Adams v. D & D Leasing Co. of Georgia, Inc.

381 S.E.2d 94, 191 Ga. App. 121, 1989 Ga. App. LEXIS 491
CourtCourt of Appeals of Georgia
DecidedMarch 14, 1989
Docket77810, 77811
StatusPublished
Cited by21 cases

This text of 381 S.E.2d 94 (Adams v. D & D Leasing Co. of Georgia, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adams v. D & D Leasing Co. of Georgia, Inc., 381 S.E.2d 94, 191 Ga. App. 121, 1989 Ga. App. LEXIS 491 (Ga. Ct. App. 1989).

Opinion

Carley, Chief Judge.

Linnie Adams leased a vehicle from D & D Leasing Company of Georgia, Inc. (D & D). Subsequently, Ms. Adams defaulted on the monthly rental payments. After selling the vehicle at a private sale, D & D filed suit, seeking to recover under the liquidated damages provision of the “vehicle lease” agreement. Ms. Adams answered and asserted, among her other defenses, that D & D had failed to comply with the requirements of the Uniform Commercial Code regarding the giving of notification to her prior to the sale and the disposal of the automobile in a commercially reasonable manner. See OCGA §§ 10-1-36 and 11-9-540 (3).

Following discovery, D & D moved for summary judgment, urging that the provisions of the Uniform Commercial Code were inapplicable. Ms. Adams filed a cross-motion for partial summary judgment, urging that the liquidated damages provision of the “vehicle lease” agreement was an unenforceable penalty. The trial court granted both motions for summary judgment and, in accordance with those rulings, entered summary judgment in favor of D & D for $9,168.71 as actual damages for the breach of the lease. In Case No. 77810, Ms. Adams appeals from the trial court’s grant of D & D’s motion for summary judgment. In Case No. 77811, D & D cross-appeals from the trial court’s grant of Ms. Adams’ motion for partial summary judgment.

Case No. 77811

1. D & D’s cross-appeal from the grant of Ms. Adams’ motion for partial summary judgment will be addressed first.

It is D & D’s contention that the trial court erroneously con *122 strued the following liquidated damages provisions to be an unenforceable penalty: “In the event of a default^] this Lease shall terminate [and] all rights and privileges pertaining to the use of the Vehicle afforded under the provisions of the Lease shall cease to exist with respect to Lessee, and Lessor may take any or all of the following actions, to the extent permitted under applicable laws: (a) seek immediate payment by Lessee (as liquidated damages for loss of a bargain and not as a penalty) of an amount equal to all unpaid rental payments which absent a default would have been payable hereunder for the full Lease Term hereof and, in addition, the Residual Value of the Vehicle. . . .”

“ ‘In deciding whether a contract provision is enforceable as liquidated damages, the court makes a tripartite inquiry to determine if the following factors are present: “First, the injury caused by the breach must be difficult or impossible of accurate estimation; second, the parties must intend to provide for damages rather than for a penalty; and third, the sum stipulated must be a reasonable pre-estimate of the probable loss.” [Cits.]’ [Cit.]” Gibson v. Sheriff, 155 Ga. App. 578 (271 SE2d 710) (1980). “ ‘[I]n cases of doubt the courts favor the construction which holds the stipulated sum to be a penalty, and limits the recovery to the amount of damages actually shown, rather than a liquidation of the damages.’ [Cit.]” Southeastern Land Fund v. Real Estate World, 237 Ga. 227, 231 (227 SE2d 340) (1976).

A determination of the enforceability of the instant liquidated damages provision requires consideration of several prior decisions of this court. In Military Armament Corp. v. ITT Terryphone Corp., 134 Ga. App. 694, 695 (2) (215 SE2d 724)(1975), a liquidated damages provision not unlike that at issue in the present case was held to be enforceable. This holding was subsequently followed in Hughes Motor Co. v. First Nat. Bank of Atlanta, 136 Ga. App. 295, 296 (3) (220 SE2d 782) (1975) and in Ford Motor Credit Co. v. Dowdy, 159 Ga. App. 666 (284 SE2d 679) (1981). However, a similar liquidated damages provision was then held to be unenforceable in Taylor v. Commercial Credit &c. Corp., 170 Ga. App. 322 (316 SE2d 788) (1984). The previous decisions were not overruled, but were distinguished on the basis that “substantial portions of the lease terms had passed and the range of damages was 25 to 50 percent of the total amounts due. Those cases thus differ significantly from the instant case, where the default occurred in the second year of a 10-year term and liquidated damages of almost 60 percent of the original total lease payments were sought.” Taylor v. Commercial Credit &c. Corp., supra at 323. In a special concurrence in Taylor, Judge Banke and three other judges agreed with the majority that the liquidated damages provision was unenforceable, but urged that the prior decisions were not distinguishable and should be overruled. The decision in Taylor, supra, was *123 subsequently followed and applied in Blair v. Motorized Leasing, 173 Ga. App. 283 (3) (325) SE2d 896) (1985).

