ABS Services, Inc. v. James Construction Group, L.L.C., and the Continental Insurance Company

Louisiana Court of Appeal·Decided July 22, 2021·No. 2020CA0841, 2020CA0842·Unknown

Opinion

NOT DESIGNATED FOR PUBLICATION

STATE OF LOUISIANA

COURT OF APPEAL

A, FIRST CIRCUIT C

2020 CA 0841 c/ w 2020 CA 0842

A.B. S. SERVICES, INC.

VERSUS

JAMES CONSTRUCTION GROUP, L.L.C. & THE CONTINENTAL INSURANCE COMPANY

Judgment rendered JUL 2 2 2021 E3EMME3

On Appeal from the

Nineteenth Judicial District Court In and for the Parish of East Baton Rouge State of Louisiana

No. C541834 c/ w C542671

The Honorable Wilson Fields, Judge Presiding

Murphy J. Foster, III Attorneys for Defendant/ Appellant Jacob E. Roussel James Construction Group, L.L.C.

John T. Andrishok Baton Rouge, Louisiana

Henry D.H. Olinde, Jr. Attorneys for Plaintiff/Appellee Scott E. Mercer A.B. S. Services, Inc.

Douglas S. Smith, Jr.

Baton Rouge, Louisiana

BEFORE: McDONALD, HOLDRIDGE, AND PENZATO, JJ.

HOLDRIDGE, J.

In this breach of contract case, James Construction Group, L.L.C. ( James), appeals a judgment awarding A.B. S. Services, Inc. ( ABS) attorney' s fees in the amount of $2, 394,940. 05 and taxing James with costs in the amount of $45, 970. 01. ABS answered the appeal, seeking to increase the attorney' s fee award and a modification of the date from which legal interest is to run on the amounts awarded to it. ABS also asks this court to award additional attorney' s fees incurred in connection with this appeal. For the following reasons, we amend the attorney' s fee award, affirm the cost assessment, and deny all relief sought by ABS in its answer to the appeal.

BACKGROUND

Some of the background forming the basis of this appeal can be gleaned from this court' s en Banc decision in ABS Services, Inc. v. James Construction

Group, L.L.C., 2016- 0705, 2016- 0706 ( La. App 1St Cir. 12/ 21/ 18), 269 So. 3d 723 per curiam), writ denied, 2019- 0473 ( La. 6/ 17/ 19), 273 So. 3d 1212. The

underlying lawsuit, which serves as the basis for the attorney' s fee award challenged in this appeal, arose out of a road construction project on Interstate 10 in East Baton Rouge Parish, Louisiana ( the " Project"). The owner of the Project,

the Louisiana Department of Transportation and Development ( DOTD) contracted with James to be the general contractor on the Project. James subcontracted a

portion of the work to ABS, which included the installation of retaining walls for the Project. Id. at 726.

There were a number of complications and problems impacting the construction of the retaining walls, including delays in construction and materials, geotechnical problems, and inspection issues. ABS began working on the Project in April 2004. The relationship between ABS and James deteriorated and by letter dated July 27, 2005, ABS notified James that it was in material breach and default of its subcontract with ABS. ABS claimed that it sustained over 1. 6 million dollars

in damages as a result of James' s breach of contract. James and ABS were unable

to resolve their differences, and on August 9, 2005, and before the retaining walls were completed, ABS demobilized from the Project. Id. at 726- 728.

On March 28, 2006, ABS filed the underlying lawsuit against James and its surety, The Continental Insurance Company, claiming that James breached the subcontract. ABS sought to recover damages, including but not limited to, increased costs for labor, equipment, overhead, and lost profits, in addition to

interest, attorney' s fees, court costs, and expenses. Id. at 728.

During the course of the litigation, numerous additional defendants were added to the litigation, including ABMB Engineers, Inc. ( ABMB) and Professional Services Industries, Inc. ( PSI). Also, numerous cross- claims, reconventional

demands, and third -party demands were filed thereafter, including a claim by James against ABS for breach of contract. In 2012, ABS amended its petition to

assert direct claims against DOTD and three suppliers of materials used to

construct the retaining walls. Id. at 728- 29.

In the underlying litigation, ABS did not seek recovery from James for unpaid invoices for work ABS performed on the Project pursuant to La. R.S.

