19900 W 9 Mile, LLC v. The Hanover Insurance Company

CourtDistrict Court, E.D. Michigan
DecidedJune 9, 2023
Docket2:20-cv-10677
StatusUnknown

This text of 19900 W 9 Mile, LLC v. The Hanover Insurance Company (19900 W 9 Mile, LLC v. The Hanover Insurance Company) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
19900 W 9 Mile, LLC v. The Hanover Insurance Company, (E.D. Mich. 2023).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION 19900 W Nine Mile, LLC, Plaintiff, Case No. 20-10677

v. Hon. Denise Page Hood

THE HANOVER INS. CO.,

Defendant. _______________________________/ ORDER GRANTING PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT [ECF No. 21] and DENYING DEFENDANT’S MOTION FOR SUMMARY JUDGMENT [ECF No. 23]

I. INTRODUCTION This breach of contract case stems from three claims Plaintiff submitted to Defendant pursuant to a policy of commercial property insurance (the “Policy”). The claims arose from two separate water losses and a fire loss at Plaintiff’s commercial building at 19900 W. Nine Mile Road in Southfield (the “Building”), that occurred in February and March 2019. Plaintiff filed a Motion for Summary Judgment on July 23, 2021 [ECF No. 21], and Defendant filed a Motion for Summary Judgment on July 28, 2021. [ECF No. 23] The Motions have been briefed, and a hearing was held.

II. BACKGROUND Plaintiff purchased the Building on October 2, 2018 for $3.5 million. As a

condition of its purchase, Plaintiff was required to escrow $600,000 from its mortgage for planned capital improvements, including replacement of the roof, which had been described as “very old” when Plaintiff bought the Building. The

Building’s anchor tenant, Specs Howard School of Media Art (“Specs Howard”), leased approximately 65% of the available square footage in the Building. In mid- November 2018, water leaks originating at the roof damaged the second-floor bathrooms and marketing room. Plaintiff hired a contractor who timely identified

the source of the leaks and repaired them. That damage is not pertinent to this case. Following that leak, Plaintiff concluded it would be prudent to replace the roof as soon as possible, and Plaintiff’s contractor obtained multiple bids soon thereafter.

Plaintiff accepted a $151,000 bid on January 4, 2019 for the complete tear off and re-roofing of the Building. Materials for the job were delivered on January 15, 2019, and the work began shortly thereafter. On January 23, 2019, while the replacement of the roof was in progress, an accumulation of ice and snow on the roof melted,

causing interior water damage to the Building’s second floor, including classrooms 201, 204, 205, 207; the Marketing room; the Entrance stairs; and the Fiber Optics

room. Plaintiff’s contractor timely identified and repaired the source of the leaks. The January 23, 2019 damage is not at issue in this action.

A. Claim #1: February 4, 2019 Water Loss On February 4, 2019, another freeze/thaw cycle melted 3” to 4” of accumulated ice and snow on the roof and a deluge of water entered the Building,

reaching the first floor and causing significantly greater damage than had previously occurred. The interior water damage affected the same areas of second floor as the prior water intrusions: classrooms 201, 203, 204, 205, 206, 207 and 208. Several first-floor offices and vending area, previously unaffected, were damaged.

Due to the extent of the damage, Plaintiff notified Defendant of the February 4, 2019 loss and its intent to make a claim. Plaintiff’s representative, Jack Echterling (“Echterling”), submitted a Sworn Statement and Proof of Loss to Hanover

Insurance Company dated June 24, 2019 that identified the cause of the loss as “weight of ice/snow.” ECF No. 23, Ex. C at 1. The Proof of Loss sets forth the following figures:1

1 Plaintiff retained Emergency Response Services to perform estimates with respect to the damages in this matter. A copy of the report and estimate from Emergency Response Services includes “an estimate for three claims and will need to be separated per occurrence.” The report provides on page 267 for the following breakdown:

• Replacement Cost Value: $1,115,844.52; • Less depreciation: $222,249.71; • Actual cash value: $893,594.81; • Less deductible: $5,000.00; • Net claim: $888,594.81; • Total recoverable depreciation: $222,249.71; 3

• Actual Cash Value: $144,011.09 • The Whole Loss and Damage: $276,663.36 • Less Amount of Deductible: $ 5,000.00 • The Total Amount Claimed: $271,663.36

Defendant hired Donan Engineering (“Donan”) to inspect the roof and assess the damage. Weather conditions prevented Donan’s Engineer, Andrew Vane, P.E. (“Vane”), from inspecting the property until March 19, 2019. ECF No. 21, Ex. 10. By that date, all but a small portion of the roof had been replaced, including the areas where the February 4, 2019 water intrusion entered the building. Id. at 3-4. Vane concluded that water from the rapid melting of ice and snow infiltrated the building’s interior through pre-existing pathways from age-related deterioration. Id. at 11. He found that:

• The building experienced a widespread water intrusion originating from the roof; • The water intrusion was a recent one-time event; • The water intrusion occurred on February 3 and February 4, during rapid melting of snow and ice on the roof; • The cause of water intrusion is rapid melting of ice and snow, blocked roof dams, and pre-existing pathways for water entry through the roof membrane; • The pre-existing pathways for water entry through the membrane resulted from age-related deterioration; and • The damage to the EPDM membrane was not caused by snow, ice, hail, wind, or storm activity.

