Abelman v. Indelli & Conforti Co.

170 A.D. 740, 156 N.Y.S. 401, 1915 N.Y. App. Div. LEXIS 6032
Appellate Division of the Supreme Court of the State of New York·Decided December 30, 1915·Published·Cited by 7 cases

Opinions

Clarke, J.:

The plaintiff as the assignee of the Han Construction Company sues to recover $1,621, with interest from January 1, 1912, alleged to have been paid by said company to the defendant under duress. The Han Construction Company owned property on the northerly side of Tremont avenue near Jerome avenue in The Bronx, and was engaged in the construction of a building. On January 9, 1911, it entered into a written contract with defendant for the excavation, digging of trenches and stone and concrete work for the cellar at an agreed price of $2,400, which covered the work to a depth of four feet below the cellar, as is shown by the plans, and, in case the excavation was carried to a greater depth, it was provided that the defendant receive nineteen cents per cubic yard for stone work and twenty-five cents per cubic yard for concrete work. Defendant was to be paid in installments as the work progressed, $700 when the second tier of beams was up, $700 when the fourth tier of beams was up, $700 when the building was finally inclosed and $300 when the studding was in and brown [742] mortar throughout the building. It further provided that the defendant should not he entitled to receive any sum whatever for any extra work unless at the request of the Han Construction Company and upon its written consent. The defendant commenced work under said contract and proceeded for some weeks when it stopped. It claimed that it had excavated all the trenches at four feet below the cellar; that it was ready to start the foundation when an inspector of the building department made a test and gave instruction to go down at least six or eight or ten feet below the cellar, to excavate the trenches four feet wide, to have the concrete two feet six inches high and four feet wide and the stone wall two feet six all the way through on a level with the cellar; that the parties had a conference in regard to the extra work and that as a result of that on March 7, 1911, a new contract in writing was entered into, which provided: “We agree to do all the excavating of job Tremont Ave. 100 ft. E. Jerome, including all trenches for said building for sum of One thousand ($1,000) Dollars. Stone work 12 cents per cubic ft. Labor and Stone. Concrete 14 cents per cubic ft. Labor and Broken Stone. It is understood that first contract to be destroyed.”

Under the first contract the defendant was to furnish the cement and sand. Under the second contract the Han Construction Company was to furnish said materials, defendant claiming that this was at the request of the Han Construction Company. There is ho dispute that this second contract was made. The plaintiff, however, claims that it was coerced because the defendant refused to proceed under the first contract; that the defendant claimed that it belonged to an association under whose by-laws it was forbidden to make contracts for a lump sum; that no member of the association would finish the job that had been commenced by one of its members unless that member released its claims; that the defendant refused to release its claims and that the Han Construction Company was unable to procure any other contractor to finish the job which the defendant commenced without such release upon its part and that, in view of the building loan which it had contracted to obtain, payable as the building progressed, it was held up by the action of the defendant and so was forced [743] to consent to the abrogation of the first contract and the making of the second. While the evidence in support of these claims is strenuously denied by the defendant, there was evidence in support thereof, and as the jury decided in favor of the plaintiff we shall assume, in the consideration of this appeal, that the plaintiff’s claim in this regard was established.

After the making of this new contract of March seventh, the defendant proceeded with its work and completed the same and received payment in full therefor, to wit, $3,038. The defendant claims that even assuming the second contract was made under duress it was ratified by the voluntary payment of the amounts due thereunder after the work was fully completed and accepted by the plaintiff. The plaintiff claims that the payments were not voluntary, but were also made under threats and by duress, the threats being that if the payments were not made the defendant would file a mechanic’s hen against the building. The first payment was of $400 on April 14, 1911, about which Abelman testified as follows: “On April 14th I gave him a check of $400. * * * I told Mr. Indelli, ‘ Here is $400, on account, and you come around at the end of the week or early part of next week, I will give you another check.’ * * * I said: ‘You have presented a bill to me for $3,038.’ I said: ‘Do you know that I am overpaying you according to the contract, with my materials, an average of about $1,600? * * * ’ He says: ‘You know you have got a contract, and we went ahead and we did the work, and we want to get paid,’ and I paid him every check. * * * The first time that was all said.”

The second payment was $600. That was paid by check of April 21, 1911. “I told Mr. Indelli, I said: ‘ You ought tobe more reasonable now. * * * Now, the job is finished, you ought to come to an understanding. We have got a contract of $2,400, and I think we ought to come to some understanding. You have got a new contract, and we have got to see what we can do.’ He says: ‘We have got a contract, and you have not signed it.’ I said; ‘Well, of course, I have not signed it.’ I said: ‘Now, you have got me now.’ He said: ‘ You have not signed it, ’ and I paid him that check of $600. * * * Q. What other conversation did you have with him ? A, Well, this I [744] don’t remember, but on May 8th he came up for a check, he . wanted $1,000. He came up and he says: ‘ Maurice, my partner, my brother are fighting with me. They said: ‘You have got to go and collect that money that is before the enclosure payment. You have got to go, you have got to go and get that money.’ I said: ‘Well, you know, Mr. Indelli, you have got to give us a chance. I paid you so much money. I paid you pretty near $2,400 before the enclosure payment, what do you want ? Give us a chance.’ He said: ‘I have got to have an order to the building loan man, otherwise I am going to file a lien to-morrow morning.’ Well, I said: ‘Indelli, what do you mean ? I told you I have not got money to pay you any money,’ because I am going to fight this out with him. He said: ‘If you don’t get me $1,000, I am going to file alien to-morrow morning.’ Well, I said: ‘ What do you mean, you are going to file a lien to-morrow morning ? You will ruin the job.’ He says: ‘ The partner says I have got to do so.’ ” This payment was made by check May 8, 1911.

Free access — add to your briefcase to read the full text and ask questions with AI

Abelman v. Indelli & Conforti Co., 170 A.D. 740, 156 N.Y.S. 401, 1915 N.Y. App. Div. LEXIS 6032 (N.Y. Ct. App. 1915).

170 A.D. 740 (Abelman v. Indelli & Conforti Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Joseph F. Egan, Inc. v. City of New York
18 A.D.2d 357 (Appellate Division of the Supreme Court of New York, 1963)
J. R. Construction Corp. v. Berkeley Apts., Inc.
259 A.D. 830 (Appellate Division of the Supreme Court of New York, 1940)
In re the Estate of Gude
150 Misc. 56 (New York Surrogate's Court, 1933)
Crossways Apartments Corp. v. Amante
213 A.D. 430 (Appellate Division of the Supreme Court of New York, 1925)
In re the Judicial Settlement of Account of Proceedings of Swiller
205 A.D. 302 (Appellate Division of the Supreme Court of New York, 1923)
Burne v. Van Raalte Co.
202 A.D. 189 (Appellate Division of the Supreme Court of New York, 1922)
Aronoff v. Levine
105 Misc. 668 (New York Supreme Court, 1919)