§ 243.204-70-5 — Exceptions.
eCFR · current through Aug 7, 2026
243.204-70-5 Exceptions.
(a)The limitations in 243.204-70-2, 243.204-70-3, and 243.204-70-4 do not apply to unpriced change orders for the purchase of initial spares.
(b)The limitations in 243.204-70-4(a) do not apply to unpriced change orders for ship construction and ship repair.
(c)The head of the agency may waive the limitations in 243.204-70-2, 243.204-70-3, and 243.204-70-4 for unpriced change orders if the head of the agency determines that the waiver is necessary to support—
(1)A contingency operation; or
(2)A humanitarian or peacekeeping operation.
[75 FR 48277, Aug. 10, 2010]
Free access — add to your briefcase to read the full text and ask questions with AI
48 C.F.R. § 243.204-70-5 (Exceptions.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
11
§ 243.204-70
Definitization of change orders.§ 243.204-70-1
Scope.§ 243.204-70-2
Price ceiling.§ 243.204-70-3
Definitization schedule.§ 243.204-70-4
Limitations on obligations.§ 243.204-70-5
Exceptions.§ 243.204-70-6
Allowable profit.§ 243.204-70-7
Plans and reports.§ 243.205
Contract clauses.§ 243.205-70
Pricing of contract modifications.