15th Place Condominium Association v. South Campus Development Team, LLC

2014 IL App (1st) 122292
CourtAppellate Court of Illinois
DecidedAugust 28, 2014
Docket1-12-2292, 1-12-2301 cons.
StatusPublished
Cited by7 cases

This text of 2014 IL App (1st) 122292 (15th Place Condominium Association v. South Campus Development Team, LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
15th Place Condominium Association v. South Campus Development Team, LLC, 2014 IL App (1st) 122292 (Ill. Ct. App. 2014).

Opinion

Illinois Official Reports

Appellate Court

15th Place Condominium Ass’n v. South Campus Development Team, LLC, 2014 IL App (1st) 122292

Appellate Court 15TH PLACE CONDOMINIUM ASSOCIATION, Plaintiff- Caption Appellant, v. SOUTH CAMPUS DEVELOPMENT TEAM, LLC, Defendant and Third-Party Plaintiff-Appellant (Fitzgerald Associates Architects P.C., and Linn-Mathes, Inc., Third-Party Defendants- Appellees).

District & No. First District, Fourth Division Docket Nos. 1-12-2292, 1-12-2301 cons.

Filed June 26, 2014

Held In an action by a condominium association against the developer of (Note: This syllabus the project based on defects in the construction, the trial court properly constitutes no part of the dismissed the developer’s third-party claims against the architect and opinion of the court but the general contractor for breach of contract, breach of the implied has been prepared by the warranty of good workmanship and implied indemnity on the ground Reporter of Decisions that those claims were time-barred pursuant to the contract accrual for the convenience of provision under which all causes of action were to accrue on the date the reader.) of substantial completion of the project, since the actions at issue were filed beyond the expiration of the four-year limitations period calculated from the dates of completion as determined according to the contract; however, because the claim against the contractor for express indemnity was based on the failure to indemnify, not for any construction activities, the contract’s accrual provision did not apply, and pursuant to the 10-year limitations period applicable to written contracts, that part of the claim was timely, the dismissal thereof was reversed and the cause was remanded for further proceedings.

Decision Under Appeal from the Circuit Court of Cook County, No. 08-L-9839; the Review Hon. Raymond W. Mitchell, Judge, presiding.

Judgment Affirmed in part and reversed in part; cause remanded. Counsel on Michael J. Delrahim, Shelley Smith, and Glenn M. Kanter, all of Appeal Brown, Udell, Pomerantz & Delrahim, Ltd., of Chicago, for appellant South Campus Development Team, LLC.

Thomas B. Orlando, Douglas J. Palandech, and Michael A. Kuiken, all of Foran Glennon Palandech Ponzi & Rudloff PC, of Chicago, for appellee Fitzgerald Associates Architects P.C.

Jeffrey H. Winick and Jeffrey B. Charkow, both of Harris|Winick LLP, of Chicago, for appellee Linn-Mathes, Inc.

Panel PRESIDING JUSTICE HOWSE delivered the judgment of the court, with opinion. Justices McBride and Palmer concurred in the judgment and opinion.

OPINION

¶1 In this case, third-party plaintiff-appellant South Campus Development Team (SCDT) appeals the trial court’s order that dismissed with prejudice its third-party claims against third-party defendants Fitzgerald Associates Architects P.C. (Fitzgerald) and Linn-Mathes, Inc. (Linn-Mathes), on the grounds that the claims are time-barred. The third-party complaint contains claims of breach of contract, breach of the implied warranty of good workmanship, implied indemnity and express indemnity. The implied warranty of good workmanship and the express indemnity claims are only applicable to Linn-Mathes. In order to make a ruling in this appeal, we must determine three issues: (1) whether a cause of action accrual provision is enforceable to bar a third-party complaint against one of the contracting parties; (2) whether the trial court improperly resolved a disputed issue of fact when it ruled on a motion to dismiss; and (3) whether the 4-year limitations period applicable to construction-related activities (735 ILCS 5/13-214(a) (West 2008)) or the 10-year statute of limitations period applicable to written contracts (735 ILCS 5/13-206 (West 2008)) applies to a general contractor’s written promise to indemnify an owner against claims of defects in construction. ¶2 For the reasons that follow, we affirm that part of the trial court’s order enforcing the accrual agreements and dismissing the breach of contract and implied indemnity claims as time-barred. We reverse the trial court’s judgment dismissing the express indemnity claim against Linn-Mathes and remand this case for further proceedings on that claim because we find the 10-year limitations period for written contracts is applicable.

