49Hopkins, LLC v. City and County of San Francisco

District Court, N.D. California·Decided September 2, 2020·No. 3:19-cv-00811·Unknown

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 NORTHERN DISTRICT OF CALIFORNIA 6 7 49HOPKINS, LLC, Case No. 19-cv-00811-SI

8 Plaintiff, ORDER GRANTING IN PART AND 9 v. DENYING IN PART DEFENDANTS' MOTION TO DISMISS SECOND 10 CITY AND COUNTY OF SAN AMENDED COMPLAINT FRANCISCO, et al., 11 Re: Dkt. No. 54 Defendants. 12 13 14 Now before the Court is a motion to dismiss filed by defendants City and County of San 15 Francisco (“the City”), Planning Commission of the City and County of San Francisco (“Planning 16 Commission”), San Francisco Planning Department (“Planning Department”), San Francisco 17 Department of Building Inspection (“DBI”), and the San Francisco Board of Supervisors (“BOS”). 18 Pursuant to Civil Local Rule 7-1(b) and General Order No. 72-5, the Court finds this matter 19 appropriate for resolution without oral argument and VACATES the hearing set for September 4, 20 2020. The Court CONTINUES the case management conference to October 16, 2020, at 3:00 p.m. 21 For the reasons set forth below, the Court GRANTS IN PART and DENIES IN PART the motion 22 to dismiss. 23 24 BACKGROUND 25 This lawsuit arises out of the demolition of a home in the Twin Peaks neighborhood of San 26 Francisco. Plaintiff is a California limited liability company and is the owner of real property 27 situated at 49 Hopkins Avenue, San Francisco, California. Dkt. No. 51 (“SAC”) ¶ 3. The subject 1 by well-known architect Richard Neutra. Id. ¶ 21. The home had since been altered, primarily 2 between 1959 and 2004, to include a second story, garage, and an enclosed swimming pool. Id. 3 Post-alterations, the property included a 240 square foot garage; a 1,312 square foot two-story, one- 4 bedroom home; and a 1,580 square foot indoor pool house, for a total of 3,132 square feet. Id. ¶ 22. 5 In 2014, the then-property owner engaged an architect to redesign the property into a three- 6 story, four-bedroom/four bath, 3,675 square foot single-family home with a 240 square foot garage. 7 Id. ¶ 23. The architect submitted the plans to the Planning Department, the then-owner engaged an 8 architectural historian as required to conduct a historic evaluation of the property,1 and on July 25, 9 2014, the then-owner began the permit approval process by submitting the architectural plans 10 (commonly referred to as a “site plan”) to DBI. Id. ¶¶ 23-25. The site plan and subsequently 11 submitted addendum (including structural engineering plans) were part of the plans that were 12 approved under the assigned permit number (“2014 Permit”). Id. ¶ 25. On or about August 10, 13 2015, the Planning Department approved the site plan, which authorized:

14 REMOVAL [OF] EXISTING SUNROOM, INTERIOR REMODEL & VERTICAL ADDITION. WORK TO INCL: VERTICAL 15 ADDITION ABOVE THE 2ND FLOOR, INTERIOR REMODEL OF 1ST & 2ND FLOOR. FRONT YARD TO REMOVE EXISTING 16 WALL ENCLOSURE & PROPOSE LANDSCAPE. 17 Id. ¶ 26. The 2014 Permit required maintaining “(1) portions of the east side CMU [concrete 18 masonry unit] wall; (2) portions of the existing second story kitchen floor; (3) portions of the 19 existing framing above the garage; (4) portions of the westside wall at the bottom of [the] stairs 20 leading to the front entrance[;] and (5) the underlying structure supporting the east side windows.” 21 Id. ¶ 31. 22 On or about December 3, 2015, after the Planning Department and DBI’s approval of the 23 site plan, the then-property owner submitted a structural engineering plan addendum to DBI as part 24 of DBI’s process for approving the 2014 Permit. Id. ¶ 28. In May 2016, DBI approved and stamped 25 the 2014 Permit for the proposed three-story, four-bedroom/four bath single-family home, 26

