15th Place Condominium Association v. South Campus Development Team, LLC

2014 IL App (1st) 122292, 14 N.E.3d 592
Appellate Court of Illinois·Decided June 26, 2014·No. 1-12-2292, 1-12-2301cons.·Unpublished·Cited by 7 cases

Opinion

2014 IL App (1st) 122292

Nos. 1-12-2292 and 1-12-2301, Consolidated Opinion filed June 26, 2014

FOURTH DIVISION

IN THE

APPELLATE COURT OF ILLINOIS

FIRST DISTRICT

15TH PLACE CONDOMINIUM ASSOCIATION, ) Appeal from the ) Circuit Court of Plaintiff-Appellant, ) Cook County.

)

v. )

)

SOUTH CAMPUS DEVELOPMENT TEAM, ) LLC, )

)

Defendant and )

Third-Party Plaintiff- )

Appellant )

) No. 08 L 9839 )

(FITZGERALD ASSOCIATES ) ARCHITECTS P.C., and ) LINN-MATHES, INC., )

) Honorable Third-Party Defendants- ) Raymond W. Mitchell, Appellees). ) Judge Presiding.

PRESIDING JUSTICE HOWSE delivered the judgment of the court, with opinion.

Justices McBride and Palmer concurred in the judgment and opinion.

OPINION

¶1 In this case, third-party plaintiff-appellant South Campus Development Team (SCDT) appeals the trial court's order that dismissed with prejudice its third-party claims against third-

1-12-2301)Cons. party defendants Fitzgerald Associates Architects P.C. (Fitzgerald) and Linn-Mathes, Inc. (Linn- Mathes), on the grounds that the claims are time-barred. The third-party complaint contains claims of breach of contract, breach of the implied warranty of good workmanship, implied indemnity and express indemnity. The implied warranty of good workmanship and the express indemnity claims are only applicable to Linn-Mathes. In order to make a ruling in this appeal, we must determine three issues: (1) whether a cause of action accrual provision is enforceable to bar a third-party complaint against one of the contracting parties; (2) whether the trial court improperly resolved a disputed issue of fact when it ruled on a motion to dismiss; and (3) whether the 4-year limitations period applicable to construction-related activities (735 ILCS 5/13-214(a) (West 2008)) or the 10-year statute of limitations period applicable to written contracts (735 ILCS 5/13-206 (West 2008)) applies to a general contractor's written promise to indemnify an owner against claims of defects in construction.

¶2 For the reasons that follow, we affirm that part of the trial court's order enforcing the accrual agreements and dismissing the breach of contract and implied indemnity claims as time- barred. We reverse the trial court's judgment dismissing the express indemnity claim against Linn-Mathes and remand this case for further proceedings on that claim because we find the 10- year limitations period for written contracts is applicable.

¶3 I. BACKGROUND

¶4 A. The Underlying Cause of Action

¶5 SCDT was the developer of two adjacent condominium towers located at 811 and 833 West 15th Place in Chicago, Illinois (the project). SCDT contracted with Fitzgerald for

1-12-2301)Cons. architectural services and with Linn-Mathes to be the general contractor for the project. Both contracts contain a cause of action accrual provision which states that all causes of action against Fitzgerald and Linn-Mathes are to accrue when substantial completion of the project is achieved. The terms of both contracts state how the date of substantial completion is determined.

¶6 The SCDT/Fitzgerald contract provides that Fitzgerald as the architect is to have the sole and exclusive responsibility to determine the date of substantial completion. Section 2.6.12 of the SCDT/Fitzgerald contract states:

"The Architect shall make site visits to determine the date or dates of Substantial Completion and the date of final completion, and may issue a final Certificate for Payment upon compliance with the requirements of the Contract Documents."

¶7 Similarly, section 4.2.9 of the SCDT/Linn-Mathes contract contains the following provisions relating to dates of substantial completion:

"The Architect will conduct inspections to determine the date or dates of Substantial completion and the date of final completion, will receive and forward to the Owner, for the Owner's review and records, written warranties and related documents require [sic] by the Contract and assembled by the Contractor, and will issue a final Certificate for Payment upon compliance with the requirements of the Contract Documents."

1-12-2301)Cons. Further, section 9.8.4 the SCDT/Linn-Mathes contract states: "When the Work or designated portion thereof is substantially complete, the Architect will prepare a Certificate of Substantial completion which shall establish the date of Substantial completion[]***." The SCDT/Linn- Mathes contract defines substantial completion in section 9.8.1 as follows:

"Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or Utilize the Work for its intended use."

¶8 In April 2005, after a number of condominium units were sold, SCDT turned over control of the condominiums to its owners and the 15th Place Condominium Association (the Association). Following the turnover, the board of directors of the Association discovered numerous design and workmanship defects related to the balconies, masonry, and garage. The Association hired an engineering company that confirmed the presence of design and workmanship defects, and the Association filed a lawsuit against SCDT on September 4, 2008. The complaint included claims of breach of the implied warranty of fitness and habitability, breach of fiduciary duty, and negligence. The complaint alleged that SCDT knew or should have known that the defects existed; SCDT failed to have any of the defects fixed; and SCDT failed to disclose the defects to buyers.

¶9 B. Third-Party Action

1-12-2301)Cons.

¶ 10 On March 9, 2009, SCDT entered into a written tolling agreement with Fitzgerald and Linn-Mathes that tolled "any and all claims or causes of action" between the parties that "had not expired as of the date of this [tolling] Agreement."

¶ 11 On June 21, 2011, SCDT filed a third-party complaint against Fitzgerald and Linn- Mathes. The third-party complaint alleged claims for breach of contract and, alternatively, implied indemnity against Fitzgerald, and claims for breach of contract, breach of implied warranty of good workmanship, express indemnity and, alternatively, implied indemnity against Linn-Mathes.

¶ 12 C. Motions to Dismiss

¶ 13 On July 27, 2011, Fitzgerald filed a motion to dismiss the third-party complaint pursuant to section 2-619.1 of the Code of Civil Procedure (the Code) (735 ILCS 5/2-619.1 (West 2008)). In its motion, Fitzgerald argued that SCDT's third-party complaint was time-barred or, in the alternative, SCDT's implied indemnity claim had to be dismissed for failing to state a cause of action pursuant to section 2-615 of the Code. 735 ILCS 5/2-615 (West 2008). Fitzgerald argued in the motion that all causes of action SCDT had against it accrued on the date of substantial completion, which occurred on May 16, 2003 for the first tower and on October 11, 2004 for the second tower. Applying those accrual dates to the four-year statute of limitations applicable to construction-related activity (735 ILCS 5/13-214(a) (West 2008)), Fitzgerald argued that SCDT's claims against it were time-barred because Fitzgerald and SCDT did not enter into the tolling agreement until March 9, 2009, which was more than four years following the latest possible date on which substantial completion could have occurred, October 11, 2004. Fitzgerald

1-12-2301)Cons. attached to its motion to dismiss an affidavit of Michael DeRouin, president of Fitzgerald and project manager of Fitzgerald at the time of the development project, stating that substantial completion had occurred on May 16, 2003 and October 11, 2004. The affidavit incorporated a letter and a certificate of substantial completion, which indicated the same dates of substantial completion, May 16, 2003 and October 11, 2004, respectively.

Free access — add to your briefcase to read the full text and ask questions with AI

15th Place Condominium Association v. South Campus Development Team, LLC, 2014 IL App (1st) 122292, 14 N.E.3d 592 (Ill. Ct. App. 2014).

2014 IL App (1st) 122292 (15th Place Condominium Association v. South Campus Development Team, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related