A. Finkl & Sons Co. v. Illinois Commerce Commission

620 N.E.2d 1141, 250 Ill. App. 3d 317, 189 Ill. Dec. 824
CourtAppellate Court of Illinois
DecidedJune 8, 1993
Docket1-91-3854, 1-91-3869, 1-91-3871 and 1-91-3899
StatusPublished
Cited by21 cases

This text of 620 N.E.2d 1141 (A. Finkl & Sons Co. v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. Finkl & Sons Co. v. Illinois Commerce Commission, 620 N.E.2d 1141, 250 Ill. App. 3d 317, 189 Ill. Dec. 824 (Ill. Ct. App. 1993).

Opinion

JUSTICE HARTMAN

delivered the opinion of the court:

This review proceeds under sections 10 — 113 and 10 — 201 of the Public Utilities Act (Ill. Rev. Stat. 1989, ch. 1112/3, pars. 10 — 113, 10 — 201 (now 220 ILCS 5/10 — 113, 10 — 201 (West 1992)) (section 10— 201) (Act)) and Supreme Court Rule 335 (134 Ill. 2d R. 335), from a final order of the Illinois Commerce Commission (Commission), which allowed Commonwealth Edison (Edison) to recover costs associated with demand-side management (DSM) programs through a rider, designated “Rider 22.” Illinois Industrial Energy Consumers (IIEC) and Citizens Utility Board (CUB) appeal.

The issues presented for review are whether (1) IIEC and CUB have standing to pursue this review; (2) the Commission violated the prohibition against single-issue ratemaking; (3) the Commission acted beyond its jurisdiction in approving the rider as an incentive to Edison to comply with the law; (4) the Commission violated the Public Utilities Act (Ill. Rev. Stat. 1989, ch. 1112/3, par. 1 — 101 et seq. (now 220 ILCS 5/1 — 101 et seq. as amended (West 1992)) (Act)) by allowing Edison to charge consumers for “lost revenues”; (5) the Commission violated the prohibition against retroactive rule making; (6) the Commission’s approval of Rider 22 is a violation of its own rules and the laws pertaining to use of a test year; and (7) the Commission erred in not requiring a cap on cost recovery in the rider.

A brief consideration of policy and procedural history is necessary to an understanding of the issues presented in this review. Section 8 — 402 of the Act (Ill. Rev. Stat. 1989, ch. 111 2/3, par. 8 — 402 (section 8 — 402)) requires the Commission to adopt long-range energy plans for both the State as a whole and for each energy service utility in order to effectuate “least cost” policies of the State. Every three years, the Department of Energy and Natural Resources (DENR) is required to prepare and submit proposed utility energy plans for Illinois. The utilities also prepare and submit individual company plans for Commission approval. 1 Evidentiary hearings are to be held, and the Commission must either adopt or modify the plans submitted. The Commission must select the plan, and components thereof, which will result in the greatest likelihood of providing adequate, efficient, reliable and environmentally safe energy services at the least cost to consumers and which will utilize, to the fullest extent practicable, all economical sources of conservation, renewable resources, cogeneration and improvements in energy efficiency as the primary sources of new energy supply. To the fullest extent possible, the plans adopted for each utility are to be consistent with the statewide plan. 2 Ill. Rev. Stat. 1989, ch. 1112/3, par. 8 — 402.

Where the Commission determines, as a result of the hearings, that a utility’s existing or planned programs or policies inhibit or do not fully ensure the economical utilization of conservation, renewable resources, cogeneration or improvements in energy efficiency, it “shall” revise the plan as necessary and order the utility to implement the program or policies in cooperation with the DENR. Implementation by a utility of such additional programs or policies as ordered by the Commission entitles the utility to recover reasonable costs through the ratemaking procedures outlined in the Act. Ill. Rev. Stat. 1989, ch. 111/s, par. 8 — 402.

On October 6, 1989, the Commission adopted the first statewide plan, setting forth in detail how utilities are to develop the capability to use the demand-side resources that are favored, consistent with section 8 — 402. The Commission directed the utilities to “begin to build the capability to turn potential demand resources into available resources consistent with section 8 — 402 ***. This process should include technical and market research and development, pilot programs, and marketing tests designed to gather information, test incentive designs, and assess and build delivery mechanisms.”

