1800 OCOTILLO, LLC v. WLB Group, Inc.

176 P.3d 33, 217 Ariz. 465, 522 Ariz. Adv. Rep. 37, 2008 Ariz. App. LEXIS 9
CourtCourt of Appeals of Arizona
DecidedJanuary 29, 2008
Docket1 CA-CV 07-0037
StatusPublished
Cited by5 cases

This text of 176 P.3d 33 (1800 OCOTILLO, LLC v. WLB Group, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
1800 OCOTILLO, LLC v. WLB Group, Inc., 176 P.3d 33, 217 Ariz. 465, 522 Ariz. Adv. Rep. 37, 2008 Ariz. App. LEXIS 9 (Ark. Ct. App. 2008).

Opinion

*468 OPINION

TIMMER, Judge.

¶ 1 1800 Ocotillo, LLC (“Ocotillo”) appeals the trial court’s grant of partial summary-judgment in favor of The WLB Group, Inc. (“WLB”) and the trial court’s order limiting Ocotillo’s recoverable damages to the fees Ocotillo has already paid to WLB. We must decide whether Arizona’s public policy prohibits enforcement of a contractual provision that limits the liability of a design professional for its sole negligence and, if not, whether a jury must always decide the enforceability of such a provision pursuant to Article 18, Section 5, of the Arizona Constitution. For the reasons that follow, we conclude that public policy does not prohibit the enforcement of such provisions and that enforceability must be decided by a jury. We therefore reverse the partial summary judgment and remand for additional proceedings.

BACKGROUND 1

¶ 2 Ocotillo is a real estate developer who, in 1998, commenced development of a townhouse project in Phoenix on property bounded on one side by the Arizona Canal. In November of that year, Ocotillo agreed to pay WLB $26,970 in exchange for WLB’s provision of surveying, engineering, and landscape architecture services to the townhouse project. Ocotillo authorized its design-build contractor, Morris Building and Management, Inc. (“Morris Building”), to sign the contract with WLB. WLB sent the contract to Morris Building via facsimile and attached a page to the contract entitled “Standard Conditions.” Although the conditions were set forth in small print and were largely illegible, Morris Building separately signed the page evidencing its agreement to these terms, including the following limitation-of-liability provision:

7. Client agrees that the liability of WLB, its agents and employees, in connection with services hereunder to the Client and to all persons having contractual relationships with them, resulting from any negligent acts, errors, and/or omissions of WLB, its agents, and/or employees is limited to the total fees actually paid by the Client to WLB for services rendered by WLB hereunder.

The parties never discussed this provision prior to execution of the contract.

¶ 3 In January 2000, Ocotillo entered into a supplemental contract with WLB for provision of additional services in exchange for payment of $28,000 to WLB. The supplemental contract incorporated the 1998 contract. As before, the parties did not discuss a limitation-of-liability provision prior to execution of the supplemental contract.

¶ 4 Pursuant to the terms of the contract and supplemental contract (collectively, the “Contract”), WLB prepared a survey purportedly depicting the boundaries of the townhouse project property and all claimed rights-of-way affecting the property. This survey, however, failed to accurately identify an existing right-of-way owned by Salt River Project and Salt River Valley Water Users Association (collectively, “SRP”), the entity charged with managing the Arizona Canal. WLB prepared improvement drawings and a final plat based on this erroneous survey. After SRP disputed the final plat due to the inaccurate depiction of its right-of-way, the City of Phoenix refused to issue needed construction permits. Moreover, after SRP’s right-of-way was properly identified, Ocotillo was required to procure a redesigned site layout and property improvements from other engineering and survey firms.

¶ 5 In December 2000, Ocotillo sued WLB for breach of contract and professional negligence and asserted entitlement to any surety bond or insurance WLB possessed. 2 WLB counterclaimed for unpaid fees and sought a declaratory judgment regarding the enforceability of the limitation-of-liability provision set forth in the Contract.

*469 ¶ 6 In July 2002, the trial court granted partial summary judgment for WLB on Oco-tillo’s breaeh-of-contract claim and additionally ruled that the limitation-of-liability provision in the Contract was unenforceable as against public policy. After WLB filed a second motion for partial summary judgment in March 2004 regarding the validity of the limitation-of-liability provision, the court reconsidered its prior ruling and decided the provision was enforceable. Finally, in November 2006, after WLB filed a third motion for partial summary judgment, the court entered judgment pursuant to Arizona Rule of Civil Procedure (“ARCP”) 54(b), declaring that the limitation-of-liability provision was enforceable and that any damages due to Ocotillo for professional negligence were capped at $14,242, the amount Ocotillo actually paid to WLB under the Contract. This timely appeal followed.

DISCUSSION

¶ 7 Summary judgment is appropriate when “there is no genuine issue as to any material fact and ... the moving party is entitled to a judgment as a matter of law.” ARCP 56(c). Summary judgment should be granted “if the facts produced in support of the claim or defense have so little probative value, given the quantum of evidence required, that reasonable people could not agree with the conclusion advanced by the proponent of the claim or defense.” Orme Sch. v. Reeves, 166 Ariz. 301, 309, 802 P.2d 1000, 1008 (1990). For a claim or defense to withstand a motion for summary judgment, the proponent of the claim or defense must present evidence “from which a reasonable jury could find, directly or by inference, that the probabilities favored the proponent.” Id. at 310, 802 P.2d at 1009. If the evidence would allow a jury to resolve a material issue in favor of either party, summary judgment is improper. United Bank of Ariz. v. Allyn, 167 Ariz. 191, 195, 805 P.2d 1012, 1016 (App.1990). We determine de novo whether genuine issues of material fact exist and whether the trial court erred in its application of the law. Unique Equip. Co. v. TRW Vehicle Safety Sys., Inc., 197 Ariz. 50, 52, ¶ 5, 3 P.3d 970, 972 (App.1999).

¶ 8 Ocotillo argues the trial court erred by entering partial summary judgment in favor of WLB because (1) the limitation-of-liability provision is void as against public policy, (2) alternatively, the enforceability of the provision is an issue of fact that must be submitted to the jury, and (3) even assuming the provision is valid as a matter of law, the court erred by capping the damage award against WLB at $14,242.

I. Public policy

¶ 9 Ocotillo acknowledges that in appropriate circumstances, limitation-of-liability provisions in commercial contracts are enforceable. See Salt River Project Agric. Improvement & Power Dist. v. Westinghouse Elec. Corp., 143 Ariz. 368, 385, 694 P.2d 198, 215 (1984) (“SRP v. Westinghouse ”) (reversing summary judgment in products liability action as fact issues existed regarding enforceability of limitation-of-liability provision),

Free access — add to your briefcase to read the full text and ask questions with AI

Related

1800 OCOTILLO, LLC v. WLB Group, Inc.
196 P.3d 222 (Arizona Supreme Court, 2008)
McEver v. Planners & Engineers Collaborative, Inc.
663 S.E.2d 240 (Supreme Court of Georgia, 2008)
Highland Village Partners, LLC v. BRADBURY & STAMM CONSTRUCTION CO.
195 P.3d 184 (Court of Appeals of Arizona, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
176 P.3d 33, 217 Ariz. 465, 522 Ariz. Adv. Rep. 37, 2008 Ariz. App. LEXIS 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/1800-ocotillo-llc-v-wlb-group-inc-arizctapp-2008.