Adco Services, Inc. v. Bullard

628 N.E.2d 772, 256 Ill. App. 3d 655, 195 Ill. Dec. 308
CourtAppellate Court of Illinois
DecidedDecember 21, 1993
Docket1-92-3405
StatusPublished
Cited by10 cases

This text of 628 N.E.2d 772 (Adco Services, Inc. v. Bullard) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adco Services, Inc. v. Bullard, 628 N.E.2d 772, 256 Ill. App. 3d 655, 195 Ill. Dec. 308 (Ill. Ct. App. 1993).

Opinion

JUSTICE HARTMAN

delivered the opinion of the court:

Plaintiff, Adco Services, Inc. (Adco), filed a four-count complaint alleging libel against defendants, Ronald Bullard and A. B. Gamma, Inc., based upon two letters written by Bullard concerning Adco’s business operation.

Defendants moved to dismiss Adco’s complaint under section 2 — 619(a)(9) of the Civil Practice Law (735 ILCS 5/2 — 619(a)(9) (West 1992) (formerly Ill. Rev. Stat. 1991, ch. 110, par. 2 — 619(a)(9))). After finding that the agencies to whom the letters were written, the Illinois Department of Nuclear Safety (IDNS) and the Central Midwest Interstate Low-level Radioactive Waste Commission (CMILRWC), were quasi-judicial agencies created by statute, the circuit court held, as a matter of law, that Bullard’s two letters were not entitled to an absolute privilege, but only to a conditional privilege. The court further held that there was no showing that Bullard’s letters were written without malice and denied defendants’ motion to dismiss.

Defendants petitioned for leave to appeal from the circuit court’s order under Supreme Court Rule 308 (134 Ill. 2d R. 308), which we allowed. Certified for immediate appeal is the following question:

"When the trial court determines, as a matter of law, that Defendants’ letters were sent to quasi-judicial agencies of the State of Hlinois, are the Defendants’ letters entitled to an absolute privilege or merely a conditional privilege?”

Adco is a corporation engaged in business as a broker and transporter of low-level radioactive waste. Adco employed defendant Bullard as a truck driver from 1987 until February 24, 1992. Bullard was required to handle and transport low-level radioactive waste.

Adco’s business is regulated by and operated under a license issued by IDNS, which is responsible, under the Radiation Protection Act of 1990 (Act) (420 ILCS 40/1 et seq. (West 1992) (formerly Ill. Rev. Stat. 1991, ch. 1111/2, par. 210 — 1 et seq.)), for licensing radioactive material handlers and investigating information concerning violations of the Act and any regulations promulgated thereunder. (420 ILCS 40/12, 26 (West 1992) (formerly Ill. Rev. Stat. 1991, ch. 1111/2, pars. 210 — 12, 210 — 26).) The Act recognizes that ionizing radiations may be destructive or detrimental to life or health if carelessly employed and may harm the State’s environment if improperly used. The specific public policy behind the Act is to prohibit and prevent exposure to ionizing radiation in amounts which are or may be detrimental to health. 420 ILCS 40/2 (West 1992) (formerly Ill. Rev. Stat. 1991, ch. 1111/2, par. 210 — 2).

Similarly, the Central Midwest Radioactive Waste Compact Act provides for a regulatory commission. CMILRWC allows for compliance with the Low-Level Radioactive Waste Policy Act, a Federal act which encourages the development of low-level radioactive waste compacts as a tool for managing such waste. (45 ILCS 140/1 (West 1992) (formerly Ill. Rev. Stat. 1991, ch. 127, par. 63v — 1).) The purpose of the compact is, among other things, to provide facilities for the proper management of low-level radioactive waste generated in the region and to protect the health and safety of citizens of the region. (45 ILCS 140/1 (West 1992) (formerly Ill. Rev. Stat. 1991, ch. 127, par. 63v — 1).) Among the duties of the CMILRWC is the obligation to adopt a regional management plan designed to ensure the safe and efficient management of waste generated within the region.

Adco’s four-count complaint sounding in libel was based upon two letters authored by Bullard. The first letter, dated February 24, 1992, was addressed and mailed to IDNS. It complained about a breakdown in Adco’s safety program. The second letter, dated March 25, 1992, was sent to CMILRWC and was an attempt to correct alleged misstatements made by James P. Bell, president of Adco, at his meeting with CMILRWC held on March 17, 1992.

Counts I and II of the complaint purport to state a claim against Bullard for libel per quod and libel per se, respectively. Counts III and IV purport to state a claim against A.B. Gamma for libel per quod and libel per se, based upon the doctrine of respondeat superior.

I

Defendants assert that the complaint should have been dismissed because both letters are protected by an absolute privilege. Defendants maintain that absolute privilege is accorded to all actions required or permitted by law in the course of judicial proceedings or quasi-judicial proceedings, as well as actions necessarily preliminary to those proceedings.

Bullard’s February 24 letter was addressed to Bruce Sanza, an IDNS inspector. The letter complains about three problems Bullard encountered while working at Adco:

(1) At the end of 1991, Bullard and a co-employee were instructed to pick up a package of radium needles at a hospital in Evanston, Illinois. The needles were not packaged as Bullard was accustomed to seeing them packaged. Bullard’s co-employee called Adco’s general manager about the lack of proper packaging and was told to package it himself. In February of 1992, Bullard discovered that he had been over-exposed to radiation. No one from Adco had told him of this over-exposure;
(2) Bullard found out that Adco was storing explosives at its place of business and that he had unknowingly assisted in packaging a load of potentially explosive material; and
(3) Adco on February 21, 1991 distributed a memo and confidentiality agreement to all of its employees, the effect of which was allegedly to absolutely prohibit all of Adco’s employees from giving any information regarding Adco’s business operations. Bullard believed that this memo and confidentiality agreement were at odds with IDNS regulations because they allegedly prohibited employees from reporting to IDNS the existence of unsafe working conditions, license violations or IDNS regulation violations.

Bullard’s March 25 letter was addressed to Clark W. Bullard (no relation), chairman of CMILRWC. It complained of three statements made by James Bell of Adco to CMILRWC:

(1) Adco was the only radioactive waste broker in Illinois;
(2) IDNS would be dropping the ball if it did not renew Adco’s license because Illinois companies that generate radioactive waste need Adco; and
(3) Adco offers expertise and expensive computer programs to aid IDNS and/or CMILRWC in the interstate and intrastate tracking of radioactive waste drums.

Bullard then averred that the statements were false and misleading for the following reasons:

(1) Chem-Nuclear, U.S. Ecology, SEG and other radioactive waste brokers do business in Illinois;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SmileDirectClub, LLC v. Delta Dental Plans Ass'n
2022 IL App (1st) 220208-U (Appellate Court of Illinois, 2022)
Mauvis-Jarvis v. Wong
2013 IL App (1st) 120070 (Appellate Court of Illinois, 2013)
Kocontes v. McQuaid
778 N.W.2d 410 (Nebraska Supreme Court, 2010)
Kopchar v. City of Chicago
Appellate Court of Illinois, 2009
McNall v. Frus
Appellate Court of Illinois, 2002
Bushell v. Caterpillar, Inc.
291 Ill. App. 3d 559 (Appellate Court of Illinois, 1997)
Barakat v. Matz
648 N.E.2d 1033 (Appellate Court of Illinois, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
628 N.E.2d 772, 256 Ill. App. 3d 655, 195 Ill. Dec. 308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adco-services-inc-v-bullard-illappct-1993.