This text of 151 A.3d 745 (A. Salvati Masonry Inc. v. Michael Andreozzi) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. Salvati Masonry Inc. v. Michael Andreozzi, 151 A.3d 745, 2017 R.I. LEXIS 2 (R.I. 2017).

Opinion

OPINION

Justice Indeglia, for the Court.

In these consolidated cases, 1 the plaintiff, A. Salvati Masonry Inc. (Salvati or plaintiff), appeals a nonjury-trial judgment for the defendants, Michael and Amy An-dreozzi (the Andreozzis or defendants). This case came before the Supreme Court on November 3, 2016, pursuant to an order directing the parties to appear and show cause why the issues raised should not be summarily decided. After considering the arguments set forth in the parties’ memo-randa and at oral argument, we are convinced that cause has not been shown. Thus, further argument or briefing is not required to decide this matter. For the reasons outlined below, the Superior Court’s judgment is affirmed.

I

Facts and Travel

This appeal emanates from a payment dispute over the construction of a backyard patio at defendants’ property on Old Farm Road in East Greenwich, Rhode Island. To develop their property, the property owners, the Andreozzis, hired Pari-seault Builders (Pariseault) as a general contractor. In turn, Pariseault, a nonparty, subcontracted with Salvati for masonry work. From this involvement, Salvati claims money owed by the Andreozzis beyond that paid to it by Pariseault.

Mr. Michael Andreozzi testified first. He stated that he contracted in writing with Pariseault to build his home for $1.8 million. He and his wife paid Pariseault $180,000 for their general contracting services, and Pariseault subcontracted out various project parts. Mr. Andreozzi stated that Salvati submitted two bids on the project. The first, which involved the house structure, was completed. For this bid, Salvati received full payment of approxi- *747 raately $135,000. Pertinent to this appeal, the second bid, for $88,845, related to exterior landscaping.

Mr. Andreozzi testified that the second bid with Pariseault “included all of the back patio work, the pool patio, the walls around the back of the house, stone pillars, limestone caps, steps, et cetera * * *.” As such, he believed that Pariseault should have paid Salvati for the aforementioned work. Mr. Andreozzi responded affirmatively when asked whether he paid for the patio as part of Salvati’s $88,845 bid for the second phase of masonry work. 2

Additionally, Mr. Andreozzi testified about a conversation with Keith Salvati, 3 owner of Salvati, on July 10, 2013. He stated that Mr. Salvati told him that he made a significant error in his bid, worth between $12,000 . and $15,000, because the. bid erroneously omitted, the patio masonry work. He also stated that Mr. Salvati told him to withhold payment for not-yet-completed work. He further acknowledged that Salvati performed extra work outside of the original Pariseault subcontract, which he paid for on the basis of “time and materials.”

Mr. Salvati testified next. He confirmed that Pariseault contacted Salvati to submit a masonry bid for the Andreozzis’ project. Mr. Salvati denied making any bid-preparation error and asking Mr. Andreozzi to hold back payments.

Mr. Salvati testified that his prepared bid for Pariseault as the masonry project subcontractor excluded the back patio. He stated that he therefore did not bill Pari-seault for the patio work he performed. He testified that the item Mr. Andreozzi referenced on the bid involved “the landscape part of the project,” which encompassed “[cjultured stone on walls, steps, and columns.” Mr. Salvati also testified that he neither discussed a specific price for the patio work with the Andreozzis nor billed them on the basis of labor and materials. He suggested that the second masonry bid excluded the patio because the patio specifications, including the stone material and color, were not yet specified at the time of the masonry bid. Instead, he testified that he did not bill the Andreozzis for the patio until he did so with an invoice dated July 7, 2013.

Mr. Salvati confirmed that the Andreoz-zis requested that he complete extra work beyond that outlined in the original Pari-seault subcontract. Mr. Salvati testified that, for work prior to the spring of 2013, Salvati billed Pariseault directly, and Pari-seault either paid or declined to pay. After that time period, Salvati billed the Andre-ozzis directly. He testified that some original bid items shifted to the Andreozzis because the project was not yet complete. Mr. Salvati testified that, in February 2013, Pariseault paid him in full for everything billed through November 2012. However, because Mr. Salvati claimed that the original subcontract omitted the patio work, he stated that he never received payment for that work.

Mr. Salvati testified that the aggregate amount that the Andreozzis owed him was $45,377.08, which included the balance owed for work and material under the original Pariseault subcontract and work *748 he performed directly for the Andreozzis. The witness indicated that he never billed the Andreozzis for anything for which Par-iseault paid him.

Mr. Salvati confirmed that, as was Pari-seault’s practice for the Andreozzis’ project, Salvati signed lien releases for the amount of payments he would receive. He testified that, as payments were received, Pariseault provided him with a corresponding lien waiver, and he executed all of them. When Salvati received notice of Pariseault’s withdrawal from the project, he had signed lien waivers for all payments received up to that point.

Thomas Rezendes, Pariseault’s general manager, testified next. He stated that the original Andreozzi project, for their home, was completed. He described it as a “cost-plus project,” which meant that the Andre-ozzis were to complete outstanding work independently.

When asked whether “Pariseault Builders ever pa[id] A Salvati Masonry for the patio in the rear of the building?” Rez-endes responded, “[a]ll we paid Salvati Masonry for what would have been * * * the cultured stone on the walls, steps and columns which surround the patio, but not the patio pavers itself.”- He confirmed that he understood that Salvati never submitted a bid for the home’s rear patio; and, when asked whether Pariseault paid Salva-ti for the patio or the blocks themselves, he stated that he did not think so. Rez-endes also testified that he was aware that Mr. Andreozzi was responsible for paying Salvati for all work after March 2013, regardless of whether or not the work was a part of the original Pariseault subcontract.

A bench trial was held on June 1 through June 3, 2015. The trial justice rejected both of plaintiffs claims in a written decision dated July 24, 2015, and judgment was entered for the Andreozzis on September 11, 2015. The plaintiff appealed on September 28, 2015,

II

Standard of Review

“When a trial justice presides over a nonjury trial, Rule 52(a) of the Superior Court Rules of Civil Procedure requires that he or she ‘find the facts specially and state separately [his or her] conclusions of law thereon.’ ” South County Post & Beam, Inc. v. McMahon, 116 A.3d 204, 210 (R.I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
151 A.3d 745, 2017 R.I. LEXIS 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-salvati-masonry-inc-v-michael-andreozzi-ri-2017.