3M Co. (Minnesota Mining & Manufacturing) v. Browner

17 F.3d 1453, 305 U.S. App. D.C. 100, 1994 WL 62318
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 4, 1994
DocketNo. 92-1126
StatusPublished
Cited by16 cases

This text of 17 F.3d 1453 (3M Co. (Minnesota Mining & Manufacturing) v. Browner) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
3M Co. (Minnesota Mining & Manufacturing) v. Browner, 17 F.3d 1453, 305 U.S. App. D.C. 100, 1994 WL 62318 (D.C. Cir. 1994).

Opinion

Opinion for the court filed by Circuit Judge RANDOLPH.

RANDOLPH, Circuit Judge:

This petition for review of the Environmental Protection Agency’s assessment of civil penalties turns on the meaning of 28 U.S.C. § 2462, the direct descendant of a statute of limitations enacted more than a century and a half ago. There, are three questions. Does § 2462 apply to administrative proceedings? If so, is a proceeding to assess a civil penalty an action for the enforcement of a penalty within § 2462’s meaning? If it is, does § 2462’s five-year period of limitations begin running only when EPA reasonably could have been expected to detect the violations giving rise to the civil penalties?

I

Between August 1980 and July 1986, 3M unwittingly committed several violations of the Toxic Substances Control Act (TSCA), 15 U.S.C. §§ 2601-2629. On July 28, 1986, after the company became aware of its transgressions, it notified EPA’s compliance office. The company had learned that one of its chemicals, Chemical A,1 was not on an EPA inventory of existing chemicals. Although 3M had believed that Chemical A came from a manufacturer in this country, the company’s investigation revealed that 3M received the chemical from the manufacturer’s Canadian affiliate.

At least ninety days before a new chemical may be imported, TSCA requires the importer to provide EPA with a Premanufacture Notice. 15 U.S.C. § 2604(a)(1). Because Chemical A was both new and imported, 3M’s importation of Chemical A without the requisite notice violated this provision. In addition, 3M’s brokers wrongly certified to Customs officials that TSCA’s requirements had been met.

The mishap with Chemical A spurred 3M to review its other imported chemicals. Thus, it discovered a problem with Chemical B. This chemical has the same code and the same use as another chemical listed on the inventory of existing chemicals. When 3M imported Chemical B on various occasions between July 15,1983, and August 4, 1986, it assumed Chemical B was not new and did not require a Premanufacture Notice. Closer inspection revealed that Chemical B was not identical to the chemical on the inventory. As with Chemical A, a Premanufacture [1455]*1455Notice had been required but not submitted, and the Customs certifications regarding compliance with TSCA were incorrect. On September 16, 1986, 3M notified EPA of the violations concerning Chemical B.

Two years later, on September 2, 1988, EPA filed an administrative complaint against 3M seeking $1.3 million in civil penalties under § 16(a)(2)(A) of TSCA for 3M’s failure to file Premanufaeture Notices and for 3M’s submitting inaccurate Customs certifications with respect to Chemicals A and B. Section 16(a)(2)(A), 15 U.S.C. § 2615(a)(2)(A), provides that the EPA Administrator shall assess civil penalties for violations of the Act “by an order made on the record after opportunity ... for a hearing. ...”

In its answer to the complaint, 3M interposed a statute of limitations — 28 U.S.C. § 2462 — claiming that the statute barred proceedings to impose penalties for 3M’s importation of the chemicals without the requisite notices five years prior to EPA’s complaint, that is, before September 1983. An EPA Administrative Law Judge ruled that no statute of limitations applied to § 16(a)(2)(A) proceedings. The ALJ found 28 U.S.C. § 2462 inapplicable on the grounds that it applied only to judicial proceedings; and that, in any event, civil penalty cases under § 16 of TSCA were not the sort of enforcement proceedings covered by § 2462. After the ALJ assessed a civil penalty of $104,720, 3M filed an administrative appeal with the EPA Chief Judicial Officer, who acts as the Administrator’s delegate in these cases. The Chief Judicial Officer, “adopting] and incorporating]” the “applicable portions” of the ALJ’s opinion, also ruled that § 2462 did not apply.2 He then assessed a penalty against 3M of $130,650. This petition followed.

II

Any person who violates § 15 of TSCA, 15 U.S.C. § 2614, “shall be liable to the United States for a civil penalty in an amount not to exceed $25,000 for each such violation.” 15 U.S.C. § 2615(a)(1). Before the EPA Administrator assesses a penalty pursuant to § 16(a)(2)(A), the alleged violator has the right to a hearing. 15 U.S.C. § 2615(a)(2)(A). If the hearing results in the Administrator’s issuing an order fixing liability and setting the amount of the penalty, any person “aggrieved” has thirty days to file a petition for review in a federal court of appeals. 15 U.S.C. § 2615(a)(3).

While TSCA thus sets a deadline on the alleged violator’s petition for judicial review, TSCA contains no provision limiting the time within which the EPA Administrator must initiate the administrative action. If there is such a time limit, it must be derived from the five-year statute of limitations, '28 U.S.C. § 2462, generally applicable to civil fines and penalties, which reads:

Except as otherwise provided by Act of Congress, an action, suit or proceeding for the enforcement of any civil fine, penalty, or forfeiture, pecuniary or otherwise, shall not be entertained unless commenced within five years from the date when the claim first accrued if, within the same period, the offender or the property is found within the United States in order that proper service may be made thereon.

A

The most fundamental question raised by 3M’s invocation of § 2462 is whether the statute applies to civil penalty cases brought before agencies. The question has received little attention in judicial opinions. In one case, the government and the defendant agreed that § 2462 “at least requires that any administrative action aimed at imposing a civil penalty must be brought within [1456]*1456five years of the alleged violation.” United States v. Meyer, 808 F.2d 912, 914 (1st Cir.1987). In three other cases, the courts have assumed, without discussion, that § 2462 covers administrative penalty proceedings. See Williams v. United States Dep’t of Transp., 781 F.2d 1573, 1578 n. 8 (11th Cir.1986); H.P. Lambert Co. v. Secretary of the Treasury, 354 F.2d 819, 822 (1st Cir.1965); The A/S Glittre v. Dill, 152 F.Supp. 934, 940 (S.D.N.Y.1957).3 Reports of two congressional committees on unrelated legislation, cited in Meyer, also assumed that § 2462 “is applicable to administrative as well as judicial proceedings.” S.Rep. No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BP America v. FERC
Fifth Circuit, 2022
John M. Crim
U.S. Tax Court, 2021
SEC v. Fowler
6 F.4th 255 (Second Circuit, 2021)
Jet ICU Leasing, Inc.
M.D. Florida, 2020
United States v. Rutherford Oil Corporation
756 F. Supp. 2d 782 (S.D. Texas, 2010)
Securities & Exchange Commission v. Alexander
248 F.R.D. 108 (E.D. New York, 2007)
Federal Election Commission v. Larry R. Williams
104 F.3d 237 (Ninth Circuit, 1996)
3m Company v. Carol M. Browner
17 F.3d 1453 (D.C. Circuit, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
17 F.3d 1453, 305 U.S. App. D.C. 100, 1994 WL 62318, Counsel Stack Legal Research, https://law.counselstack.com/opinion/3m-co-minnesota-mining-manufacturing-v-browner-cadc-1994.