A.C. Moore Arts & Crafts, Inc. v. Fellsway Plaza, LP

23 Mass. L. Rptr. 189
CourtMassachusetts Superior Court
DecidedOctober 9, 2007
DocketNo. 044170
StatusPublished

This text of 23 Mass. L. Rptr. 189 (A.C. Moore Arts & Crafts, Inc. v. Fellsway Plaza, LP) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A.C. Moore Arts & Crafts, Inc. v. Fellsway Plaza, LP, 23 Mass. L. Rptr. 189 (Mass. Ct. App. 2007).

Opinion

Henry, Bruce R., J.

This subrogation matter arises out of a fire loss sustained by the plaintiff, A.C. Moore Arts & Crafts, Inc. (Moore) on or about November 10, 2002. Before the Court are various motions by the remaining defendants for summary judgment.

Factual Background

Facts as to which there is no genuine dispute are as follows. Other material facts are set forth below as they become pertinent to the discussion.

Fellsway Plaza, LP (Fellsway) is the owner of Fellsway Plaza, a shopping center in Medford, Massachusetts. Pursuant to a contract with Fellsway, the defendant Construction Coordinators, Inc. (CCI), did construction work at the new Fellsway Plaza store for Bed & Bath. That work was done in 1996 and into early 1997. Suburban Fire Protection, Inc. (Suburban) was a subcontractor during that job. Suburban has not answered this lawsuit. In 1998, Moore took over the lease for the premises in question and engaged McLean Construction Company (McLean) as the general contractor for its buildout of the premises. N.A.P.M.S., Inc. was the sprinkler subcontractor for McLean. Bert Masse Fire Protection Services, Inc. (Masse) was engaged by Fellsway, or Manley-Berenson (Manley-Ber-enson), to test periodically the fire sprinkler system at the premises. Masse contends that its responsibility was limited to main drain testing and did not extend to the system within Moore’s space. At some point before the fire in November 2002, a plug, or blank flange, was inserted into the sprinkler system, within the interior of Moore’s space, apparently to block a portion of the system while work was being done. The plug or flange was not removed and Moore contends that the failure to remove the plug caused it to suffer damages it would not have suffered if the plug was not in place. All of the defendants deny responsibility for the insertion of the plug and Masse denies responsibility for testing the fire sprinkler system within the premises.

Summary Judgment Standard

Summary judgment shall be granted where there are no genuine issues of material fact and where the moving party is entitled to judgment as a matter of law. Mass.R.Civ.P. 56(c); Cassesso v. Commissioner of Cor[190]*190rection, 390 Mass. 419, 422 (1983); Community National Bank v. Dawes, 369 Mass. 550, 553 (1976). The moving party bears the burden of demonstrating affirmatively the absence of a triable issue, and that it is entitled to judgment as a matter of law. Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989). The moving pariy may satisfy this burden either by submitting affirmative evidence that negates an essential element of the opposing party’s case or by demonstrating that the opposing party has no reasonable expectation of proving an essential element of its case at trial. Flesner v. Technical Communications Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). All evidence must be viewed in the light most favorable to the non-moving pariy. Williams v. Hartman, 413 Mass. 398, 401 (1992).

CCI’s Motion for Summary Judgment

CCI has moved for summary judgment arguing that its work was completed at the premises in early 1997 and that the Statute of Repose, G.L.c. 260, §2B, bars the plaintiffs claims and the cross claims being made against it by Fellsway, which is the only party opposing CCI’s motion. As the plaintiff does not oppose the motion insofar as it relate to its claims against CCI, summary judgment shall enter for CCI on the plaintiffs claims in the complaint.

