This text of 48 C.F.R. § 1850.103-670 (Implementation of the Contract Adjustment Board's decision.) is published on Counsel Stack Legal Research, covering United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
48 C.F.R. § 1850.103-670 (2026).
Text
1850.103-670 Implementation of the Contract Adjustment Board's decision.
(a)The contracting officer shall take action authorized in the CAB's decision.
(b)Immediately upon execution, including any required Headquarters approval, of a contract or contract modification or amendment implementing the CAB decision, the contracting officer shall forward a copy of the contractual document to the Associate General Counsel for Contracts and Procurement Law.
[76 FR 72328, Nov. 23, 2011, as amended at 80 FR 36722, June 26, 2015]
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
11
§ 1850.102-2
Contract adjustment boards.§ 1850.103
Contract adjustments.§ 1850.103-5
Processing cases.§ 1850.103-570
Submission of request to the Contract Adjustment Board.§ 1850.103-6
Disposition.§ 1850.104
Residual powers.§ 1850.104-2
General.§ 1850.104-370
Subcontractor indemnification requests.§ 1850.104-4
Contract clause.Cite This Page — Counsel Stack