Adler v. Seligman of Florida, Inc.

438 So. 2d 1063
CourtDistrict Court of Appeal of Florida
DecidedOctober 19, 1983
Docket81-1897
StatusPublished
Cited by5 cases

This text of 438 So. 2d 1063 (Adler v. Seligman of Florida, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adler v. Seligman of Florida, Inc., 438 So. 2d 1063 (Fla. Ct. App. 1983).

Opinion

438 So.2d 1063 (1983)

Samuel I. ADLER, John R. Frankenfield, Charles Donner, Howard Mescon, al Ketchum, J & R Forming Co., and Versatile Construction Systems, Inc., a Florida Corporation, Appellants,
v.
SELIGMAN OF FLORIDA, INC., Fidelity and Deposit Company of Maryland, and J & R Crane Service, et al., Appellees.

No. 81-1897.

District Court of Appeal of Florida, Fourth District.

October 19, 1983.

*1064 Sam Daniels of Daniels & Hicks, Miami, and Marc Cooper of Greene & Cooper, P.A., Miami, for appellants.

Daniel Neal Heller of Heller & Kaplan, Miami, for appellee, Seligman of Florida, Inc.

Joel S. Perwin of Podhurst, Orseck, Parks, Josefsberg, Eaton, Meadow & Olin, P.A., Miami, for amicus curiae.

BERANEK, Judge.

This is an appeal from a final judgment finding a breach of a fiduciary duty and awarding Seligman of Florida, Inc., $615,564.65 *1065 in compensatory damages, $204,401.19 in prejudgment interest, and $1,310,000.00 in punitive damages. These damages were awarded against Samuel Adler, John Frankenfield, Charles Donner, Howard Mescon, Al Ketchum, J & R Forming Company, and Versatile Construction Systems, Inc., who now appeal asserting numerous errors. The action was originally filed as a mechanic's lien foreclosure in 1974 by one of the subcontractors on a condominium construction project. Seligman of Florida, Inc., the builder, counterclaimed asserting conspiracy and breach of fiduciary duty against various individuals and corporate counterdefendants, all of whom had been involved in the project. Damages for defective construction were also sought. A non-jury trial was concluded on April 27, 1976, after which both sides submitted proposed findings of facts and conclusions of law. At some time thereafter, the court advised counsel of its intention to rule in favor of the counter-plaintiff, Seligman of Florida, Inc. This advice apparently occurred at an informal conference. The matter was then taken under advisement. In October, 1979, the counter-defendant made a motion for a new trial stating that the court could not rule on the matter which had then been under advisement for three and one-half years. The motion for new trial asserted that the delay was simply too long. In December, 1979, the court entered an order denying the motion for new trial and therein stated it intended to rule and render a judgment at the first possible moment. More than a year later, after four and one-half years, the trial court issued a final judgment dated January 6, 1981. The last brief was filed before this court on February 4, 1983, and oral argument occurred on May 17, 1983.[1] We reverse in part and remand for further proceedings.

We start by condemning the four and one-half year delay but caution that we do not reverse on this basis. However, in view of this delay, we will dispose of this matter without extended discussion.

The facts as found in the final judgment are briefly as follows. Seligman, president of various real estate development companies, and Adler, also a builder, entered into a joint venture to plan, build, and sell a 531 unit condominium project. Seligman was to provide the land and money and Adler was responsible for the actual construction. Adler involved various corporations and individuals in the project, all of whom conspired to siphon off the profits which should have belonged to Seligman or the joint venture. The devious nature of the conspiracy was far reaching and much of the construction actually performed was defective. Although the joint venture was formally terminated before substantial construction occurred, the conspiracy was conceived during its existence. The project was initially planned using ground level cast-in-place concrete floors over pads and upper level prestressed concrete floors. Adler changed from this initial plan to a flying form system with a flat plate design and did so in bad faith and without consultation with Seligman. The flat plate flying form system was more expensive than the initial plan. The change in plans was done so Versatile could successfully bid the job and siphon off the profits. Adler failed to disclose his own personal ownership interest in Versatile Construction System, Inc., the corporation subcontractor involved in the flying form system. This system of construction was used solely for the benefit of Adler and the others who conspired against Seligman. All of the actions of the various counterdefendants constituted a conspiracy to the detriment of Seligman. Adler breached his fiduciary duty to Seligman.

