§ 624.9 Time limits.
Funds must be obligated by the State Conservationist and construction completed within 220 calendar days after the date funds are committed to the State Conservationist, except for exigency situations in which case the construction must be completed within 10 days after the date the funds are committed.
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
8
§ 624.4
Definitions.§ 624.5
Coordination.§ 624.6
Program administration.§ 624.7
Cost-sharing.§ 624.8
Assistance.§ 624.9
Time limits.§ 624.10
Floodplain easements.§ 624.11
Waivers.Cite This Page — Counsel Stack
Bluebook (online)
7 C.F.R. § 624.9, Counsel Stack Legal Research, https://law.counselstack.com/cfr/7/624/624.9.