182 Tenth, LLC v. Manhattan Construction Company

CourtCourt of Appeals of Georgia
DecidedJuly 11, 2012
DocketA12A0639
StatusPublished

This text of 182 Tenth, LLC v. Manhattan Construction Company (182 Tenth, LLC v. Manhattan Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
182 Tenth, LLC v. Manhattan Construction Company, (Ga. Ct. App. 2012).

Opinion

FOURTH DIVISION DOYLE, P. J., ANDREWS and BOGGS, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. (Court of Appeals Rule 4 (b) and Rule 37 (b), February 21, 2008) http://www.gaappeals.us/rules/

July 11, 2012

In the Court of Appeals of Georgia A12A0639. 182 TENTH, LLC v. MANHATTAN CONSTRUCTION COMPANY.

ANDREWS, Judge.

182 Tenth, LLC appeals from the judgment entered on a jury verdict granting

Manhattan Construction Company foreclosure on a special lien in the amount of

$1,750,000.00 pursuant to OCGA § 44-14-360 et seq. on real property owned by 182

Tenth. For the following reasons, we reverse and remand the case for a new trial.

Manhattan filed a claim of lien pursuant to OCGA § 44-14-361.1 against 182

Tenth’s real property in the amount of $2,148,122.00 for furnishing labor, services,

and materials on a construction project for the improvement of 182 Tenth’s real

property. The lien claim arose pursuant to a construction contract between Manhattan,

the general contractor, and Mid Atlanta Properties, Inc. in the original amount of $36,250,000.00 to build a condominium complex on 182 Tenth’s property. Manhattan

stopped work on the project due to non-payment and subsequently filed suit asserting

claims for breach of the construction contract against Mid Atlanta and foreclosure of

the lien against 182 Tenth’s property. Prior to trial, Manhattan obtained an order

granting partial summary judgment establishing that it was entitled at that time to

recover $2,729,652.00 for amounts owed under the construction contract. After

applying credits for payments received under the contract, Manhattan subsequently

obtained a default judgment against Mid Atlanta for $4,886,606.00 which included

the sum of $2,126,148.00 for unpaid amounts due under the contract.

1. 182 Tenth claims that the trial court erred in denying its motion for a

directed verdict made after the close of the evidence.

In support of the lien foreclosure claim, Manhattan produced testimony from

its project manager, along with documentation of the unpaid items, showing that

Manhattan submitted payment applications for labor, services, and materials

furnished to improve the property pursuant to the contract with Mid Atlanta; that 182

Tenth consented to and made payments on the contract under which items were

furnished; and that Manhattan was owed $2,126,148.00 for unpaid items furnished

under the contract to improve 182 Tenth’s property. Manhattan also introduced

2 evidence of its default judgment against Mid Atlanta. After the testimony and

documents were admitted without objection, 182 Tenth cross-examined the project

manager about the furnished items for the purpose of questioning whether the unpaid

sums owed to Manhattan under the contract represented lienable items under OCGA

§ 44-14-361 or non-lienable items. When Manhattan concluded its case, 182 Tenth

rested without presenting any evidence and moved for a directed verdict. While

conceding that Manhattan presented evidence of lienable claims against the property,

182 Tenth argued that it was entitled to a directed verdict because Manhattan failed

to produce evidence separating lienable and non-lienable items due under the

contract, so that “there is nothing in the record at this point that has given the jury any

amount of expenses that are lienable on the property of 182 Tenth.” The trial court

denied the motion. We find no error. “[A] directed verdict is appropriate only if there

is no conflict in the evidence as to any material issue and the evidence introduced,

construed most favorably to the party opposing the motion, demands a particular

verdict.” St. Paul Mercury Ins. Co. v. Meeks, 270 Ga. 136, 137 (508 SE2d 646)

(1998); OCGA § 9-11-50 (a). Even if there was evidence of non-lienable items –

admitted without objection – along with evidence of lienable items, it was for the jury

3 to decide, under the court’s instructions, the amount of any lien that Manhattan was

entitled to foreclose on the property.