There are eleven points on appeal.

POINT I.

WHETHER THE $217,000 AWARD FOR INCREASED CONSTRUCTION COST IS BASED ON SUBSTANTIAL COMPETENT EVIDENCE.

The trial court awarded over $217,000 as the increased cost of using the flying *1066 form system as opposed to the less expensive system on which the project was initially designed. We find the evidence as to Seligman's actual costs of construction to have been lacking and thus reverse this award. The Seligman company actually constructed the building after the termination of the joint venture and did so using the flying form system. The evidence presented in support of this element of damage was merely an estimate rather than the actual cost figure. We reverse on the authority of Safe-T-Lawn, Inc. v. Agricultural Engineering Association, 235 So.2d 25 (Fla. 3d DCA 1970).

POINTS II AND III.

WHETHER THE $247,000 AWARD FOR "STEP-DOWN" CONSTRUCTION IN THE INDIVIDUAL UNITS IS PROPER WHEN MOST OF THE UNITS HAD ALREADY BEEN SOLD.

WHETHER THE $59,000 AWARD FOR RECONSTRUCTION OF ALL THE STAIRWELLS IS PROPER WHEN (1) MOST OF THE UNITS HAD BEEN SOLD AND (2) THERE WAS NO PROOF THAT ALL THE STAIRWELLS WERE DEFECTIVE.

The trial court awarded Seligman damages for defendants' failure to build each unit with a "step-down." One hundred thirty units were completed. Seligman owned only 46 of these units, having sold the balance prior to trial. There was no showing that Seligman was actually responsible or would ever be compelled to build "step-downs" in the units previously sold. Further, Seligman was awarded damages for total reconstruction of all 42 stairwells. There was no showing of Seligman's liability to rebuild these stairwells. These damages appear to have been awarded under the theory of breach of a fiduciary duty in that the "step-downs" were part of the initial design but not part of the flat plate flying form design. The damages here were improper because they did not involve actual damages to Seligman, but instead were in the nature of damages for repairs which might occur in the future. On retrial, Seligman shall be entitled to recover future damages only if it can be shown that the repairs will necessarily occur and that Seligman will be responsible for them. Damages, if any, arising from diminution in value may be the subject of amended pleadings and proof on retrial.

POINT IV.

WHETHER THE $14,232.16 AWARD FOR DELAY DAMAGES IS SUPPORTED BY SUBSTANTIAL COMPETENT EVIDENCE.

No error has been made to appear under this point and said amount is thus affirmed.

POINT V.

WHETHER THE LOWER COURT WAS CORRECT IN HOLDING ALL THE COUNTERDEFENDANTS LIABLE FOR THE COMPENSATORY DAMAGE AWARDS.

The trial court awarded $615,564.65 in compensatory damages and $204,401.19 in prejudgment interest. These awards were jointly and severally against Adler, Versatile, J & R Forming, Frankenfield, Donner, Mescon, and Ketchum. We hold that these damages were improperly assessed against Donner and Mescon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pulla v. Amoco Oil Co.
882 F. Supp. 836 (S.D. Iowa, 1994)
Rety v. Green
546 So. 2d 410 (District Court of Appeal of Florida, 1989)
Adler v. Seligman of Florida, Inc.
492 So. 2d 730 (District Court of Appeal of Florida, 1986)
Flagship Nat. Bank v. Gray Distribution Syst.
485 So. 2d 1336 (District Court of Appeal of Florida, 1986)
Burkhart v. Kroeger Concrete Products, Inc.
468 So. 2d 469 (District Court of Appeal of Florida, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
438 So. 2d 1063, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adler-v-seligman-of-florida-inc-fladistctapp-1983.