• Net claim if depreciation is recovered: $1,110,844.52.

Defendant retained Hexagon General Contractor’s Services, LLC (“Hexagon”) to evaluate the loss, and Hexagon concluded that the replacement cost value for the

loss totaled $133,012.83. Defendant initially confirmed coverage for the loss and issued $200,000 in advance payments on this first water damage claim. ECF No. 21, Ex. 11. Defendant ultimately denied coverage for this loss, however, in

correspondence dated February 11, 2020. Defendant’s denial was based on its investigation, review, evaluation, and analysis of the claim, and concluded that the loss was excluded under the “wear and tear exclusion” as well as the “faulty, inadequate, or defective maintenance” of the roof at issue in the claim.

B. Claim #2: March 25, 2019 Fire Loss On March 25, 2019, the roofers caused a fire while using a torch. The fire damage was limited but smoke entered a nearby air intake vent and caused

substantial damage throughout the Building. Due to the large amount of smoke damage, Specs Howard could not continue its operations in the Building. Within days, Specs Howard arranged to relocate out of the Building to a different location because of the perceived health risk to its students. ECF No. 21, Ex. 12.

Plaintiff provided a sworn statement by Echtrling and Proof of Loss relative to the March 25, 2019 incident, with the following figures: • Actual Cash Value: $895,594.81; • The Whole Loss and Damage: $1,115,844.52; 5

• Less Amount of Deductible: $5,000.00; and • The Amount Claimed: $1,110,844.52.

Defendant again retained Hexagon to evaluate the damages and prepare an estimate with respect to the fire loss, and Hexagon assessed the total replacement cost value for the March 25 fire loss at $35,836.80 (that does not include costs that would otherwise cover the impacted roof portions of the loss). Emergency Response Services, Inc. performed an evaluation regarding the fire loss and estimated the replacement cost to be $146,230.91. Defendant issued

payment with respect to this claim in the amount of $163,520.72 on October 31, 2019. Defendant issued a coverage opinion letter related to the March 25, 2019 fire loss on February 11, 2020, and it identified the payment of $163,520.72. The letter

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Emil Salamey v. Aetna Casualty & Surety Company
741 F.2d 874 (Sixth Circuit, 1984)
Red Cedars, Inc. v. Westchester Fire Insurance
686 F. Supp. 614 (E.D. Michigan, 1988)
Edgar's Warehouse, Inc. v. United States Fidelity & Guaranty Co.
134 N.W.2d 746 (Michigan Supreme Court, 1965)
Fresard v. Michigan Millers Mutual Insurance
327 N.W.2d 286 (Michigan Supreme Court, 1982)
Parmet Homes, Inc. v. Republic Insurance
314 N.W.2d 453 (Michigan Court of Appeals, 1981)
Raska v. Farm Bureau Mutual Insurance
314 N.W.2d 440 (Michigan Supreme Court, 1982)
Lawrence v. Will Darrah & Associates, Inc
516 N.W.2d 43 (Michigan Supreme Court, 1994)
Wendt v. Auto-Owners Insurance
401 N.W.2d 375 (Michigan Court of Appeals, 1986)
Corl v. Huron Castings, Inc.
544 N.W.2d 278 (Michigan Supreme Court, 1996)
Kaczmarck v. La Perriere
60 N.W.2d 327 (Michigan Supreme Court, 1953)
Kewin v. Massachusetts Mutual Life Insurance Company
295 N.W.2d 50 (Michigan Supreme Court, 1980)
Shelby Mutual Insurance v. United States Fire Insurance
162 N.W.2d 676 (Michigan Court of Appeals, 1968)
Griswold Properties, LLC v. Lexington Insurance
741 N.W.2d 549 (Michigan Court of Appeals, 2007)
Bi-Economy Market, Inc. v. Harleysville Insurance
886 N.E.2d 127 (New York Court of Appeals, 2008)
Bowlers' Alley, Inc. v. Cincinnati Insurance
108 F. Supp. 3d 543 (E.D. Michigan, 2015)
Dunn v. Bennett
846 N.W.2d 75 (Michigan Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
19900 W 9 Mile, LLC v. The Hanover Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/19900-w-9-mile-llc-v-the-hanover-insurance-company-mied-2023.