Adkins Ltd. Partnership v. O St. Management, LLC

District of Columbia Court of Appeals·Decided July 14, 2022·No. 20-CV-13·Published

Opinion

Notice: This opinion is subject to formal revision before publication in the Atlantic and Maryland Reporters. Users are requested to notify the Clerk of the Court of any formal errors so that corrections may be made before the bound volumes go to press.

DISTRICT OF COLUMBIA COURT OF APPEALS No. 20-CV-13

ADKINS LIMITED PARTNERSHIP, APPELLANT, V.

O STREET MANAGEMENT, LLC, APPELLEE.

Appeal from the Superior Court of the District of Columbia (CAB-8137-18)

(Hon. William M. Jackson, Trial Judge)

(Argued April 20, 2021 Decided July 14, 2022)

Ronald C. Jessamy, with whom Robert L. Bell was on the brief, for appellant.

Paul Kiernan for appellee.

Before BLACKBURNE-RIGSBY, Chief Judge, DEAHL, Associate Judge, and WASHINGTON, Senior Judge.

DEAHL, Associate Judge: In 2001, Adkins Limited Partnership and O Street Management (OSM) jointly formed O Street Roadside, LLC, to develop a large piece of real estate in the District’s Shaw neighborhood. The death of one Adkins partner and the incapacitation of another triggered a buyout provision in Roadside’s operating agreement, allowing OSM to buy Adkins out of its seventy-five percent

interest in Roadside. That led to an initial round of litigation, and in 2009, the Superior Court ruled that OSM was entitled to buy Adkins out of its interest. We affirmed that decision the following year. In 2012, the Superior Court issued a second order resolving the only issue left open by the first round of litigation—the buyout price that OSM would have to pay to acquire Adkins’ ownership interest in Roadside. The court confirmed the price as $721,000, and we again affirmed.

For various reasons, OSM never actually bought Adkins out of its interest in Roadside. Each party casts blame on the other for that failure. OSM complains that Adkins refused to accept the payments it tendered shortly after the buyout price was set. Adkins counters that it had not exhausted its appeals at that point, and that once it had done so in 2013, it made clear it was ready to accept payment and settle, but OSM refused. In 2018, after repeated failed attempts to procure the buyout payment from OSM, Adkins recorded the 2012 order setting the buyout price and filed a complaint in the Superior Court to enforce it as a “final judgment or final decree for the payment of money.” See D.C. Code § 15-101 (2012 Repl.). The trial court dismissed Adkins’ complaint, ruling that the 2012 order was not a “final judgment or final decree for the payment of money” and was therefore not enforceable as a money judgment under D.C. Code § 15-101.

Adkins now appeals, contending that the 2012 order was an enforceable money judgment under § 15-101. In the alternative, it argues that it was deprived of its interest in Roadside without just compensation, in violation of the Fifth Amendment’s Takings Clause. We disagree with Adkins on both points and affirm.

I.

This dispute has come before this court twice before. Adkins Ltd. P’ship v. O St. Mgmt., No. 09-CV-1067, Mem. Op. & J. (May 20, 2010) (Adkins I); Adkins Ltd. P’ship v. O St. Mgmt., 56 A.3d 1159 (D.C. 2012) (Adkins II). In 2001, Adkins and OSM became the joint owners of Roadside, which was formed to manage valuable real estate that was previously owned by Adkins alone. The real estate is located at the site of the historic O Street Market, at 9th and O Streets NW, and it now houses a multi-use development, including a Giant supermarket. Adkins II, 56 A.3d at 1162. Adkins contributed the property to Roadside, and received a seventy-five percent interest in the venture. OSM acquired the remaining twenty-five percent interest in Roadside, and in exchange agreed to pay off substantial liens encumbering the property and other obligations of Adkins. Adkins I, supra, at 2.

In 2008, one Adkins partner died and the other was deemed incapacitated, so that the partnership was dissolved. This triggered an “Optional Buy-Out” provision

in the Roadside operating agreement, which permitted OSM to purchase Adkins’ interest in Roadside at fair-market value, with twenty-five percent down and the balance payable in installments over a period of five years. OSM filed suit in the Superior Court for a declaratory judgment that it could enforce the buyout provision, and the court ruled in 2009 that OSM was entitled to buy Adkins out of its interest. This court affirmed that ruling the following year in Adkins I.