¶3 I. BACKGROUND ¶4 A. The Underlying Cause of Action ¶5 SCDT was the developer of two adjacent condominium towers located at 811 and 833 West 15th Place in Chicago, Illinois (the project). SCDT contracted with Fitzgerald for

-2- architectural services and with Linn-Mathes to be the general contractor for the project. Both contracts contain a cause of action accrual provision which states that all causes of action against Fitzgerald and Linn-Mathes are to accrue when substantial completion of the project is achieved. The terms of both contracts state how the date of substantial completion is determined. ¶6 The SCDT/Fitzgerald contract provides that Fitzgerald as the architect is to have the sole and exclusive responsibility to determine the date of substantial completion. Section 2.6.12 of the SCDT/Fitzgerald contract states: “The Architect shall make site visits to determine the date or dates of Substantial Completion and the date of final completion, and may issue a final Certificate for Payment upon compliance with the requirements of the Contract Documents.” ¶7 Similarly, section 4.2.9 of the SCDT/Linn-Mathes contract contains the following provisions relating to dates of substantial completion: “The Architect will conduct inspections to determine the date or dates of Substantial completion and the date of final completion, will receive and forward to the Owner, for the Owner’s review and records, written warranties and related documents require [sic] by the Contract and assembled by the Contractor, and will issue a final Certificate for Payment upon compliance with the requirements of the Contract Documents.” Further, section 9.8.4 of the SCDT/Linn-Mathes contract states: “When the Work or designated portion thereof is substantially complete, the Architect will prepare a Certificate of Substantial completion which shall establish the date of Substantial completion[ ] ***.” The SCDT/Linn-Mathes contract defines substantial completion in section 9.8.1 as follows: “Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or Utilize the Work for its intended use.” In April 2005, after a number of condominium units were sold, SCDT turned over control of the condominiums to its owners and the 15th Place Condominium Association (the Association). Following the turnover, the board of directors of the Association discovered numerous design and workmanship defects related to the balconies, masonry, and garage. The Association hired an engineering company that confirmed the presence of design and workmanship defects, and the Association filed a lawsuit against SCDT on September 4, 2008. The complaint included claims of breach of the implied warranty of fitness and habitability, breach of fiduciary duty, and negligence. The complaint alleged that SCDT knew or should have known that the defects existed; SCDT failed to have any of the defects fixed; and SCDT failed to disclose the defects to buyers.

¶8 B. Third-Party Action ¶9 On March 9, 2009, SCDT entered into a written tolling agreement with Fitzgerald and Linn-Mathes that tolled “any and all claims or causes of action” between the parties that “had not expired as of the date of this [tolling] Agreement.” ¶ 10 On June 21, 2011, SCDT filed a third-party complaint against Fitzgerald and Linn-Mathes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monroy-Perez v. Sentry Select Insurance Co.
2025 IL App (1st) 241711 (Appellate Court of Illinois, 2025)
M&S Industrial Co., Inc. v. Allahverdi
2018 IL App (1st) 172028 (Appellate Court of Illinois, 2018)
933 Van Buren Condominium Assoc. v. West Van Buren, LLC
2016 IL App (1st) 143490 (Appellate Court of Illinois, 2016)
15th Place Condominium Association v. South Campus Development Team, LLC
2014 IL App (1st) 122292 (Appellate Court of Illinois, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2014 IL App (1st) 122292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/15th-place-condominium-association-v-south-campus--illappct-2014.