2. 182 Tenth contends that the trial court erred by instructing the jury that

Manhattan’s pre-trial judgment against Mid Atlanta for unpaid labor, services, or

materials furnished under the construction contract shifted the burden to 182 Tenth

to separate lienable from non-lienable items.

The trial court correctly instructed the jury that Manhattan had the burden to

prove by the preponderance of the evidence that it was entitled to foreclose the lien

on 182 Tenth’s property. The trial court then gave the following additional instruction

regarding the burden of proof:

In lien foreclosure cases, proof of rendition of a judgment in favor of a materialman, such as Manhattan, against a third party, such as [Mid Atlanta], is not conclusive against an owner; but it does establish, as an initial matter, that the materialman has a valid claim against the third party for the amount of the judgment. The burden is then on the owner, in this instance, 182 Tenth, to introduce evidence sufficient to rebut the correctness of the judgment. In other words, in a lien foreclosure proceeding, where a judgment has been obtained against a contracting party, the burden of separating items which are lienable from those which are non-lienable rests upon the property owner. Whether or not such evidence has been presented is a matter solely for your determination.

4 The portion of the above-quoted instruction placing on 182 Tenth “the burden

of separating items which are lienable from those which are non-lienable” was error.

182 Tenth had no burden to prove which items supporting Manhattan’s prior

judgment against Mid Atlanta were lienable or non-lienable under OCGA § 44-14-

361. As a condition precedent to foreclosing the lien on 182 Tenth’s property,

Manhattan obtained a judgment against Mid Atlanta for the underlying debt on the

construction contract. OCGA § 44-14-361.1 (a) (3); Stonepecker, Inc. v. Shepherd

Constr. Co., 188 Ga. App. 513, 514 (373 SE2d 295) (1988). The reason for the rule

is that 182 Tenth’s property should not be subjected to the statutory lien until

Manhattan obtained a judgment against Mid Atlanta establishing that Mid Atlanta

owed Manhattan the amount for which Manhattan sought to assert the lien. Tri-State

Culvert Mfg., Inc. v. Crum, 139 Ga. App. 448, 449 (228 SE2d 403) (1976). When

Manhattan obtained its default judgment against Mid Atlanta, this was an

adjudication of the items furnished and the amount due with respect to the

construction contract. Id. at 449-450. The judgment precluded Manhattan from

establishing in the lien foreclosure that 182 Tenth’s liability exceeded that of Mid

Atlanta or that details of the amounts owed under the contract differed from that

proved in the judgment against Mid Atlanta. Id. at 450. Although 182 Tenth was not

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson's Mill & Lumber Co. v. Holliday
134 S.E.2d 563 (Court of Appeals of Georgia, 1963)
D. H. Overmyer Warehouse Co. v. W. C. Caye & Co.
157 S.E.2d 68 (Court of Appeals of Georgia, 1967)
St. Paul Mercury Insurance v. Meeks
508 S.E.2d 646 (Supreme Court of Georgia, 1998)
Browning v. Gaster Lumber Co.
475 S.E.2d 576 (Supreme Court of Georgia, 1996)
Bowen v. Collins
217 S.E.2d 193 (Court of Appeals of Georgia, 1975)
Stonepecker, Inc. v. Shepherd Construction Co.
373 S.E.2d 295 (Court of Appeals of Georgia, 1988)
ALDWORTH CO., INC. v. England
637 S.E.2d 198 (Supreme Court of Georgia, 2006)
Sears, Roebuck & Co. v. Superior Rigging & Erecting Co.
170 S.E.2d 721 (Court of Appeals of Georgia, 1969)
Amador v. Thomas
578 S.E.2d 537 (Court of Appeals of Georgia, 2003)
Tri-State Culvert Manufacturing, Inc. v. Crum
228 S.E.2d 403 (Court of Appeals of Georgia, 1976)
Wier v. Wier
696 S.E.2d 658 (Supreme Court of Georgia, 2010)
Skandia Draperies Manufacturing Co. v. Augusta Innkeepers, Ltd.
277 S.E.2d 282 (Court of Appeals of Georgia, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
182 Tenth, LLC v. Manhattan Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/182-tenth-llc-v-manhattan-construction-company-gactapp-2012.