The Commission also recognized that utilities should recover costs they incur with demand-side program analyses and were directed to develop proposals for the recovery of “prudently-incurred” costs associated with analysis, design and implementation of demand-side programs. The Commission found it premature to articulate a uniform policy with respect to DSM cost recovery and lost revenues.

The statewide plan also addressed the recovery of a particular cost associated with demand-side programs due to lost revenue, which are revenues that the utility would earn but for DSM capability building activities, referred to as a potential barrier to implementing demand-side programs. The utilities were directed to include in their least cost plan a proposal to reduce this barrier.

Witnesses during hearings on Rider 22 explained, in part, that: “The lost earnings due to implementing such a demand[-]side resource prematurely are a real cost of the decision to do so.” Further, “[t]he recovery of Lost Revenues allows utilities to recover revenues lost through the implementation of capability building pilot programs that the Commission has found to be in the public interest.” Also, “demand-side resources provide much lower earnings than supply-side resources, unless profits lost as a result of decreased sales due to demand-side management [‘DSM’] are offset in some manner.”

Edison submitted its first individual company electric energy plan on January 8, 1990, in which it charted its capability to design, implement and evaluate demand-side resources. Edison addressed the issue of how to best recover the costs associated with its DSM and proposed that its cost of building capability in the design, evaluation and implementation of demand-side resources be recovered by the use of a cost recovery mechanism called a rider, which is a form of tariff that modifies an otherwise applicable standard rate under specific circumstances.

The Commission confirmed the use of a rider as an appropriate cost recovery mechanism in an order dated December 12, 1990 (Illinois Commerce Commission, Illinois Commerce Commission No. 90— 0038 (Dec. 12, 1990) (Docket No. 90 — 0038)), asserting that the absence of a cost recovery mechanism for DSM presents substantial barriers to least cost energy planning, which should be reduced or minimized if possible.

Pursuant to the Commission’s order, on January 3 and 8, 1991, Edison met with interested parties to discuss the proposed cost-recovery rider. Prior to these “workshops” Edison circulated a proposed rider for review to all those entities participating in the prior proceeding. Edison received written comments on the proposed rider from the Commission staff, DENR, the City of Chicago, IIEC, the Attorney General and the Office of the Public Counsel (OPC).

Following the workshop, Edison, DENR, the Cook County State’s Attorney’s office, the City of Chicago and Low-Income Residential Consumers entered into a stipulation agreeing that Rider 22 be placed into effect without suspension or hearing. IIEC sought modification and objected to the recovery of costs on a per-kilowatt basis and raised other objections.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Illinois Commerce Commission
2015 IL 116005 (Illinois Supreme Court, 2015)
People ex rel. Madigan v. Illinois Commerce Comm'n
2013 IL App (2d) 120243 (Appellate Court of Illinois, 2013)
Apple Canyon Lake Property Owners' Ass'n v. Illinois Commerce Comm'n
2013 IL App (3d) 100832 (Appellate Court of Illinois, 2013)
People v. ILLINOIS COMMERCE COMM'N
958 N.E.2d 405 (Appellate Court of Illinois, 2011)
People v. Illinois Commerce Commission
2011 IL App (1st) 100654 (Appellate Court of Illinois, 2011)
Commonwealth Edison Co. v. Illinois Commerce Commission
937 N.E.2d 685 (Appellate Court of Illinois, 2010)
Archer-Daniels-Midland Co. v. Illinois Commerce Commission
687 N.E.2d 1144 (Appellate Court of Illinois, 1997)
Cook County State's Attorney v. Illinois State Labor Relations Board
684 N.E.2d 970 (Appellate Court of Illinois, 1997)
City of Chicago v. Illinois Commerce Commission
666 N.E.2d 1212 (Appellate Court of Illinois, 1996)
Citizens Utility Board v. Illinois Commerce Commission
651 N.E.2d 1089 (Illinois Supreme Court, 1995)
Pennsylvania Industrial Energy Coalition v. Pennsylvania Public Utility Commission
653 A.2d 1336 (Commonwealth Court of Pennsylvania, 1995)
Central Illinois Light Co. v. Illinois Commerce Commission
626 N.E.2d 728 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
620 N.E.2d 1141, 250 Ill. App. 3d 317, 189 Ill. Dec. 824, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-finkl-sons-co-v-illinois-commerce-commission-illappct-1993.