This text of 362 A.2d 78 (68th St. Apts., Inc. v. Lauricella) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
68th St. Apts., Inc. v. Lauricella, 362 A.2d 78, 142 N.J. Super. 546 (N.J. Ct. App. 1976).

Opinion

142 N.J. Super. 546 (1976)
362 A.2d 78

68TH STREET APTS., INC., A NEW JERSEY CORPORATION, ET AL., PLAINTIFFS,
v.
CASIMIRO LAURICELLA, D/B/A CASS ELECTRIC CO., DEFENDANT. CASIMIRO LAURICELLA, D/B/A CASS ELECTRIC CO., PLAINTIFF,
v.
INTROCASO CONSTRUCTION CO., INC. AND RALPH L. INTROCASO, DEFENDANTS.

Superior Court of New Jersey, Law Division.

Decided May 13, 1976.

*549 Messrs. Gigante & Aslanian, attorneys for Casimiro Lauricella, d/b/a Cass Electric Co. (Mr. Antranig Aslanian, Jr., appearing).

Messrs. Platoff, Heftler, Harker & Nashel, attorneys for Introcaso Construction Co., Inc. and Ralph L. Introcaso (Mr. Howard M. Nashel appearing).

GAULKIN, J.S.C.

These consolidated actions arise out of a complex of business relationships entered into by Casimiro Lauricella and Ralph L. Introcaso with respect to two properties known as 6818 Park Avenue and 138-142 68th Street, both in Guttenberg, New Jersey.

I. 6818 Park Avenue

In early 1972 Lauricella, an electrical contractor, learned that 6818 Park Avenue was available for purchase and contacted Introcaso, a building contractor known to him from other projects, who expressed interest in their jointly purchasing and developing the property. After determining that an apartment building of approximately 30 units could be accommodated on the site, Lauricella and Introcaso negotiated with the then owner and reached agreement on a purchase at $70,000.

Lauricella and Introcaso then orally agreed that they would participate equally in the purchase and ownership; that they would use Mario M. Polcari, Esq. as their attorney; that they would hold the property in corporate form; that Introcaso's company, Introcaso Construction Co., Inc. (ICC) would be the general contractor for the contemplated construction, and that Lauricella, who was a major stockholder of certain banks, would arrange the necessary financing.

*550 Pursuant to that agreement Lauricella and Introcaso formed 6818 Park Avenue Corporation (6818), a New Jersey corporation; each was issued five shares of common capital stock, the only corporate stock then or thereafter issued. The minutes of the initial corporate meeting recite that Lauricella was elected president and Introcaso secretary and treasurer; they do not indicate any election of directors, and neither the by-laws nor the certificate of incorporation fix the number of directors authorized. Lauricella contributed $35,000 to the capital of the corporation and Introcaso contributed $34,134, which funds were used for the purchase of the title.

Construction commenced in October 1972 but, as more fully discussed below, the project aborted and on April 16, 1973 Introcaso filed an action in the Chancery Division (Docket C-2943-72) to dissolve 6818 under N.J.S.A. 14A:12-7 by reason of deadlock. By order there entered on August 31, 1973, 6818 was dissolved; Thomas M. Venino, Esq. was appointed as receiver; and the process of making distribution to creditors and winding up the corporate affairs was initiated. Following extensive hearings conducted by him pursuant to N.J.S. 14A:14-16, the receiver filed his findings concerning the creditors' claims. His determinations were upheld by order entered September 19, 1975. In light of those findings in the Chancery Division action (which was consolidated with this proceeding until its disposition), this court determined, by order entered December 19, 1975, that the parties here are collaterally estopped from litigating the following factual determinations:

1. That there was a verbal agreement between ICC and 6818, the terms of which are set forth in the opinion of the receiver dated November 1, 1974;
2. That 6818 breached that agreement;
3. That as a result of that breach, ICC sustained damages of $88,494.41.

