alexander L. Tom argued the cause for intervenors. With him on the brief were Christine A. Powell, Ada Statler, Nick Lawton, Linnet Davis-Stermitz, John Moore, Caroline Reiser, Gregory E. Wannier, Justin Vickers, Adam Kurland, Ben Norris, Melissa Alfano, Gabriel Tabak, and Jeremy McDiarmid. Danielle Fidler entered an appearance.

Before: MILLETT, WALKER, and CHILDS, Circuit Judges.

Opinion for the Court filed PER CURIAM.

PER CURIAM: The on-ramps to our nation’s power grid are in the middle of a decades-long traffic jam. At the end of 2023, roughly 2,600 gigawatts of proposed generating and storage capacity were stuck in interconnection queues, waiting years

for the completion of the studies needed before they can connect to the transmission system. Solar, wind, and energy storage accounted for about 95 percent of that capacity.1 That 0F

backlog represents more than twice the country’s installed generation capacity, which stood at roughly 1,200 gigawatts in 2023. 2 The Federal Energy Regulatory Commission (“FERC”)

1F

concluded that the existing process could not keep up with the “unprecedented” volume of interconnection requests and that the resulting delays were producing unjust and unreasonable conditions in wholesale markets.

Order 2023 is FERC’s attempt to clear that traffic. Acting under its remedial authority, FERC directed every transmission provider under its jurisdiction to overhaul how it processes interconnection requests—moving from a serial, project-byproject model to clustered studies, requiring substantial deposits, imposing withdrawal fines, setting firm study deadlines, and backing those deadlines with automatic late fees.

Those reforms drew fire from several directions.

Transmission providers and system operators argue that FERC exceeded its authority under the Federal Power Act, violated due process, and ran afoul of the Administrative Procedure Act by layering “strict-liability penalties” on top of already-revised tariffs. Clean-energy developers challenge the rule from the opposite flank, attacking what they see as an arbitrary safe harbor that shields transmission providers from penalties when

1 Joseph Rand et al., Queued Up: 2024 Edition, Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2023, Lawrence Berkeley Nat’l Lab’y, 14 (Apr. 2024), https://perma.cc/Y6KF-KX55.

2 Electricity explained, U.S. Energy Info. Admin. (July 16, 2024), https://perma.cc/RFE7-LE2A.

their cost estimates prove wildly wrong. FERC and supporting intervenors defend the rule as a measured response to a systemic breakdown in the interconnection process.

These petitions ask whether FERC lawfully adopted that nationwide interconnection regime and whether FERC reasonably explained how the rule balances the interests of transmission providers, interconnection customers, and ultimate consumers.

We conclude that FERC acted within its authority and reasonably explained its order. Accordingly, we deny the petitions.

I. Background

A

Under the Federal Power Act, FERC regulates the transmission of electric energy in interstate commerce and wholesale sales of that energy. See 16 U.S.C. § 824(b)(1). The Act requires that “all rates and charges” for those services, and the rules and practices that affect them, remain “just and reasonable” and not unduly discriminatory or preferential. Id. §§ 824d(a), 824e(a). That mandate extends to the terms on which new generators connect to the transmission grid because interconnection procedures and costs directly affect wholesale rates and competition. See Improvements to Generator Interconnection Procedures and Agreements, Order Addressing Arguments Raised on Rehearing, Setting Aside Prior Order, in Part, and Granting Clarification, Order No. 2023-A, 186 FERC ¶ 61,199, at P 315 (2024) (“Order 2023- A”) (“queue backlogs are causing unjust and unreasonable rates and . . . must, therefore, be remedied pursuant to our statutory mandate”).

Before a new generating facility can inject power into the grid, the transmission provider must complete technical studies to determine whether the system can safely accommodate the new resource and what network upgrades would be needed. Those studies often involve not only the transmission owner whose facilities the project will connect to, but also neighboring “affected systems” that may be affected when the new resource comes online. Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023, 184 FERC ¶ 61,054, at P 13 n.22 (2023) (“Order 2023”). Under FERC’s standard interconnection procedures, the generator enters the queue, posts deposits, undergoes successive studies, and eventually receives an interconnection agreement that identifies any required upgrades and assigns their costs.

Over the last decade, that process has strained under the volume of new projects. FERC found that the combined capacity of projects sitting in interconnection queues across the country was nearly equal to the entire existing United States generation fleet. Order 2023 at P 30. 3 It noted, too, that more 2F

than seventy percent of the interconnection requests submitted between 2000 and 2017 were eventually withdrawn. Id. at P 49. FERC explained that late-stage withdrawals were increasing and could require transmission providers to redo studies, raising costs and further delaying projects behind them in the queue. Id.

FERC concluded that these backlogs, delays, and repeated restudies were hampering the timely development of new generation and “stifl[ing] competition” in wholesale markets,

3 And now surpasses it. See notes 1 & 2, supra, and accompanying text.

producing unjust and unreasonable conditions under the Federal Power Act. Order 2023 at PP 37, 44. Order 2023 is FERC’s response to those findings.

B

1

Federal Power Act—Section 205. The Federal Power Act sets out two major avenues through which FERC can regulate rates and related aspects of our energy grid: Sections 205 and 206. Section 205 governs utility-initiated changes to rates and practices. As relevant here, it provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Advanced Energy United v. FERC, (D.C. Cir. 2026).

Advanced Energy United v. FERC (Advanced Energy United v. FERC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

§ 824
16 U.S.C. § 824
§ 824d
16 U.S.C. § 824d
§ 824e
16 U.S.C. § 824e
§ 706
5 U.S.C. § 706
§ 825l
16 U.S.C. § 825l
§ 825o
16 U.S.C. § 825o