ACT I, LLC v. Davis

2002 WY 183, 60 P.3d 145, 157 Oil & Gas Rep. 864, 2002 Wyo. LEXIS 220, 2002 WL 31886912
CourtWyoming Supreme Court
DecidedDecember 30, 2002
Docket01-168
StatusPublished
Cited by15 cases

This text of 2002 WY 183 (ACT I, LLC v. Davis) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ACT I, LLC v. Davis, 2002 WY 183, 60 P.3d 145, 157 Oil & Gas Rep. 864, 2002 Wyo. LEXIS 220, 2002 WL 31886912 (Wyo. 2002).

Opinion

GOLDEN, Justice.

[¶ 1] Appellees own working interests in various oil and gas leases located in the Powder River Basin of Campbell County, Wyoming. Appellant and Appellees entered into an agreement by which Appellant agreed to obtain financing for a project related to developing and working the mineral leases in exchange for the opportunity to buy a thirty-five percent share of the mineral leases. Appellant claims that it procured a suitable financing commitment and thereby fulfilled its obligation under the agreement. Appel-lees, however, declined to finalize any financing agreement and refused to sell the thirty-five percent ownership interest in the mineral leases to Appellant. Appellant sued for breach of contract, breach of the duty of good faith and fair dealing, and for specific performance.

[¶ 2] Appellees moved for summary judgment, arguing the agreement was unenforceable due to the operation of the statute of frauds. The district court granted summary judgment to Appellees. We find that, as a matter of law, no statute of frauds is applicable to the agreement. We further find that issues of material fact exist regarding the interpretation of the agreement. Summary *147 judgment was inappropriate, and we remand this ease back to the district court for appropriate further proceedings.

ISSUES

[¶ 3] Appellant presents two issues:

1. Does Wyoming or Colorado law govern the rights of the parties to a contract entered into in the State of Colorado by Colorado residents dealing with the right to purchase and develop an interest in mineral properties located in the State of Wyoming?
2. Was the written contract entered into between the parties, obligating Appellees to sell Appellants [sic] a 35% interest in certain coalbed methane leases upon the Appellants [sic] obtaining acceptable financing for the project, enforceable under Wyoming and Colorado law once the Ap-pellees agreed to the financing?

Appellees respond with three issues:

1. Do Wyoming conflict of law principles require application of Colorado law to Appellant’s causes of action where the majority of significant factors related to the contract occurred in, or are connected exclusively with, Colorado?
2. Does Colorado’s credit agreement statute of frauds, Colo.Rev.Stat. § 38-10-124, bar Appellant’s causes of action because it is undisputed that the DNR-Tindall Group never signed a writing accepting any of the proposed credit agreements?
3. If Wyoming law applies, does Wyoming’s statute of frauds, Wyo. Stat. Ann. § 1-23-105, bar Appellant’s causes of action because the DNR-Tindall Group never signed a writing accepting the new condition in the proposed credit agreements requiring the DNR-Tindall Group to assign a real property overriding royalty interest to the proposed lender?

FACTS

[¶ 4] Appellee Charles B. Davis is the President of Appellee DNR Oil and Gas, Inc. Appellee R. Lee Tucker is the President of Appellee Tindall Operating Company. Ap-pellees are all Colorado residents and Colorado corporations. Appellant, ACT I, is a limited liability company doing business in Colorado.