The terms of the agreement between 6818 and ICC incorporated by reference in the December 19, 1975 order *551 and thus deemed to be a finding of fact herein, were found in the Chancery Division to be as follows:

They [i.e., Introcaso and Lauricella] further agreed, orally, that ICC would act as the general contractor and would deliver to the owner corporation a "turnkey" 30 family apartment building at cost plus 8% for ICC's services and efforts. ICC was to have the option of performing any of the sub trades at cost plus 15% overhead plus 10% profit so long as that gross cost did not exceed a competitive price. Similarly, [Lauricella], an experienced electricial contractor, could elect to perform the electrical work on the project at cost plus 15% overhead plus 10% profit so long as that gross cost did not exceed a competitive price. I find that the parties understood that so long as the costs were reasonable and competitive, ICC would perform the masonry portion of the project since it was an experienced mason contractor and that [Lauricella] would perform the electrical portion for the same reason. Although there was a conflict as to whether ICC would be entitled to an 8% overwrite on the masonry work performed by it or on the electrical work performed by [Lauricella], I find from all the evidence that the intention of the parties was to compensate ICC at the rate of 8% on subcontracted work for its services as general contractor, and also on the work it performed as masonry contractor and on the electrical portion of the project whether performed by [Lauricella] or others.

In winding up the corporate affairs the receiver sold the real estate for $110,000 and, after deducting fees and expenses of the receivership, paid out all of the corporate funds to creditors, each creditor receiving approximately 84.51 cents on each dollar of claim. The major claimant was ICC, which received $74,785.90 on its allowed claim of $88,494.41. No return of capital was therefore available to Lauricella or Introcaso as stockholders.

The parties now assert the following claims:

1. Introcaso claims that Lauricella wrongfully and maliciously caused 6818 to breach its contract with ICC and thereby caused the project to abort. He seeks recovery for his losses as a stockholder and claims, derivatively, on behalf of 6818, the losses sustained by the corporation.
2. Lauricella contends that it was Introcaso himself who caused the breach of the ICC contract and the failure *552 of the project; he claims against Introcaso the same losses as are urged by Introcaso.
3. ICC claims against Lauricella for wrongful and malicious interference with the contract between ICC and 6818; it claims compensatory damages arising therefrom in the sum of $13,708.51, being the difference between the damages for the breach of that contract as found by the receiver and the sum received by it in the liquidation.

Both claimants also seek punitive damages, interest and costs and, in connection with the derivative claims on behalf of 6818, the award of counsel fees.

A. Findings of Fact

After taking title in March 1972, 6818 prepared plans and demolished the buildings then on the site. Lauricella arranged for construction and permanent financing through United Jersey Mortgage Company, which issued its $360,000 mortgage commitment on August 16, 1972; Lauricella and Introcaso accepted the commitment on behalf of 6818 on September 21, 1972.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jana M. Watts v. Joseph F. Farinella
New Jersey Superior Court App Division, 2024
Fischer v. Fischer
197 S.W.3d 98 (Kentucky Supreme Court, 2006)
Chiron Corp. v. Director, Division of Taxation
21 N.J. Tax 528 (New Jersey Tax Court, 2004)
Pagonis v. Donnelly
929 F. Supp. 459 (District of Columbia, 1995)
Wanaque Borough Sewerage Auth. v. TP. OF WEST MILFORD
656 A.2d 448 (New Jersey Superior Court App Division, 1995)
Tibball v. Galog, No. Cv94 0311149s (Aug. 26, 1994)
1994 Conn. Super. Ct. 8634 (Connecticut Superior Court, 1994)
Fliegel v. Sheeran
640 A.2d 852 (New Jersey Superior Court App Division, 1994)
Leadership Real Estate v. Harper
638 A.2d 173 (New Jersey Superior Court App Division, 1993)
Chandler Medical Building Partners v. Chandler Dental Group
855 P.2d 787 (Court of Appeals of Arizona, 1993)
Walker Rogge v. Chelsea Title & Guar.
603 A.2d 557 (New Jersey Superior Court App Division, 1992)
Walter v. Holiday Inns, Inc.
784 F. Supp. 1159 (D. New Jersey, 1992)
Berger v. Berger
592 A.2d 321 (New Jersey Superior Court App Division, 1991)
Fanarjian v. Moskowitz
568 A.2d 94 (New Jersey Superior Court App Division, 1989)
Monteleone v. Monteleone
497 N.E.2d 1221 (Appellate Court of Illinois, 1986)
Gregory Marketing Corp. v. Wakefern Food Corp.
504 A.2d 828 (New Jersey Superior Court App Division, 1985)
Erlich v. First Nat'l Bank of Princeton
505 A.2d 220 (New Jersey Superior Court App Division, 1984)
Estate of Schroer v. Stamco Supply, Inc.
482 N.E.2d 975 (Ohio Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
362 A.2d 78, 142 N.J. Super. 546, Counsel Stack Legal Research, https://law.counselstack.com/opinion/68th-st-apts-inc-v-lauricella-njsuperctappdiv-1976.