A & A Mechanical, Inc. v. Satterfield & Pontikes Construction Group, LLC

83 So. 3d 363, 2011 La.App. 4 Cir. 0784, 2012 WL 90133, 2012 La. App. LEXIS 13
CourtLouisiana Court of Appeal
DecidedJanuary 11, 2012
DocketNo. 2011-CA-0784
StatusPublished
Cited by3 cases

This text of 83 So. 3d 363 (A & A Mechanical, Inc. v. Satterfield & Pontikes Construction Group, LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A & A Mechanical, Inc. v. Satterfield & Pontikes Construction Group, LLC, 83 So. 3d 363, 2011 La.App. 4 Cir. 0784, 2012 WL 90133, 2012 La. App. LEXIS 13 (La. Ct. App. 2012).

Opinion

ROLAND L. BELSOME, Judge.

|tA & A Mechanical, Inc. appeals the trial court’s dismissal without prejudice of its claims against Satterfield & Pontikes Construction Group, L.L.C. and Chris Head and referral of the matter in its entirety to arbitration. For the reasons that follow, we find that the trial court committed legal error in failing to allow claims outside of the scope of the arbitration clause to proceed in state court and reverse and remand.

FACTS AND PROCEDURAL HISTORY

On November 25, 2008, Appellee, contractor Satterfield & Pontikes Construction Group, L.L.C. (“S & P”), entered into a subcontract with Appellant, A & A Mechanical, Inc. (“A & A”) to perform work in connection with the construction of L.B. Landry High School in Algiers, Louisiana. On January 6, 2011, A & A filed suit, naming S & P and Chris Head, the project manager for S & P, as defendants. In the petition, A & A asserted that it was not paid for all the work performed under the subcontract.1 In addition to the breach of contract claims, |2A & A also alleged that Chris Head demanded side payments of cash and other benefits from A & A as a kickback on the job and threatened that if A & A refused to pay the kickbacks, he would make things “difficult” for A & A. A & A further asserted that although A & A’s principles notified George Pontikes, the manager of S & P, of Head’s demands for cash and kickbacks, neither S & P nor Pontikes attempted to address the issue.

A & A alleged that as a result of the refusal to provide kickbacks to Chris Head, A & A suffered retaliation. Specifically, A & A asserted that S & P barred A & A’s project manager, Kenny Diaz, from the jobsite; refused A & A’s payment applications, requiring A & A to resubmit payment applications and/or change order requests multiple times to include additional detail and supporting documentation beyond what was typically required; failed to respond to requests for information about the project; and refused to coordinate ongoing work with A & A. As a result, A & A argues that it suffered lost profits and business opportunity, and that A & A’s overhead and labor costs were increased. A & A contended that Chris Head and S & P’s actions and inactions constituted unfair trade practices and tor-tious interference; that S & P was vicariously liable for Chris Head’s actions; and that S & P had been unjustly enriched by A& A.

[366]*366S & P filed an exception of prematurity, arguing that the subcontract provided that any disputes arising out of the subcontract should be mediated, and if mediation was unsuccessful, the dispute was to be settled by binding arbitration. The matter was heard on March 18, 2011, and the trial court granted S & P’s | (¡exception on March 29, 2011, dismissing all of A & A’s claims without prejudice and referring the entire matter to arbitration. This appeal followed.

