15th Place Condominium Association v. South Campus Development Team, LLC

2014 IL App (1st) 122292, 14 N.E.3d 592
CourtAppellate Court of Illinois
DecidedJune 26, 2014
Docket1-12-2292, 1-12-2301cons.
StatusUnpublished
Cited by7 cases

This text of 2014 IL App (1st) 122292 (15th Place Condominium Association v. South Campus Development Team, LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
15th Place Condominium Association v. South Campus Development Team, LLC, 2014 IL App (1st) 122292, 14 N.E.3d 592 (Ill. Ct. App. 2014).

Opinion

2014 IL App (1st) 122292

Nos. 1-12-2292 and 1-12-2301, Consolidated

Opinion filed June 26, 2014

FOURTH DIVISION ______________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

FIRST DISTRICT ______________________________________________________________________________

15TH PLACE CONDOMINIUM ASSOCIATION, ) Appeal from the ) Circuit Court of Plaintiff-Appellant, ) Cook County. ) v. ) ) SOUTH CAMPUS DEVELOPMENT TEAM, ) LLC, ) ) Defendant and ) Third-Party Plaintiff- ) Appellant ) ) No. 08 L 9839 ) (FITZGERALD ASSOCIATES ) ARCHITECTS P.C., and ) LINN-MATHES, INC., ) ) Honorable Third-Party Defendants- ) Raymond W. Mitchell, Appellees). ) Judge Presiding.

PRESIDING JUSTICE HOWSE delivered the judgment of the court, with opinion. Justices McBride and Palmer concurred in the judgment and opinion.

OPINION

¶1 In this case, third-party plaintiff-appellant South Campus Development Team (SCDT)

appeals the trial court's order that dismissed with prejudice its third-party claims against third- 1-12-2292) 1-12-2301)Cons.

party defendants Fitzgerald Associates Architects P.C. (Fitzgerald) and Linn-Mathes, Inc. (Linn-

Mathes), on the grounds that the claims are time-barred. The third-party complaint contains

claims of breach of contract, breach of the implied warranty of good workmanship, implied

indemnity and express indemnity. The implied warranty of good workmanship and the express

indemnity claims are only applicable to Linn-Mathes. In order to make a ruling in this appeal,

we must determine three issues: (1) whether a cause of action accrual provision is enforceable to

bar a third-party complaint against one of the contracting parties; (2) whether the trial court

improperly resolved a disputed issue of fact when it ruled on a motion to dismiss; and (3)

whether the 4-year limitations period applicable to construction-related activities (735 ILCS

5/13-214(a) (West 2008)) or the 10-year statute of limitations period applicable to written

contracts (735 ILCS 5/13-206 (West 2008)) applies to a general contractor's written promise to

indemnify an owner against claims of defects in construction.

¶2 For the reasons that follow, we affirm that part of the trial court's order enforcing the

accrual agreements and dismissing the breach of contract and implied indemnity claims as time-

barred. We reverse the trial court's judgment dismissing the express indemnity claim against

Linn-Mathes and remand this case for further proceedings on that claim because we find the 10-

year limitations period for written contracts is applicable.

¶3 I. BACKGROUND

¶4 A. The Underlying Cause of Action

¶5 SCDT was the developer of two adjacent condominium towers located at 811 and 833

West 15th Place in Chicago, Illinois (the project). SCDT contracted with Fitzgerald for

2 1-12-2292) 1-12-2301)Cons.

architectural services and with Linn-Mathes to be the general contractor for the project. Both

contracts contain a cause of action accrual provision which states that all causes of action against

Fitzgerald and Linn-Mathes are to accrue when substantial completion of the project is achieved.

The terms of both contracts state how the date of substantial completion is determined.

¶6 The SCDT/Fitzgerald contract provides that Fitzgerald as the architect is to have the sole

and exclusive responsibility to determine the date of substantial completion. Section 2.6.12 of

the SCDT/Fitzgerald contract states:

"The Architect shall make site visits to determine the date

or dates of Substantial Completion and the date of final

completion, and may issue a final Certificate for Payment upon

compliance with the requirements of the Contract Documents."

¶7 Similarly, section 4.2.9 of the SCDT/Linn-Mathes contract contains the following

provisions relating to dates of substantial completion:

"The Architect will conduct inspections to determine the

date or dates of Substantial completion and the date of final

completion, will receive and forward to the Owner, for the Owner's

review and records, written warranties and related documents

require [sic] by the Contract and assembled by the Contractor, and

will issue a final Certificate for Payment upon compliance with the

requirements of the Contract Documents."

3 1-12-2292) 1-12-2301)Cons.

Further, section 9.8.4 the SCDT/Linn-Mathes contract states: "When the Work or designated

portion thereof is substantially complete, the Architect will prepare a Certificate of Substantial

completion which shall establish the date of Substantial completion[]***." The SCDT/Linn-

Mathes contract defines substantial completion in section 9.8.1 as follows:

"Substantial Completion is the stage in the progress of the

Work when the Work or designated portion thereof is sufficiently

complete in accordance with the Contract Documents so that the

Owner can occupy or Utilize the Work for its intended use."

¶8 In April 2005, after a number of condominium units were sold, SCDT turned over control

of the condominiums to its owners and the 15th Place Condominium Association (the

Association). Following the turnover, the board of directors of the Association discovered

numerous design and workmanship defects related to the balconies, masonry, and garage. The

Association hired an engineering company that confirmed the presence of design and

workmanship defects, and the Association filed a lawsuit against SCDT on September 4, 2008.

The complaint included claims of breach of the implied warranty of fitness and habitability,

breach of fiduciary duty, and negligence. The complaint alleged that SCDT knew or should have

known that the defects existed; SCDT failed to have any of the defects fixed; and SCDT failed to

disclose the defects to buyers.

¶9 B. Third-Party Action

4 1-12-2292) 1-12-2301)Cons.

¶ 10 On March 9, 2009, SCDT entered into a written tolling agreement with Fitzgerald and

Linn-Mathes that tolled "any and all claims or causes of action" between the parties that "had not

expired as of the date of this [tolling] Agreement."

¶ 11 On June 21, 2011, SCDT filed a third-party complaint against Fitzgerald and Linn-

Mathes. The third-party complaint alleged claims for breach of contract and, alternatively,

implied indemnity against Fitzgerald, and claims for breach of contract, breach of implied

warranty of good workmanship, express indemnity and, alternatively, implied indemnity against

Linn-Mathes.

¶ 12 C. Motions to Dismiss

¶ 13 On July 27, 2011, Fitzgerald filed a motion to dismiss the third-party complaint pursuant

to section 2-619.1 of the Code of Civil Procedure (the Code) (735 ILCS 5/2-619.1 (West 2008)).

In its motion, Fitzgerald argued that SCDT's third-party complaint was time-barred or, in the

alternative, SCDT's implied indemnity claim had to be dismissed for failing to state a cause of

action pursuant to section 2-615 of the Code. 735 ILCS 5/2-615 (West 2008). Fitzgerald argued

in the motion that all causes of action SCDT had against it accrued on the date of substantial

completion, which occurred on May 16, 2003 for the first tower and on October 11, 2004 for the

second tower.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2014 IL App (1st) 122292, 14 N.E.3d 592, Counsel Stack Legal Research, https://law.counselstack.com/opinion/15th-place-condominium-association-v-south-campus-development-team-llc-illappct-2014.