§ 203.43 — Inspection of Federal flood control works.

33 CFR § 203.43

This text of 33 C.F.R. § 203.43 (Inspection of Federal flood control works.) is published on Counsel Stack Legal Research, covering United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
33 C.F.R. § 203.43 (2026).

Text

§ 203.43 Inspection of Federal flood control works.

(a)Required inspections. A completed Federal flood control project, or completed functional portions thereof, is granted Active status in the RIP upon transfer of the operation and maintenance of the project (or functional portion thereof) to the non-Federal sponsor. Federal flood control works will be periodically inspected in accordance with 33 CFR 208.10 and Engineer Regulation (ER) 1130-2-530, Flood Control Operations and Maintenance Policies. These periodic inspections of Federal flood control works are also, for simplicity, known as CEI's. If a Federal project is found to be inadequately maintained on a CEI, then it will be placed in an Inactive status in the RIP. [Note: This is a separate and distinct action from project deauthori

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 208.10
33 C.F.R. § 208.10

Nearby Sections

11

Cite This Page — Counsel Stack

Bluebook (online)
33 C.F.R. § 203.43, Counsel Stack Legal Research, https://law.counselstack.com/cfr/33/203/203.43.
View on eCFR ↗