Aalco Construction Company, a Corporation, and Robert W. Sewell v. F. H. Linneman Construction Co., Inc.

399 F.2d 516, 1968 U.S. App. LEXIS 5639
CourtCourt of Appeals for the Tenth Circuit
DecidedSeptember 4, 1968
Docket9505
StatusPublished
Cited by5 cases

This text of 399 F.2d 516 (Aalco Construction Company, a Corporation, and Robert W. Sewell v. F. H. Linneman Construction Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aalco Construction Company, a Corporation, and Robert W. Sewell v. F. H. Linneman Construction Co., Inc., 399 F.2d 516, 1968 U.S. App. LEXIS 5639 (10th Cir. 1968).

Opinion

ORIE L. PHILLIPS, Circuit Judge.

F. H. Linneman Construction Co., 1 a Colorado corporation, brought this action against Aalco Construction Company, Inc., 2 an Oklahoma corporation, to recover damages for breach of an alleged subcontract to furnish all the labor and materials and to construct Project No. 1 of the Washington County Sewer Improvement District No. 2, in Bartlesville, Oklahoma, and a contract collateral thereto, and against Robert W. Sewell for breach of an alleged oral contract of indemnity. The case was tried to the court without a jury.

Aalco and Sewell have appealed from a judgment in favor of FHL Co.

Fred H. Linneman is president, and Jack Rose is vice-president of FHL Co. Sewell is president and principal stockholder of Aalco.

In midsummer of 1963, the District was about to call for bids for the construction of its Project No. 1. Aalco was desirous of bidding for the job, but its financial condition was such that it could not obtain a performance bond or a statutory payment (lien) bond, or satisfy the District that it was financially competent as a bidder.

In July 1963, Sewell contacted Linne-man by telephone, told him about the Sewer District Project, and asked Lin-neman if he or the FHL Co. would be interested in joining with Aalco in bidding for the job, or in underwriting Aalco as a bidder. Linneman replied that he would not be interested in a joint venture, but would try to work out an arrangement to assist Aalco.

The trial court found the facts substantially as above stated, 3 and further found these facts:

The FHL Co., through its president, Linneman, and its vice-president, Rose, had several conversations with Sewell, some by telephone and others in person, and as a result an oral agreement was reached, by which it was agreed that the FHL Co. would submit a bid for the job, and if awarded the contract would enter into a prime contract with the District to construct the project and furnish the performance and payment bonds; and that the FHL Co. and Aalco would enter into a subcontract, by which the latter would agree as subcontractor to furnish all the labor and materials and perform all the work and construct the *518 project in accordance with the terms of the prime contract, and the FHL Co. would agree that Aalco should receive the full contract price; and that for the risk assumed by the FHL Co., Aalco would agree to pay it five per cent of the gross amount of the bid when the project was completed.

The bid was based on estimates prepared by Aalco and Sewell and furnished by them to the FHL Co. The bid form was checked and approved by Rose.

The FHL Co. submitted a bid of $533,-642.87, which was accepted, and on August 9, 1963, it entered into a prime contract to furnish all the labor and materials and construct the project. On the same day, FHL Co. and Aalco entered into a subcontract, by the terms of which Aalco was to receive the full contract price, and was to furnish all the labor and materials and construct the project and fully perform the entire prime contract.

Also on the same day, Aalco wrote a letter to the FHL Co., by which it agreed to pay the latter for the risk it assumed, five per cent of the gross amount of the contract price on completion of the project.

Early in the negotiations, Linneman insisted that the FHL Co. must have a personal indemnity agreement from Se-well against a loss by the FHL Co. Se-well, individually, orally promised the FHL Co. that he would hold it harmless against any loss. The FHL Co. relied on that promise, and would not have entered into the prime contract, or the balance of the arrangement, without such promise by Sewell. 4

Aalco commenced performance under the subcontract. The FHL Co. advanced funds to Aalco. Not long after Aalco commenced performance of the subcontract, the FHL Co. began to receive complaints from the District and its engineers of unsatisfactory performance of the work by Aalco. That continued, because Aalco did not perform the work in accordance with the requirements of the prime contract, which requirements were made a part of the subcontract. As a result, the FHL Co. was required to take the job over and complete the contract, in order to avoid breaches of the prime contract and the incurring of penalties and damages, as provided for therein. On February 17, 1964, the FHL Co., with the acquiescence of Aalco, took over the work and finished the job.

The trial court further found that due to the breach of the subcontract by Aalco, the FHL Co. suffered damages in the following amounts:

(a) $58,736.72, which was a portion of $285,307.64 advanced by the FHL Co. to Aalco, under the provisions of the subcontract, which Aalco “retained for purposes not authorized” by the subcontract ;

(b) $38,555.74, being the net deficit between funds received and expended by the FHL Co. in connection with the project;

(c) $9,041.85, being the amount of additional unpaid claims in connection with the project;

(d) $50,617.40, representing the charge for the use of necessary equip *519 ment furnished by FHL Co. in completing the work on the project;

(e) $44,633.13, representing the necessary additional overhead expense incurred by FHL Co. in completing the project;

(f) $26,663.47, being the amount due the FHL Co. under the five per cent contract with Aalco.

The court further found that the FHL Co. was entitled to recover from Aalco, under its subcontract with Aalco, $228,-275.21, and was entitled to recover against Sewell, individually, upon his. oral contract of indemnity, the sum of $201,611.84, that being the amount of the judgment against the defendant, Aalco, less the sum of $26,663.47, due under the five per cent contract.

The findings of the trial- court are all amply supported by substantial and creditable evidence and none of them are clearly erroneous. We think no useful purpose would be served by' setting out all of the evidence in detail that thus supports the findings of the trial court.

Since such findings are not clearly erroneous, under Rule 52 of the Federal Rules of Civil Procedure they are binding on this court.

The court concluded that the prime contract between FHL Co. and the District was a valid legal contract, which required the FHL Co. to construct the project in accordance with the terms and provisions thereof; that the oral agreement between the FHL Co. and Aalco was reduced to a subcontract agreement and supplemental letter agreement, which bound Aalco to construct the project in accordance with the plans, specifications, and requirements of the prime contract, and to pay the FHL Co. five per cent of the total contract price; and that Sewell orally agreed to indemnify and hold the FHL Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Deposit Insurance v. Frates
44 F. Supp. 2d 1176 (N.D. Oklahoma, 1999)
Gropp v. United Airlines, Inc.
847 F. Supp. 941 (M.D. Florida, 1994)
Mississippi Ass'n of Cooperatives v. Farmers Home Administration
139 F.R.D. 542 (District of Columbia, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
399 F.2d 516, 1968 U.S. App. LEXIS 5639, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aalco-construction-company-a-corporation-and-robert-w-sewell-v-f-h-ca10-1968.