After that affirmance, the only remaining dispute between the parties was the buyout price that OSM would have to pay Adkins in exchange for its interest in Roadside. Per Roadside’s operating agreement, in the event Adkins and OSM failed to agree to a purchase price, the price would be determined via an appraisal process. At the first stage of that process, each party would appoint an appraiser to assess the fair-market value of Adkins’ interest. If the results of those appraisals were within $50,000, the purchase price would be the average of the two. If the appraisals were further apart than $50,000, that would trigger the second stage of the appraisal process, in which a third and neutral appraiser would be appointed. The median of the three appraisals, i.e., the price in the middle, would then be set as the buyout price.

The parties did not agree on a purchase price, and their appointed appraisers were tens of millions of dollars apart. Adkins’ appraiser valued Adkins’ interest at $22 million, while OSM’s appraiser assessed Adkins’ interest as worth only $721,000, or about 3% of Adkins’ valuation. The chasm between the two appraisals stemmed from Adkins’ appraiser calculating its ownership interest as a fee simple interest, whereas OSM’s appraiser assessed it as a leased fee interest. Adkins, 56 A.3d at 1163. The difference between the two led to a third appraiser being appointed. The court directed the third appraiser to treat Adkins’ interest as a leased fee interest—in line with OSM’s appraiser—and the third appraiser concluded the Adkins’ interest was worth $660,889. That left $721,000 as the middle and therefore controlling figure for buying out Adkins’ interest. OSM promptly wrote to Adkins offering to settle at that price. Adkins refused, contending that the appraisal had been “predicated on factual and legal errors so egregious that the report, among other things, can be deemed irrational, arbitrary and capricious.”

In response to Adkins’ refusal to settle, OSM moved the Superior Court to confirm the $721,000 buyout price and order settlement. In its motion, OSM asked the court to “direct[] the execution of appropriate documents and payment of required amounts so that the buyout is completed no later than August 2, 2011.” Around the same time, OSM began depositing settlement funds—paid in

installments as dictated by the agreement—into the Superior Court registry, “[i]n order to avoid any argument that [OSM] had not complied with its payment obligations.” The court granted OSM’s motion, confirmed the valuation, and ordered settlement, though it did not order that settlement be completed by any particular date, as OSM had requested. 1 The court also returned to OSM all payments it had paid into the court registry.

We affirmed the trial court’s decision in a published opinion. Adkins II, 56 A.3d at 1169. We explained that, following our 2010 decision, the “only issue left to be decided” was “how much [OSM] must pay [Adkins] in the buy-out,” id. at 1165 (emphasis added), and agreed with the Superior Court that “$721,000 was the price OSM had to pay Adkins” in order to buy it out. Id. at 1164-65 (emphasis added). Adkins, still dissatisfied with what it believed to be an erroneous valuation, unsuccessfully petitioned this court for en banc review, and then petitioned the Supreme Court for a writ of certiorari, which was likewise denied. 569 U.S. 1005 (May 28, 2013) (No. 12-1283).

1 In fact, the court did not rule on OSM’s motion until January 2012, more than five months after the date that OSM had sought to establish as a deadline for settlement.

Free access — add to your briefcase to read the full text and ask questions with AI

Adkins Ltd. Partnership v. O St. Management, LLC, (D.C. 2022).

Adkins Ltd. Partnership v. O St. Management, LLC (Adkins Ltd. Partnership v. O St. Management, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bankers Trust Co. v. Mallis
435 U.S. 381 (Supreme Court, 1978)
Bolden v. Bolden
376 A.2d 430 (District of Columbia Court of Appeals, 1977)
Robinson v. Georgetown Court Condominium, LLC
39 A.3d 1286 (District of Columbia Court of Appeals, 2012)
Adkins Ltd. Partnership v. O Street Management, LLC
56 A.3d 1159 (District of Columbia Court of Appeals, 2012)
Staples v. Warren
46 App. D.C. 363 (D.C. Circuit, 1917)