§ 333.14 Preferential scheduling.
(a)A person must schedule operations, including the acquisition of all needed production items, in a timely manner to satisfy the delivery requirements of each rated order. Modifying production or delivery schedules is necessary only when required delivery dates for rated orders cannot otherwise be met.
(b)DO rated orders must be given production preference over unrated orders, if necessary, to meet required delivery dates, even if this requires the diversion of items being processed or ready for delivery against unrated orders. Similarly, DX rated orders must be given preference over DO rated orders and unrated orders.
(1)Examples: If a person receives a DO rated order with a delivery date of June 3 and if meeting that date would mean delaying produc
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Nearby Sections
11
§ 333.8
Definitions.§ 333.10
Authority.§ 333.11
Priority ratings.§ 333.12
Elements of a rated order.§ 333.14
Preferential scheduling.§ 333.15
Extension of priority ratings.§ 333.17
Use of rated orders.Cite This Page — Counsel Stack
Bluebook (online)
44 C.F.R. § 333.14, Counsel Stack Legal Research, https://law.counselstack.com/cfr/44/333/333.14.