970.4207-501 Contracting officer determination procedure.
(b)(4) A contracting officer shall not resolve any questioned costs until the contracting officer has obtained—
(i)Adequate documentation with respect to such costs; and
(ii)The opinion of the Department of Energy's auditor on the allowability of such costs if such costs have been the subject of a DOE audit.
(5)The contracting officer shall ensure that the documentation supporting the final settlement addresses the amount of the questioned costs and the subsequent disposition of such questioned costs.
(6)The contracting officer shall ensure, to the maximum extent practicable, that the Department of Energy's auditor is afforded an opportunity to attend any negotiation or meeting with the contractor regarding a determination o
Free access — add to your briefcase to read the full text and ask questions with AI
48 C.F.R. § 970.4207-501 (Contracting officer determination procedure.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
11
§ 970.3770-2
970.3770-2 [Reserved]§ 970.4102
Acquiring utility services.§ 970.4102-1
Policy.§ 970.4207-302
Certificate of costs.§ 970.4207-370
Contract clause.§ 970.4207-501
Contracting officer determination procedure.§ 970.4302
Changes.§ 970.4302-1
Contract clause.§ 970.4400
Scope.§ 970.4401
Responsibilities.§ 970.4401-1
General.