STANDARD OF REVIEW

A determination regarding whether to stay or to compel arbitration is a question of law. Saavedra v. Dealmaker Developments, LLC, 2008-1239, p. 6 (La.App. 4 Cir. 3/18/09), 8 So.3d 758, 762, writ denied, 2009-0875 (La.6/5/09), 9 So.3d 871 (citing Billieson v. City of New Orleans, 02-1993, p. 3 (La.App. 4 Cir. 9/17/03), 863 So.2d 557, 560). Accordingly, an appellate court reviews questions of law to determine whether the trial court was legally correct or incorrect. Id. Specifically, an appellate court “should consider de novo issues of law concerning whether the dispute was within the scope of the arbitration agreement, unless the parties also clearly agreed that the issue of whether a dispute was arbitrable was subject to arbitration.” Collins v. Prudential Ins. Co. of Am., 1999-1423, p. 7, n. 11 (La.1/19/00), 752 So.2d 825, 830; see also Hoffman, Siegel, Seydel, Bienvenu & Centola, APLC v. Lee, 2005-1491, pp. 4-5 (La.App. 4 Cir. 7/12/06), 936 So.2d 853, 856, writ denied, 2006-1995 (La.11/3/06), 940 So.2d 671 (recognizing that “[i]f the trial court’s decision was based on an erroneous interpretation or application of law, rather than a valid exercise of discretion, such [an] incorrect decision is not entitled to deference by the reviewing court”)(quoting Dufrene v. HBOS Mfg., LP, 2003-2201, p. 2 (La.App. 4 Cir. 4/7/04), 872 So.2d 1206, 1209).

DISCUSSION

At the outset, S & P argues that A & A has no right to directly appeal the trial court’s dismissal without prejudice of A & A’s claims, asserting that such judgment is interlocutory and not appealable. In this case, the trial court did not stay the proceedings pending arbitration; the court dismissed the matter in its entirety, |4leaving the trial court with nothing to decide. Therefore, the trial court’s judgment dismissing all of A & A’s claims was a determination of the merits and constitutes a final appealable judgment pursuant to La. C.C.P. art. 1841.2

A & A asserts three assignments of error for our review. First, A & A argues that the trial court erred in compelling arbitration when there was no evidence of a written agreement wherein A & A and Head agreed to arbitrate any disputes between them. A & A further submits that the trial court erred in compelling arbitration of A & A’s tortious conduct claims [367]*367against S & P because the tort actions fall outside the scope of the arbitration agreement contained within the subcontract. In the third and final assignment of error, A & A argues that the trial court erred in compelling arbitration of A & A’s vicarious liability claim because S & P is solidarily liable with Head’s for his tortious conduct and A & A has only one joint cause of action against Head and S & P.

The relevant portion of the subcontract between A & A and S & P provided, under the heading “Settlement Disputes” in Section 11, Paragraph (d):

In the event any controversy or dispute arises between Subcontractor [A & A] and Contractor [S & P] relating to this subcontract (or breach thereof), which dispute or controversy does not involve the correlative rights and duties of owner, Subcontractor shall request mediation of the dispute with Contractor and the parties shall attempt in good faith to mediate the dispute. Mediation shall be a condition precedent to any further rights that the Subcontractor has to the resolution of the dispute.

The subcontract further provides, in subsection (i) under Paragraph (d):

Islf the mediation is unsuccessful, then Subcontractor [A & A] agrees that Contractor [S & P] shall make the determination (in its sole discretion) as to whether the dispute shall be settled by binding arbitration in accordance with the Construction Industry Arbitration Rules (then applicable) of the American Arbitration Association (in which case Subcontractor [A & A] agrees that it will submit its disputes to such arbitration statutes including the Federal Arbitration Act). Any arbitration held under this provision shall be held in Harris County, Texas.3

Generally, any doubt should be resolved in favor of arbitration. Aguillard v. Auction Management Corp., 04-2804, 04-2857, p. 6 (La.6/29/05), 908 So.2d 1, 7; Dufrene v. HBOS Mfg., LP, 2003-2201, pp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kyle Durand v. Kandy Rose
Louisiana Court of Appeal, 2022

Cite This Page — Counsel Stack

Bluebook (online)
83 So. 3d 363, 2011 La.App. 4 Cir. 0784, 2012 WL 90133, 2012 La. App. LEXIS 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-a-mechanical-inc-v-satterfield-pontikes-construction-group-llc-lactapp-2012.