27 1 The architectural historian determined the property “was not a historic resource given the 1 containing 3,675 square foot of living space and a 240 square foot garage. Id. 2 Plaintiff purchased the property and 2014 Permit in January 2017. Id. ¶ 29. Work on the 3 property began in August 2017 after plaintiff secured construction financing. Id. The SAC alleges, 4 “During the approved demolition work at the Property, the General Contractor exposed various 5 portions of the existing building structure that were previously hidden behind walls. Upon exposure, 6 the General Contractor discovered that several of the structural elements expected to remain in place 7 by the 2014 Permit were, in fact, structurally compromised and he determined that those elements 8 posed immediate life-safety dangers to his construction crew.” Id. ¶ 30. “The General Contractor, 9 based on his professional experience and knowledge, understood and determined that the 10 compromised structural elements uncovered during demolition would need to be removed one way 11 or the other because they could not structurally support the three-story home in the 2014 Permit 12 AND because they posed immediate life-safety hazards for workers.” Id. ¶ 37 (emphasis omitted). 13 Rather than stop work, plaintiff’s general contractor “immediately remove[d] the compromised 14 structure for life-safety reasons even though the 2014 Permit called for maintaining those structural 15 elements as part of the new home.” Id. Plaintiff’s general contractor “understood that as a matter 16 of long-standing practice at DBI, the removal of the compromised structure would necessarily 17 require submission of revised structural engineering plans to DBI as part of an alteration permit 18 prior to commencement of any construction.” Id. 19 On October 4, 2017, in response to a neighbor’s complaint, DBI issued a Notice of Violation 20 (“NOV”) “for the portion of demolition work that had occurred beyond the scope of the 2014 21 Permit.” Id. ¶ 38 (emphasis omitted). The notice of violation states that “it appears the scope of 22 demolition has been exceeded. The entire house has been demolished, except for the garage area.” 23 Dkt. No. 37 at 6 (RJN Ex. B – Notice of Violation);2 see also Dkt. No. 55 at 4 (Defs’ RJN Ex. A – 24 Notice of Violation).3 The NOV cited San Francisco Building Code (“SFBC”) section 106A.4.7, 25 2 For ease of reference, all citations to page numbers refer to the ECF branded number in the 26 upper right corner of documents.

27 3 The Court previously granted judicial notice of this document. Dkt. No. 48 at 1 n.1. The 1 “ADDITIONAL WORK-PERMIT REQUIRED.” SAC ¶ 38. The NOV listed three Corrective 2 Actions: “STOP ALL WORK SFBC section 104A.2.4, file building permit application within 15 3 days with plans, and obtain permit within 30 days and complete all work within 60 days including 4 final inspection and sign-off.” Id. The NOV further stated, “STOP ALL WORK. Submit plans 5 that show full scope of demolition. Plans shall be routed to Planning Dept. For [sic] review and 6 approval. No work may take place until a new building permit has been obtained.” Dkt. No. 55 at 7 4 (Defs’ RJN Ex. A – Notice of Violation). 8 A meeting among plaintiff’s representatives and senior DBI inspectors followed. SAC ¶ 39. 9 Plaintiff alleges that on October 20, 2017, BOS member Aaron Peskin wrote to several individuals, 10 including the head of the Planning Department and the Planning Department’s Zoning 11 Administrator regarding the subject property and said, “This is insane. We need to figure out how 12 to stop this. I am going to start holding hearings as this is happening way too often and is entirely 13 unacceptable.” Id. ¶ 40. That same day, the Planning Department’s Zoning Administrator stated 14 via email that the subject property “wasn’t a historic resource because it no longer retained integrity 15 given past alterations. Also. . . the building last sold for $1.7 million . . . so it may appraise out of 16 the CU requirement.” Id. (ellipses and emphases in SAC). The SAC states, “The ‘CU requirement’ 17 refers to Planning Code section 317, under which ‘tantamount to demolition’ violations under the 18 Planning Code are processed.

Free access — add to your briefcase to read the full text and ask questions with AI

49Hopkins, LLC v. City and County of San Francisco, (N.D. Cal. 2020).

49Hopkins, LLC v. City and County of San Francisco (49Hopkins, LLC v. City and County of San Francisco) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Norman v. Apache Corp.
19 F.3d 1017 (Fifth Circuit, 1994)
Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
Ruckelshaus v. Monsanto Co.
467 U.S. 986 (Supreme Court, 1984)
City of Cleburne v. Cleburne Living Center, Inc.
473 U.S. 432 (Supreme Court, 1985)
Kokkonen v. Guardian Life Insurance Co. of America
511 U.S. 375 (Supreme Court, 1994)
Romer v. Evans
517 U.S. 620 (Supreme Court, 1996)
United States v. Bajakajian
524 U.S. 321 (Supreme Court, 1998)
Lingle v. Chevron U. S. A. Inc.
544 U.S. 528 (Supreme Court, 2005)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Blair v. Bethel School District
608 F.3d 540 (Ninth Circuit, 2010)
Gerhart v. Lake County, Mont.
637 F.3d 1013 (Ninth Circuit, 2011)
Nl Industries, Inc. v. Stuart M. Kaplan
792 F.2d 896 (Ninth Circuit, 1986)
Steven J. Harris v. County of Riverside
904 F.2d 497 (Ninth Circuit, 1990)