716 Windsor Street Associates, LLC v. Catholic Charities/Catholic Family Services, Inc.

842 A.2d 1162, 82 Conn. App. 133, 2004 Conn. App. LEXIS 113
Connecticut Appellate Court·Decided March 23, 2004·No. AC 24094·Published

Opinion

[135] Opinion

SCHALLER, J.

In this breach of contract action, the plaintiff, 716 Windsor Street Associates, LLC, appeals from the judgment of the trial court, rendered after a trial to the court, in favor of the defendant, Catholic Charities/Catholic Family Services, Inc. On appeal, the plaintiff claims that the court improperly concluded that (1) the plaintiff did not substantially complete required repair work, which was a condition precedent to the commencement of the parties’ lease, and (2) as a matter of law, the repair work was not substantially completed where the plaintiffs contractor had certified its completion. We affirm the judgment of the trial court.

The court found the following facts that are relevant to the plaintiffs appeal. The plaintiff and the defendant signed a thirty-six month lease for the subject premises. The anticipated commencement date of the lease was July 1, 2000. Exhibit C of the lease set forth a timetable for the completion of the plaintiffs work. Exhibit C contained nine items to be completed by the landlord, seven of which were “delay items” that had to be completed by the commencement date. The lease provided in relevant part that the landlord’s work “shall be deemed completed . . . [by] the date on which Landlord’s Work is substantially complete and ready for occupancy as certified by Landlord’s architect or contractor, with the exception of the Non-Delay items.” The lease further provided in relevant part that the commencement date begins when “the Premises are deemed ready for occupancy and are available to Tenant and Tenant’s acceptance of such completion.”

The lease contained a cancellation provision for the defendant to terminate the lease agreement if the work was not completed by July 1, 2000. It provided that the “[t]enant may elect to cancel this Lease at any time thereafter while the Landlord’s Work is not completed [136] by giving written notice to Landlord of such cancellation, which notice shall be effective forty-five (45) days after Landlord’s Work, in which event such notice of cancellation shall be rendered null and void .... Tenant’s right to cancel the lease pursuant to this Section shall be Tenant’s sole remedy at law or in equity for Landlord’s failure to complete the Landlord’s work

The plaintiff signed a repair proposal with its contractor, Imagineers, LLC (Imagineers), that was contingent on the defendant’s signing the lease agreement. Nine days prior to the signing of the lease, the plaintiff crossed out the repair work for the concrete block wall on its repair agreement with Imagineers. The plaintiff subsequently entered into the lease with the defendant with the provision for the concrete block wall still included. Imagineers was not aware of all the required provisions contained in the lease between the defendant and the plaintiff.

In July, 2000, the defendant expressed its concerns to the plaintiff that the work had not been completed and that there were outstanding safety and regulatory issues. On August 22,2000, the defendant issued a notice of cancellation of the lease agreement. The plaintiff received the notice by August 24, 2000. The forty-five day cure period in the lease gave the plaintiff until October 8, 2000, to substantially complete all repairs. On August 24, 2000, Imagineers certified that the required repair work was substantially completed and that the premises were ready for occupancy. The defendant responded by correspondence dated August 28, 2000, stating that five of the seven delay items were not completed. As of October 8,2000, it was undisputed that the plaintiff had not completed two of the delay items listed in exhibit C. First, the plaintiff installed a wooden wall instead of enclosing the premises with concrete block or brick, as required in exhibit C. Sec[137] ond, the plaintiff failed to enclose the second floor rear windows with concrete block or brick, as specified, but instead enclosed them with a wood and wire mesh. The court also found that the plaintiff had failed to finish the wall repairs and painting, but that this work was substantially complete. Both of the nondelay items were not completed. Additional facts will be set forth as necessary.

I

The plaintiff claims that the court improperly concluded that the plaintiff did not substantially complete the required repair work. Specifically, the plaintiff argues that the court improperly determined that the repair work was not substantially completed during the forty-five day cure period because the defendant failed to specify the particular deficiency. Further, the plaintiff argues that the court improperly concluded that the plaintiff acted in bad faith by not substantially completing the repair work.

“Factual findings . . . are reviewed under the clearly erroneous standard of review. ... A factual finding is clearly erroneous when it is not supported by any evidence in the record or when there is evidence to support it, but the reviewing court is left with the definite and firm conviction that a mistake has been made. . . . Simply put, we give great deference to the findings of the trial court because of its function to weigh and interpret the evidence before it and to pass upon the credibility of witnesses.” (Citation omitted; internal quotation marks omitted) Advanced Financial Services, Inc. v. Associated Appraisal Services, Inc., 79 Conn. App. 22, 31-32, 830 A.2d 240 (2003). “[W]here the legal conclusions of the court are challenged, we must determine whether they are legally and logically correct. . . . Thus, where the issues present questions of law, [they are] subject to our plenary review.” (Cita[138] tion omitted; internal quotation marks omitted.) In re David W., 254 Conn. 676, 686, 759 A.2d 89 (2000).

The plaintiff had forty-five days to substantially complete the repair work required by exhibit C of the lease once the defendant gave notice of the cancellation. The defendant did not specifically reference in its cancellation notice the plaintiffs failure to enclose the wooden section of the rear wall of the premises or the second floor rear windows with concrete block or brick. The defendant did, however, reference general safety and regulatory concerns. It is not disputed that once the forty-five day cure period had passed, the plaintiff had not completed the two delay items previously mentioned.

Free access — add to your briefcase to read the full text and ask questions with AI

716 Windsor Street Associates, LLC v. Catholic Charities/Catholic Family Services, Inc., 842 A.2d 1162, 82 Conn. App. 133, 2004 Conn. App. LEXIS 113 (Colo. Ct. App. 2004).

842 A.2d 1162 (716 Windsor Street Associates, LLC v. Catholic Charities/Catholic Family Services, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re David W.
759 A.2d 89 (Supreme Court of Connecticut, 2000)
K. A. Thompson Electric Co. v. Wesco, Inc.
604 A.2d 828 (Connecticut Appellate Court, 1992)
Rosado v. Bridgeport Roman Catholic Diocesan Corp.
825 A.2d 153 (Connecticut Appellate Court, 2003)
Advanced Financial Services, Inc. v. Associated Appraisal Services, Inc.
830 A.2d 240 (Connecticut Appellate Court, 2003)