Fellsway asserts that there is a genuine fact issue as to who is responsible for the insertion of the plug and that CCI is required to indemnify Fellsway, according to the terms of the contract between the two parties. Pursuant to the terms of a written contract, CCI provided its services to Fellsway for the preparation of the Bed & Bath store at the Fellsway Plaza. Paragraph 3.18.1 of the agreement provides:

The Contractor [CCI] shall, to the full extent permitted by law, defend, indemnify and save harmless the Owner [Fellsway] and the Architect and their respective directors, officers, partners, trustees, employees and agents, from any and all claims (including attorneys fees resulting therefrom) directly or indirectly arising or alleged to arise out of the performance of or the failure to perform the Work, or the conditions of the Work, the job site, adjoining land or driveways, or streets or alleys used in connection with the performance of the Work, and from any and all claims by workmen, suppliers or subcontractors who are involved in the performance of the Work.
The obligations set forth in this provision . . . shall not include any claims arising solely from the negligence of the pariy otherwise to be defended, indemnified or saved harmless.
The Contractor also expressly warrants and guarantees to the Owner and the Architect, that all Work performed by the Contractor and by all workmen, suppliers and Subcontractors of the Contractor shall conform to the requirements of the Contract Documents and shall be performed in a safe and careful manner.

The defense offered by CCI, that the Statute of Repose bars the claims against it, does not apply to the contractual indemnification counterclaim being pursued by Fellsway. The Statute of repose does not bar action on the basis of an indemnification agreement. Gomes v. Pan American Assoc., 406 Mass 647 (1990). CCI, therefore, is not entitled to summary judgment on the indemnification cross claim brought against it by Fellsway and its motion is DENIED.

Fellsway’s Motion for Summary Judgment

Fellsway has moved for summary judgment making several arguments. First, it contends that the claim, brought by A.C. Moore’s insurer, has been waived by A.C. Moore and that the waiver is valid in Massachusetts. Fellsway also argues that indemnification provisions within the agreement with A.C. Moore preclude this claim. Lastly, Fellsway argues that the contract claim fails since the plaintiff has no reasonable expectation of being able to show that it breached the agreement between the parties. A.C. Moore disputes each of those arguments contending that under applicable Massachusetts law a party cannot insulate itself from liability for failing to comply with statutes and codes enacted for public safety and that the lease expressly excludes the negligence of the landlord from the waiver of liability under the non-subrogation clause. For the reasons which follow, Fellsway’s motion is denied.

Subrogation Waiver Argument

Fellsway’s predecessor in interest leased the premises in question to Bed & Bath in 1984. A.C. Moore took an assignment of Bed & Bath’s interest as of 1998. Article XIV of the operative lease at Section 14.2 states, in pertinent part, that “. . . Landlord and Tenant mutually agree that, with respect to any hazard which is covered by insurance then being carried by them, respectively, the one carrying such insurance and suffering such loss releases the other of and from any and all claims with respect to such loss; and they further mutually agree that their respective insurance companies shall have no right of subrogation against the other on account thereof.. . Nothing contained in this Section shall derogate from or otherwise affect releases elsewhere herein contained of either party for claims.”

While such waivers are enforceable under Massachusetts law, see

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henry v. Mansfield Beauty Academy, Inc.
233 N.E.2d 22 (Massachusetts Supreme Judicial Court, 1968)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Williams v. Hartman
597 N.E.2d 1024 (Massachusetts Supreme Judicial Court, 1992)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Haemonetics Corp. v. Brophy & Phillips Co.
501 N.E.2d 524 (Massachusetts Appeals Court, 1986)
Parent v. Stone & Webster Engineering Corp.
556 N.E.2d 1009 (Massachusetts Supreme Judicial Court, 1990)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Spence v. Reeder
416 N.E.2d 914 (Massachusetts Supreme Judicial Court, 1981)
Desseau v. Holmes
73 N.E. 656 (Massachusetts Supreme Judicial Court, 1905)
Anderson v. Fox Hill Village Homeowners Corp.
676 N.E.2d 821 (Massachusetts Supreme Judicial Court, 1997)
Federal Insurance v. CBT/Childs Bertman Tseckares, Inc.
22 Mass. L. Rptr. 472 (Massachusetts Superior Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
23 Mass. L. Rptr. 189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ac-moore-arts-crafts-inc-v-fellsway-plaza-lp-masssuperct-2007.