Acta-Fax Business Machines v. South Carolina Procurement Review Panel

325 S.E.2d 319, 283 S.C. 555, 1984 S.C. LEXIS 398
Supreme Court of South Carolina·Decided December 17, 1984·Published·Cited by 1 cases

Opinion

ORDER

All parties in this matter have petitioned the Court to determine the scope of authority of the South Carolina Procurement Review Panel.

The Procurement Review Panel was created by the legislature to serve as an advisory body to the Budget and Control Board in protests arising under S. C. Code Ann. §§ 11-35-4210,11-35-4220, and 11-35-4230 (Supp. 1983). It has no authority to make or rescind contracts, or to order the Division of General Services to do so. In protests arising under § 11-35-4210, the Panel is empowered only to determine whether an unsuccessful bidder should have been awarded a contract, and to make recommendations to the Budget and Control Board for relief to the aggrieved bidder. § 11-35-4210(7); § 11-35-4410(5) (Supp. 1983). Additionally, § 11-35-4210(6) provides that “the request for a review shall not stay the contract unless fraudulent.”

It is therefore ordered that the portion of the Procurement Review Board’s order of determination dated October 25, 1984, which purported to rescind existing contracts and to substitute Royal Business Machines, Inc., as contractor, is void.

Free access — add to your briefcase to read the full text and ask questions with AI

Acta-Fax Business Machines v. South Carolina Procurement Review Panel, 325 S.E.2d 319, 283 S.C. 555, 1984 S.C. LEXIS 398 (S.C. 1984).

325 S.E.2d 319 (Acta-Fax Business Machines v. South Carolina Procurement Review Panel) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hitachi Data Systems Corp. v. Leatherman
420 S.E.2d 843 (Supreme Court of South Carolina, 1992)