§ 53.1452 Operation under a combined license.

(a)The licensee must notify the NRC of its scheduled date for initial loading of fuel no later than 270 days before the scheduled date and must notify the NRC of updates to its schedule every 30 days thereafter. 1 Not less than 180 days before the date scheduled for initial loading of fuel into a plant by a licensee that has been issued a COL under this part, the Commission must publish notice of intended operation in the Federal Register. 2 The notice must provide that any person whose interest may be affected by operation of the plant may, within 60 days, request that the Commission hold a hearing on whether the facility as constructed complies, or on completion will comply, with the acceptance criteria in the COL, except that a hearing mu

Free access — add to your briefcase to read the full text and ask questions with AI

10 C.F.R. § 53.1452 (Operation under a combined license.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

§ 53.1440
10 C.F.R. § 53.1440
§ 53.620
10 C.F.R. § 53.620
§ 2.309
10 C.F.R. § 2.309
§ 2.206
10 C.F.R. § 2.206
§ 53.1443
10 C.F.R. § 53.1443

Nearby Sections

11
View on eCFR ↗