§ 53.1030 — Annual adjustments to cost estimates for decommissioning.
eCFR · current through Jul 28, 2026
§ 53.1030 Annual adjustments to cost estimates for decommissioning. Each holder of an OL or COL under this part must annually adjust the cost estimate for decommissioning to account for escalation in labor, energy, and waste burial costs. Licensees may elect to use either a site-specific adjustment factor, approved as part of the plan and associated decommissioning report required by § 53.1010, in paragraph (a) of this section or the generic adjustment factor in paragraph (b) of this section.
(a)A site-specific adjustment factor must address the estimated contributions and escalation of costs for the following aspects of decommissioning:
(1)Labor, materials, and services;
(2)Energy and waste transportation; and
(3)Radioactive waste burial or other disposition.
(b)A generic adjust
Free access — add to your briefcase to read the full text and ask questions with AI
10 C.F.R. § 53.1030 (Annual adjustments to cost estimates for decommissioning.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
§ 53.1010
10 C.F.R. § 53.1010
Nearby Sections
11
§ 53.910
Procedures and guidelines.§ 53.1000
Scope and purpose.§ 53.1020
Cost estimates for decommissioning.§ 53.1050
NRC oversight.§ 53.1070
Termination of license.