Upon further consideration, it would appear that the attempt in Taylor, supra, to distinguish this court’s previous decisions is unavailing. The enforceability of a liquidated damages provision is not dependent upon the time at which the underlying contract is breached. As is true with regard to the determination of the enforceability of any other contractual provision, a liquidated damages provision is or is not enforceable based upon the intent that was manifested at the time that the provision was originally proposed and agreed to. By its terms, a liquidated damages provision such as is here in issue is intended to apply regardless of when the breach occurs and courts should confine themselves to a determination of whether that intent is or is not enforceable. If a liquidated damages provision is unenforceable under the tripartite test at the time of original entry into the underlying contract, it does not become enforceable as the result of the passage of an arbitrary period of time. Likewise, if a liquidated damages provision is enforceable under the tripartite test at the time of original entry into the underlying contract, it is not thereafter rendered unenforceable by the passage of an arbitrary period of time. Accordingly, insofar as Taylor, supra, purports to add, as a fourth element to the tripartite test for determining the enforceability of a liquidated damages provision, the time of the breach of the underlying contract, it is hereby overruled. To the extent that it follows Taylor, the decision in Blair v. Motorized Leasing, supra, is likewise overruled.

Having held that the decisions in Military Armament Corp., supra, Hughes Motor Co., supra, and Ford Motor Credit Co., supra, cannot be distinguished, the issue becomes whether those decisions will continue to be followed. As previously noted, the recognized tripartite test includes, as its third element, the requirement that “ ‘ “the sum stipulated must be a reasonable pre-estimate of the probable loss.” [Cits.]’ [Cit.]” (Emphasis supplied.) Gibson v. Sheriff, supra at 578. “ ‘[T]he measure of damages for the lessee’s breach of contract is the cash, value of the contract less any saving which may accrue from the breach.’ [Cit.]” (Emphasis supplied.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Venable v. Suntrust Bank
780 S.E.2d 793 (Court of Appeals of Georgia, 2015)
JR Real Estate Development, LLC v. Cheeley Investment, L.P.
709 S.E.2d 577 (Court of Appeals of Georgia, 2011)
Mariner Health Care Management Co. v. Sovereign Healthcare, LLC
703 S.E.2d 687 (Court of Appeals of Georgia, 2010)
Summerhill Neighborhood Development Corp. v. Telerent Leasing Corp.
528 S.E.2d 889 (Court of Appeals of Georgia, 2000)
Carter v. Tokai Financial Services, Inc.
500 S.E.2d 638 (Court of Appeals of Georgia, 1998)
C's Rent to Own v. Jarrells (In Re Jarrells)
205 B.R. 994 (M.D. Georgia, 1997)
In Re Dailey
167 B.R. 932 (D. Montana, 1994)
Easterwood v. General Electric Capital Auto Lease, Inc.
825 F. Supp. 306 (N.D. Georgia, 1993)
Roswell Properties, Inc. v. Salle
430 S.E.2d 404 (Court of Appeals of Georgia, 1993)
Peterson v. P. C. Towers, L. P.
426 S.E.2d 243 (Court of Appeals of Georgia, 1992)
Peterson v. PC TOWERS, LP
426 S.E.2d 243 (Court of Appeals of Georgia, 1992)
Kedziora v. Citicorp National Services, Inc.
780 F. Supp. 516 (N.D. Illinois, 1991)
Bruner v. United States Leasing Corp.
410 S.E.2d 817 (Court of Appeals of Georgia, 1991)
Walton v. Howard
403 S.E.2d 90 (Court of Appeals of Georgia, 1991)
Chrysler Credit Corp. v. Brown
402 S.E.2d 753 (Court of Appeals of Georgia, 1991)
Bryan v. Williamson
395 S.E.2d 355 (Court of Appeals of Georgia, 1990)
Boyer v. Korsunsky, Frank, Erickson Architects, Inc.
382 S.E.2d 362 (Court of Appeals of Georgia, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
381 S.E.2d 94, 191 Ga. App. 121, 1989 Ga. App. LEXIS 491, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adams-v-d-d-leasing-co-of-georgia-inc-gactapp-1989.