9: 2784. Id. at 750 ( Whipple, C. J. concurring and dissenting in part). As discussed more fully herein, Paragraph A of La. R.S. 9: 2784, commonly referred to as

Louisiana' s Prompt Pay Statute, requires a contractor to promptly pay a

subcontractor monies received by the contractor from the owner of a project for the subcontractor' s work on that project. Although ABS did not assert a claim against

James under Paragraph A of La. R.S. 9: 2784, it sought to recover penalties and

attorney' s fees provided for in Paragraph C of La. R.S. 9: 2784, which permits the Ki

subcontractor to recover, in addition to the payment provided for in the statute,

penalties and attorney' s fees where the contractor, without reasonable cause, failed to make any payment to the subcontractor within 14 days of receipt of payment from the owner. Id. at 757- 58.

A jury trial was held from August 31 through September 11, 2015. Id. at

729. During that trial, Anthony Bertas, ABS' s owner, testified that James had paid ABS for all invoices or pay applications, less the retainage fee pursuant to the subcontract, totaling $ 1, 969, 772. 00, at the time ABS left the Project. Id. at 742, fn. 2. There was some conflicting testimony as to whether ABS was paid a final invoice submitted by ABS to James after ABS left the Project; Mr. Bertas testified that this final invoice had not been paid by James. Id. at 768 ( Guidry, J., concurring).

After the conclusion of the trial, the jury returned a verdict finding that James had breached its subcontract with ABS and that ABS did not breach that contract. In response to questions posed on a jury verdict form, the jury determined that ABS had sustained damages in the amount of $3, 174, 160. 00 as a

result of James' s breach of the contract. The jury found that James was liable to ABS for penalties and attorney' s fees in addition to the damages that had been awarded. The jury awarded a 5% penalty percentage to ABS. The jury further determined that DOTD, ABMB, and PSI were negligent and apportioned 50% fault to DOTD, 25% fault to ABMB, and 25% fault to PSI. The jury determined that ABS was entitled to $ 3, 174, 160. 00 for the damages it sustained as a result of the

parties' negligence. Id. at 730.

On September 28, 2015, the trial court adopted the jury verdict form as its judgment. Numerous post -trial motions were filed, resulting in a new final judgment signed by the trial court on December 1, 2015. In the December 1, 2015 judgment, James was ordered to pay ABS $ 3, 174, 160. 00 plus judicial interest from the date of judicial demand ( March 28, 2006) until paid; Continental was cast in solido with James to ABS for the full amount of this award; DOTD was cast in

solido with James for the sum of $1, 587, 080. 00; and ABMB and PSI

were each cast in solido with James in the amount of $793, 540. 00. The judgment

ordered James to pay ABS, pursuant to La. R.S. 9: 2784, penalties in the amount of 158, 708. 00 " plus reasonable attorney' s fees" along with judicial interest from the date of the judgment until paid. Finally, the judgment cast James, Continental, DOTD, PSI, and ABMB liable in solido for all costs of the proceedings, including reasonable expert witness fees, with judicial interest running from the date of the judgment until paid. Id. at 730- 31.

James, Continental, DOTD, ABMB, and PSI suspensively appealed the December 1, 2015 judgment. This court overruled various peremptory exceptions raised by James and DOTD, affirmed James' s liability to ABS for damages for breach of contract, and affirmed the ruling that ABS did not breach the contract. However, this court was unable to arrive at a majority consensus as to the amount of damages to which ABS was entitled. Because this court could not reach a

consensus as to the amount of the damages, the portion of the December 1, 2015

Free access — add to your briefcase to read the full text and ask questions with AI

ABS Services, Inc. v. James Construction Group, L.L.C., and the Continental Insurance Company, (La. Ct. App. 2021).

ABS Services, Inc. v. James Construction Group, L.L.C., and the Continental Insurance Company (ABS Services, Inc. v. James Construction Group, L.L.C., and the Continental Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Williams v. Louisiana Indem. Co.
658 So. 2d 739 (Louisiana Court of Appeal, 1995)
Sharbono v. Steve Lang & Son Loggers
696 So. 2d 1382 (Supreme Court of Louisiana, 1997)
SILLIMAN PRIVATE SCH. v. Shareholder Group
819 So. 2d 1088 (Louisiana Court of Appeal, 2002)
Gauthier v. Wilson
927 So. 2d 383 (Louisiana Court of Appeal, 2005)
Benjamin v. Zeichner
113 So. 3d 197 (Supreme Court of Louisiana, 2013)
Harris v. City of Baton Rouge
209 So. 3d 405 (Louisiana Court of Appeal, 2016)
Thomas v. A. Wilbert & Sons, LLC
217 So. 3d 368 (Louisiana Court of Appeal, 2017)
Quality Environmental Processes, Inc. v. IP Petroleum Co.
219 So. 3d 349 (Louisiana Court of Appeal, 2017)
Lewis v. Groetsch
32 So. 2d 396 (Louisiana Court of Appeal, 1947)