[¶ 5] Appellees are the owners of a working interest in certain mineral leases in Wyoming. This working interest includes the right to develop and produce coalbed methane natural gas. Appellees ultimately decided they wanted to explore for, drill and gather the coalbed methane themselves. To this end, on March 20, 2000, Appellees entered into a letter of intent (the “LOI”) with Appellant. Pursuant to the LOI, Appellant was to procure non-recourse financing for the project in exchange for a percentage ownership in the leases. Some of the pertinent language from the LOI includes:

The parties agree to work together on a best efforts basis to arrange for the completion of the financing upon receipt of an acceptable financing commitment.
⅜ ⅜ ⅜ ⅜
... In exchange for ACT I’s arranging financing for the Project, ACT I will purchase and DNR and Tindall will sell, a 35% proportionally reduced working interest participation in the [project]....
... The Acquisition Price shall be due upon execution of definitive agreements, including, among other things, ... financing documents for the Project.
⅜ ⅜ ⅜ ⅜
... [T]he parties understand and agree that the transactions contemplated by this letter are non-binding and subject to the following:
(a) Completion of definitive agreements incorporating the terms of this letter on or before April 20, 2000 which deadline shall automatically extend for successive 10 day increments until any party gives notice of its intent to terminate this Letter of Intent delivered to all parties at least two (2) business days prior to such termination.

On May 4, 2000, the parties entered into an agreement extending the duration of the LOI (the “Extension”). (Unless differentiated, further references to the LOI include both the LOI and the Extension.) The Extension stated in pertinent part that ACT I had until May 20

*148 in order to obtain financing arrangements for the Project and the parties.
[[Image here]]
The parties agree to continue to work together on a best efforts basis to arrange for the completion of the financing upon receipt of an acceptable financing commitment.
⅝ ⅜ ⅝ :¡s
Upon receipt of an acceptable financing commitment, DNR, Tindall, and ACT I shall enter into definitive agreements to reflect the terms outlined in the Letter of Intent.
The parties understand and agree that the transactions contemplated by the Letter of Intent are subject to the following: (a) Obtaining of a financing commitment by May 20, 2000 with definitive agreements incorporating the terms of the Letter of Intent to be finalized by May 31, 2000. To the extent the financing commitment is received and the parties are working toward completion of the definitive agreements, the parties agree to automatically extend for successive 10 day increments the Letter of Intent until any party gives notice of its intent to terminate the Letter of Intent delivered to all parties at least two (2) business days prior to such termination.

Both the LOI and the Extension were drafted by Appellant. Neither agreement contains a governing law provision.

[¶ 6] Appellant successfully negotiated a financing commitment from a lending institution. Although disputed, there is evidence in the record indicating that Appellees orally accepted the terms of the proposed financing commitment. Ultimately, however, Appel-lees decided they did not want to complete the deal and consequently never signed any loan documents.

[¶ 7] Appellant believed that it successfully had completed its obligations under the LOI by procuring a financing commitment that Appellees accepted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erickson v. Pharmacia LLC
Washington Supreme Court, 2025
Aubri Vahai v. Ryan Gertsch
2020 WY 7 (Wyoming Supreme Court, 2020)
National Union Fire Co. v. Toland
164 F. Supp. 3d 1330 (D. Wyoming, 2016)
Courtney C. Boutelle
2014 WY 147 (Wyoming Supreme Court, 2014)
Employers Mutual Casualty Co. v. Bartile Roofs, Inc.
618 F.3d 1153 (Tenth Circuit, 2010)
Christensen v. State
2010 WY 95 (Wyoming Supreme Court, 2010)
Platt v. Creighton
2007 WY 18 (Wyoming Supreme Court, 2007)
Black v. William Insulation Co., Inc.
2006 WY 106 (Wyoming Supreme Court, 2006)
Black v. William Insulation Co.
2006 WY 123 (Wyoming Supreme Court, 2006)
Habco v. L & B Oilfield Service, Inc.
2006 WY 91 (Wyoming Supreme Court, 2006)
Burnett v. Imerys Marble, Inc.
2005 WY 82 (Wyoming Supreme Court, 2005)
Franks v. Independent Production Co., Inc.
2004 WY 97 (Wyoming Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2002 WY 183, 60 P.3d 145, 157 Oil & Gas Rep. 864, 2002 Wyo. LEXIS 220, 2002 WL 31886912, Counsel Stack Legal Research, https://law.counselstack.com/opinion/act-i-llc-v-davis-wyo-2002.