48 CFR · Federal Acquisition Regulations System
§ 252.237-7014 — Loss or damage (count-of-articles).
eCFR · current through Sep 1, 2026
252.237-7014 Loss or damage (count-of-articles). As prescribed in 237.7101(c), use the following clause: Loss or Damage (Count-of-Articles) (DEC 1991)
(a)The count-of-articles will be—
(1)The count of the Contracting Officer; or
(2)The count agreed upon as a result of a joint count by the Contractor and the Contracting Officer at the time of delivery to the Contractor.
(b)The Contractor shall—
(1)Be liable for return of the number and kind of articles furnished for service under this contract; and
(2)Shall indemnify the Government for any loss or damage to such articles.
(c)The Contractor shall pay to the Government the value of any lost or damaged property using Federal supply schedule price lists. If the property is not on these price lists, the Contracting Officer shall d
Free access — add to your briefcase to read the full text and ask questions with AI
48 C.F.R. § 252.237-7014 (Loss or damage (count-of-articles).) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
11
§ 252.237-7009
Permits.§ 252.237-7011
Preparation history.§ 252.237-7012
Instruction to offerors (count-of-articles).§ 252.237-7013
Instruction to offerors (bulk weight).§ 252.237-7014
Loss or damage (count-of-articles).§ 252.237-7015
Loss or damage (weight of articles).§ 252.237-7016
Delivery tickets.§ 252.237-7017
Individual laundry.§ 252.237-7018
Special definitions of Government property.