A & W Sheet Metal, Inc. v. Berg Mechanical, Inc.

653 So. 2d 158, 1995 La. App. LEXIS 808, 1995 WL 146129
CourtLouisiana Court of Appeal
DecidedApril 5, 1995
Docket26799-CA
StatusPublished
Cited by14 cases

This text of 653 So. 2d 158 (A & W Sheet Metal, Inc. v. Berg Mechanical, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A & W Sheet Metal, Inc. v. Berg Mechanical, Inc., 653 So. 2d 158, 1995 La. App. LEXIS 808, 1995 WL 146129 (La. Ct. App. 1995).

Opinion

653 So.2d 158 (1995)

A & W SHEET METAL, INC., Plaintiff-Appellee,
v.
BERG MECHANICAL, INC. & River City Sheet Metal, Inc., Defendants-Appellants.

No. 26799-CA.

Court of Appeal of Louisiana, Second Circuit.

April 5, 1995.

*160 Katherine Clark Hennessey, Shreveport, Donald J. Anzelmo, Monroe, for appellant.

Paul J. Verlander, Monroe, for appellee.

Before NORRIS and HIGHTOWER, JJ., and CULPEPPER, J. Pro Tem.

CULPEPPER, Judge Pro Tem.

Appellant Berg, Inc.[1] (Berg) challenges a judgment in favor of A & W Sheet Metal, Inc. (A & W) awarding damages for breach of contract and loss of business reputation. A & W appeals from that portion of the judgment denying its claims of unfair trade practices against Berg and River City Sheet Metal, Inc. (River City) as well as its claim of intentional interference with contract against River City.

FACTS

This is a bidding process dispute.

In mid-1990, State Farm Insurance Company (State Farm) planned to build a substantial addition to its office in Monroe, Louisiana. State Farm issued a request for bids on the project in June; the final bid deadline for general contractors was 2:00 p.m. on July 27, 1990. McInnis Brothers (McInnis), a Minden general contractor, submitted the lowest bid and was chosen to build the addition.

Berg submitted bids on the mechanical subcontract to several general contractors, one of whom was McInnis. Berg's bid was lowest among the mechanical contractors bidding with McInnis and Berg was selected to perform this portion of the work.

The instant dispute concerns the award of the subcontract to provide Berg with sheet metal duct-work for the project. Before submitting its bid to the general contractors, Berg solicited bids from several sheet metal subcontractors by telephone. When the 2:00 p.m. bid deadline for general contractors passed on July 27, Berg had received only two bids for the sheet metal work—those of A & W ($514,000.00) and Industrial Roofing and Sheet Metal, Inc. (Industrial) ($568,000.00). About one hour before the deadline, Berg called River City for a bid but was unable to reach them. Berg submitted its bid to McInnis using the $514,000.00 figure for the metal work.

At approximately 2:17 p.m. on bid day, Ricky Auttonberry (the president of A & W) called Berg to determine the outcome of the bidding. Chris Colvin, Berg's vice-president in charge of operations, told Auttonberry that McInnis had submitted the lowest bid among general contractors, that Berg had submitted the lowest mechanical subcontract bid to McInnis, and that A & W had submitted the lowest sheet metal subcontract bid to Berg. Colvin then told Auttonberry that Berg had calculated its mechanical subcontract bid using A & W's price.

Colvin later spoke to a representative of Industrial and told that company that Berg had "committed to A & W, that they were low."

At about 2:30 p.m. on bid day, a River City representative called Berg and got permission to submit a late bid. At 4:00 p.m., River *161 City gave Berg a bid of $419,000.00 to perform the sheet metal work. By that time, the various subcontractor bids were no longer confidential, and River City may have known the approximate amount of A & W's sheet metal bid to Atkins, a competitor of Berg. The trial court was uncertain whether River City knew the amount of A & W's bid to Berg.

In early August, Auttonberry called Berg to check on the progress of the job. He again spoke to Colvin, who told Auttonberry that when McInnis picked its project manager, Berg would select its project manager who in turn would contact A & W. Colvin told Auttonberry that A & W "needed to be ready" because "this would be a fast-track job."

Later that month, Robert Hamm, president of Berg, met with Chuck Cambry, president of River City. Although Hamm was displeased that River City had submitted a late bid, he nevertheless negotiated with Cambry for the sheet metal contract. River City agreed to perform the work for $414,000.00 and Berg awarded the job to River City.

