Action Manufacturing Co. v. Simon Wrecking Co.

287 F. App'x 171
CourtCourt of Appeals for the Third Circuit
DecidedJuly 28, 2008
Docket06-3679
StatusUnpublished
Cited by9 cases

This text of 287 F. App'x 171 (Action Manufacturing Co. v. Simon Wrecking Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Action Manufacturing Co. v. Simon Wrecking Co., 287 F. App'x 171 (3d Cir. 2008).

Opinion

OPINION OF THE COURT

FISHER, Circuit Judge.

Defendants Simon Wrecking and its successor Simon Resources (collectively “Simon”) appeal the District Court’s order finding Simon liable as a transporter of hazardous wastes and awarding a monetary judgment to the plaintiffs in their contribution action under the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”). For the following reasons, we will affirm the order of the District Court.

I.

We write exclusively for the parties, who are familiar with the factual context and legal history of this case. Therefore, we will set forth only those facts necessary to our analysis.

This litigation arose over the contamination of the Malvern TCE Superfund Site in Malvern, Pennsylvania, where Chemclene Corporation had previously processed and stored industrial waste for many years. In 1996, the EPA informed the litigants that they were potentially responsible parties (“PRPs”) under CERCLA § 107(a). Appellees, members of the Chemclene Site Defense Group (“CSDG”), entered into a consent decree with the EPA and the Pennsylvania Department of Environmental Protection, agreeing to undertake *174 remediation of the site. In 2002, the CSDG brought a contribution action under CERCLA § 113 against the remaining PRPs, including Simon.

The District Court ultimately found Simon liable to the CSDG for contribution as a transporter of hazardous waste under CERCLA §§ 113(f) and 107(a). The District Court found that the expenses submitted by CSDG, with one exception, were consistent with the National Contingency Plan (“NCP”) as mandated by CERCLA § 107(a)(4)(B), yielding $4,224,701 in allocable past costs. Based on the remedies approved in the EPA’s Record of Decision (“ROD”), the District Court estimated future allocable costs for the site to be $17,872,964. In addition, the Court found that CSDG would incur $1,000,000 to the EPA in oversight costs. Thus, the Court determined that the total (past and future) allocable response cost was $23,097,665. CSDG received settlements in the amount of $6,630,670, resulting in a remaining allocable cost amount of $16,466,995. Based on relative shares of waste and other factors, the District Court determined that Simon was responsible for 6.25% of the remaining allocable costs. In addition, the District Court applied an uncertainty premium of 50% to this amount, increasing Simon’s responsibility to 9.38% of the remaining allocable costs. On July 7, 2006, based on these calculations, the District Court ordered Simon to pay CSDG $1,544,604.

II.

We have jurisdiction over this matter pursuant to 28 U.S.C. § 1291. We will set aside a District Court’s findings of fact only if they are clearly erroneous. FMC Corp. v. United States Dep’t of Commerce, 29 F.3d 833, 838 (3d Cir.1994). We exercise de novo review over the District Court’s conclusions of law. United States v. Dentsply Intern., Inc., 399 F.3d 181, 186 (3d Cir.2005). “A district court’s allocation of CERCLA response costs in a contribution action is reviewed for abuse of discretion. An abuse of discretion occurs when the district court’s decision rests upon a clearly erroneous finding of fact, an errant conclusion of law or an improper application of law to fact.” Beazer East, Inc. v. Mead Corp., 412 F.3d 429, 446 (3d Cir. 2005) (internal citations and quotation marks omitted).

III.

Simon argues that (1) Appellees failed to prove that Simon is liable as a transporter under CERCLA; (2) entry of monetary judgment, rather than declaratory judgment, for future costs was erroneous, as future costs are unknown, and the “uncertainty premium” was improperly applied to past costs; and (3) Appellees failed to prove that past costs were necessary and compliant with the NCP.

CERCLA § 107 provides that liability may only be imposed on a “responsible party.” United States v. Alcan Aluminum Corp., 964 F.2d 252, 258 (3d Cir. 1992). CERCLA § 107(a) defines four categories of responsible parties, including:

any person who accepts or accepted any hazardous substances for transport to disposal or treatment facilities, incineration vessels or sites selected by such person, from which there is a release, or a threatened release which causes the incurrence of response costs, of a hazardous substance ...

Id. § 107(a)(4). Simon does not dispute that it accepted hazardous substances for transport to the site, or that it did actually transport these substances to the site. It disputes only that Simon “selected” the site. We have construed transporter liability to include those parties that actively participated in the decision regarding the *175 location for disposal of a generator’s waste. Tippins Inc. v. USX Corp., 37 F.3d 87, 94 (3d Cir.1994) (“[A] person is liable as a transporter not only if it ultimately selects the disposal facility, but also when it actively participates in the disposal decision to the extent of having had substantial input into which facility was ultimately chosen.”).

Appellees adduced a number of pieces of circumstantial evidence that together show that the District Court did not clearly err when it determined that Simon selected or actively participated in the selection of the Chemclene site: (1) Chemclene employees did not know where Simon’s waste originated, indicating that the waste generators had no relationship with Chemclene. This lack of relationship implies that the waste generators were unlikely to have specifically selected the Chemclene site as their disposal site; (2) in a letter regarding Simon’s contract with a particular generator, the President of Chemclene informed Simon that Chemclene was in compliance with the relevant regulations, raising the inference that Simon was advising that generator, and thus taking an active role in site selection; (3) Simon brought many loads of waste to Chemclene over a period of years for many different customers, supporting the inference that Simon often had input into site selection; and (4) a contracting officer at one generator with whom Simon contracted testified that it was that generator’s policy not to tell a transporter where to take its waste, raising the inference that Simon, and not the generator, selected Chemclene as the site for that generator’s waste. This evidence is sufficient to support the District Court’s finding that it was more likely than not that Simon had actively participated in the selection of the Chemclene site. Therefore, the District Court did not clearly err in holding Simon liable as a transporter under CERCLA.

Simon next argues that the District Court erred in awarding a monetary judgment on this contribution claim, as opposed to declaratory judgment. However, Simon cites no statutory authority for this proposition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
287 F. App'x 171, Counsel Stack Legal Research, https://law.counselstack.com/opinion/action-manufacturing-co-v-simon-wrecking-co-ca3-2008.