§ 252.236-7003 — Payment for mobilization and preparatory work.
eCFR · current through Sep 1, 2026
252.236-7003 Payment for mobilization and preparatory work. As prescribed in 236.570(b)(2), use the following clause: Payment for Mobilization and Preparatory Work (JAN 1997)
(a)The Government will make payment to the Contractor under the procedures in this clause for mobilization and preparatory work under item no. __________.
(b)Payments will be made for actual payments by the Contractor on work preparatory to commencing actual work on the construction items for which payment is provided under the terms of this contract, as follows—
(1)For construction plant and equipment exceeding $25,000 in value per unit (as appraised by the Contracting Officer at the work site) acquired for the execution of the work;
(2)Transportation of all plant and equipment to the site;
(3)Material pur
Free access — add to your briefcase to read the full text and ask questions with AI
48 C.F.R. § 252.236-7003 (Payment for mobilization and preparatory work.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
11
§ 252.235-7010
Acknowledgment of support and disclaimer.§ 252.235-7011
Final scientific or technical report.§ 252.236-7000
Modification proposals—price breakdown.§ 252.236-7001
Contract drawings and specifications.§ 252.236-7002
Obstruction of navigable waterways.§ 252.236-7003
Payment for mobilization and preparatory work.§ 252.236-7004
Payment for mobilization and demobilization.§ 252.236-7005
Airfield safety precautions.§ 252.236-7006
Cost limitation.§ 252.236-7007
Additive or deductive items.§ 252.236-7008
Contract prices—bidding schedules.