On August 20, Hamm met with Auttonberry and Chuck Davis from A & W and told the two that Berg had awarded the sheet metal contract to River City because of their substantially lower bid. Hamm offered A & W $15,000.00 to cover its estimating expenses, which A & W refused. A & W subsequently sued Berg for breach of contract and unfair trade practices. A & W also sued River City for unfair trade practices as well as intentional interference with contractual rights.

ACTION OF THE TRIAL COURT

The trial court held that Berg accepted A & W's offer to perform the sheet metal work and awarded A & W $130,000.00 for lost profits and $25,000.00 for damage to business reputation and related claims. However, the court rejected A & W's unfair trade practices claims against Berg and River City. Further, the court rejected A & W's intentional interference with contract claim against River City as insufficient under 9 to 5 Fashions, Inc. v. Spurney, 538 So.2d 228 (La.1989).

ISSUES PRESENTED FOR REVIEW

1. Whether Berg accepted A & W's offer to perform the sheet metal work and, if so:

A. Whether the trial court erred by awarding A & W $130,000.00 for lost profits.
B. Whether the trial court erred by awarding A & W $25,000.00 for loss of business reputation and opportunity.

2. Unfair Trade Practice and Consumer Protection Law.

A. Whether the trial court erred by overruling Berg's exception of no right of action under the Louisiana Unfair Trade Practice and Consumer Protection Law (UTPCPL) and, if not, whether Berg is liable under that law.
B. Whether the trial court erred by denying A & W's UTPCPL claim against River City.

3. Whether the trial court erred in rejecting A & W's claims of intentional interference with contract against River City.

DISCUSSION

1. BREACH OF CONTRACT

The initial question presented is whether the trial court was manifestly erroneous in finding as a fact that Berg accepted A & W's offer to perform the sheet metal work. The law of consent is found in LSA-C.C. Art. 1927, which provides:

A contract is formed by the consent of the parties established through offer and acceptance.
Unless the law prescribes a certain formality for the intended contract, offer and acceptance may be made orally, in writing, or by action or inaction that under the circumstances is clearly indicative of consent.
Unless otherwise specified in the offer, there need not be conformity between the manner in which the offer is made and the manner in which the acceptance is made.

In its reasons for judgment, the trial court stated "A & W's offer to perform the sheet metal work for $514,000.00 was accepted by Berg's actions and inactions which clearly *162 indicated consent. Berg's subsequent actions constituted a breach of contract." We agree.

Each party presented voluminous testimony regarding the construction bidding process in general and, in particular, the significance of being the "low bidder." Chris Colvin, Berg's operations vice-president, testified that, in general, Berg awards contracts to the lowest responsible bidder and that subcontractors are expected to submit their bids before the bid deadline.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mier v. Mier
178 So. 3d 270 (Louisiana Court of Appeal, 2015)
Russel Mier v. Gregory Russel Mier
Louisiana Court of Appeal, 2015
Harp v. Autrey
121 So. 3d 1260 (Louisiana Court of Appeal, 2013)
Arthur J. Gallagher & Company v. Clayton Ba
703 F.3d 284 (Fifth Circuit, 2012)
Harris Builders, L.L.C. v. URS Corp.
861 F. Supp. 2d 746 (E.D. Louisiana, 2012)
Johnson Construction Co. v. Shaffer
87 So. 3d 203 (Louisiana Court of Appeal, 2012)
Indest-Guidry, Ltd. v. Key Office Equipment, Inc.
997 So. 2d 796 (Louisiana Court of Appeal, 2008)
Tyler v. Rapid Cash, LLC
930 So. 2d 1135 (Louisiana Court of Appeal, 2006)
Spears v. American Legion Hosp.
780 So. 2d 493 (Louisiana Court of Appeal, 2001)
Healthcare Mgmt. v. Vantage Healthplan
748 So. 2d 580 (Louisiana Court of Appeal, 1999)
Grocery Supply v. Winterton Food Stores
722 So. 2d 94 (Louisiana Court of Appeal, 1998)
Adams v. Commercial Nat. Bank in Shreveport
661 So. 2d 636 (Louisiana Court of Appeal, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
653 So. 2d 158, 1995 La. App. LEXIS 808, 1995 WL 146129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-w-sheet-metal-inc-v-berg-mechanical-inc-lactapp-1995.